Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
GOLDEN PARK SECTOR 4, SOHNA GURUGRAM Sohna GOEL & SON'S DEVELOPERS PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/614/346/2022/89 DATED 03.10.2022 RERA-GRG-1099-2022 04-Aug-2022 26-Jul-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 18-Aug-2022 HARERA/GGM/RPIN/487 dispatched to AR
First Hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/614/346/2022/89 DATED 03.10.2022 21-Nov-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
03-Oct-2022 Proceedings dated 03.10.2022 : Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. Sh. Rajesh (VP) is present on behalf of the promoter. Approved as proposed.     (Sanjeev Kumar Arora) Member, HARERA, Gurugram     (Ashok Sangwan) Member, HARERA, Gurugram     (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
27-Sep-2022 Ar. Neeraj Gautam (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e.              (1).           Zoning Plan          (2.)         Approved service plan and estimates.                          The matter is adjourned for 11.10.2022.  OBJECTION View Order
12-Sep-2022 Proceedings dated 12.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. None is present on behalf of the promoter. One more opportunity is granted for rectifying the defects in the application for registration and submission of deficit documents.   The matter to come up on 27.09.2022. ADJOURNMENT View Order
29-Aug-2022 Proceedings dated 29.08.2022Ms. Geeta Rathee Singh, Sr. L.O. and Ar. Neeraj Gautam, Associate Architectural Executive briefed about thefacts of the case.Sh. Rajesh Kumar (VP) is present on the behalf of the promoter. The AR is advised to rectify the remainingdeficiencies as well as submit the zoning plan as well service plan estimates of the above said plotted colonybefore the request is considered. Even the copy of service plan/estimates submitted to the HSVP is also notattached.The matter to come up on 12.09.2022. OBJECTION View Order
22-Aug-2022 Proceedings dated 22.08.2022 Ms. Geeta Rathee Singh, Sr. L.O. briefed about the facts of the case. Sh. Ashok Kumar (Advocate) and Sh. Rajesh Kumar (VP) are present on the behalf of the promoter. The AR submits that the deficiencies notice has been received today only vide which various shortcomings/deficiencies in documents have been conveyed and thus seeks one week time for their rectification as well submission of deficit documents. The request is allowed. The matter to come up on 29.08.2022. EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
13-Sep-2022 Proceedings dated 12.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed about the facts of the case. None is present on behalf of the promoter. One more opportunity is granted for rectifying the defects in the application for registration and submission of deficit documents.   The matter to come up on 27.09.2022. Not Yet
25-Aug-2022 Proceedings dated 22.08.2022 Ms. Geeta Rathee Singh, Sr. L.O. briefed about the facts of the case. Sh. Ashok Kumar (Advocate) and Sh. Rajesh Kumar (VP) are present on the behalf of the promoter. The AR submits that the deficiencies notice has been received today only vide which various shortcomings/deficiencies in documents have been conveyed and thus seeks one week time for their rectification as well submission of deficit documents. The request is allowed. The matter to come up on 29.08.2022. Not Yet