Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
VIENNA GREENS | SECTOR 99A | GURUGRAM | Harsaru ST | Skywhales Developers LLP |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/595/327/2022/70 DATED 25.07.2022 | RERA-GRG-1091-2022 | 30-Jun-2022 | 29-Jun-2022 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 13-Jul-2022 | HARERA/GGM/RPIN/478 | dispatched to AR | First Hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/595/327/2022/70 DATED 25.07.2022 | 26-Aug-2022 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
25-Jul-2022 | the Authority approves the grant of registration certificate. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
18-Jul-2022 | Proceedings dated 18.07.2022 Ar. Neeraj Gautam, Associate Architectural Executive, briefed the facts of the case. Sh. Manjeet Singh (Partner) is present on the behalf of the promoter. The AR has submitted the reply to the deficiency notice conveyed to the promoter on 12.07.2022. The reply has been submitted on 14.07.2022 and further additional clarifications also submitted today which needs to be examined by the office and to be put up thereafter. The matter to come up on 25.07.2022.Vijay Goyal (Member) KK Khandelwal (Chairman) | EXAMINATION BY AUTHORITY | --- |