13-Dec-2022 |
Sh. Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about the facts of the project. Sh. Sunjive Bhandari (CAO) and Sh. Aditya Mani Singh (Associate Liaison) are present on behalf of the promoter. Approved as proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
12-Dec-2022 |
The matter is adjourned to 13.12.2022 |
ADJOURNMENT |
View Order |
28-Nov-2022 |
The
authorized representative of the promoter is advised to rectify the
deficiencies and submit the deficit fee (if any) along with the deficit documents
apart from filing information in REP-I A to H format and online detailed
project information. Matter to come up
on 12.12.2022 (Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
View Order |
14-Nov-2022 |
Sh.
Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about the
facts of the project.
Sh.
Sunjive Bhandari (CAO) and Sh. Aditya Mani Singh (Associate Liaison) are
present on behalf of the promoter.
The
authority considered the application for registration of above mentioned real
estate project u/s 4 of the Act of 2016. The promoter is required to enclose
the requisite documents as provided in section 4(2) of the Act of 2016 and the
rules and regulations made thereunder. The deficiencies have already been
communicated as detailed above.
The
promoter is advised to rectify the deficiencies within 15 days otherwise the
Authority may proceed to initiate proceedings to reject the application u/s
5(1)(b) of Act of 2016 read with rule 5 of the Haryana Rules, 2017 for the
reason regarding deficiencies in the application and non-submission of
requisite documents.
The matter to come up
on 28.11.2022. (Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
View Order |
17-Oct-2022 |
Proceedings
dated: 17.10.2022
Sh.
Sumeet, Engineer Executive and Ms. Asha Chartered Accountant briefed about
the facts of the project.
None is present on behalf of the
promoter.
Deficiencies
have already been communicated. Promoter is advised to rectify the
deficiencies and submit deficient documents, as detailed above.
Further the AR of the promoter
has sent a request for adjournment of hearing for 3 weeks. The request is
allowed.
The matter to come
up on 14.11.2022.
(Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Vijay
Kumar Goyal)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
OBJECTION |
View Order |
03-Oct-2022 |
Proceedings
dated: 03.10.2022 : Sh.
Sumeet, Engineer Executive briefed about the facts of the project.
Sh.
Sanjive Bhandari (Chief Admn. Officer) and Sh. Aditya Mani Singh (Associate) are present on
behalf of the promoter.
Deficiencies have already been communicated.
Promoter is advised to rectify the deficiencies and submit deficient
documents, as detailed above.
The
matter to come up on 17.10.2022.
(Sanjeev
Kumar Arora)
Member, HARERA, Gurugram
(Ashok Sangwan)
Member, HARERA, Gurugram
(Dr. K.K. Khandelwal)
Chairman, HARERA, Gurugram
|
ADJOURNMENT |
View Order |
19-Sep-2022 |
Sh.
Sumeet, Engineer Executive briefed about the facts of the project.
Sh.
Sunjive Bhandari (Chief Admn. Officer) and Aditya Mani Singh (Associate) are
present on behalf of the promoter.
Deficiencies have already been
communicated. Promoter is advised to rectify the deficiencies and submit
deficient documents, as detailed above.
The
matter to come up on 03.10.2022. |
ADJOURNMENT |
View Order |
05-Sep-2022 |
Sh.
Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the
facts of the project.
Sh.
Aditya Mani Singh (Associate) is present on behalf of the promoter. The first
deficiencies notice has already been conveyed and the promoter has yet to
submit compliance. The AR seeks two weeks’ time for submission of the deficit
documents.
The matter to come up on
19.09.2022. |
EXAMINATION BY AUTHORITY |
View Order |