Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Signature Global City 63A(2) | Village-Kadarpur, Sector-63A, Gurugram | GURUGRAM | Gurgaon | SIGNATUREGLOBAL (INDIA) LIMITED |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/619/351/2022/94 DATED 04.10.2022 | RERA-GRG-1132-2022 | 17-Aug-2022 | 17-Aug-2022 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Not Yet | -- | First Hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/619/351/2022/94 DATED 04.10.2022 | 01-Jun-2023 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
04-Oct-2022 | Proceedings dated 04.10.2022 : Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts about the case. Sh. Anurag Srivastav is present on the behalf of the promoter. Approved as proposed. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
27-Sep-2022 | Neeraj AAE (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e. (1). Confirmation from DTCP regarding unfreezing of earlier frozen plots (2). Service plan and estimates The matter is adjourned for 04.10.2022. | OBJECTION | View Order |
12-Sep-2022 | Proceedings dated 12.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts about the case. Sh. Anurag Srivastav is present on the behalf of the promoter. AR of the promoter requested for adjournment in the matter as the promoter may take 2 weeks’ time to rectify the defects in the application and to submit deficit documents. The matter to come up on 27.09.2022. | EXAMINATION BY AUTHORITY | View Order |
Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
---|---|---|---|---|---|---|
13-Sep-2022 | Proceedings dated 12.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts about the case. Sh. Anurag Srivastav is present on the behalf of the promoter. AR of the promoter requested for adjournment in the matter as the promoter may take 2 weeks’ time to rectify the defects in the application and to submit deficit documents. The matter to come up on 27.09.2022. | Not Yet |