Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Central Park Flower Valley Floors and Villas Village Dhunela & Berka, Sector-29,30,32 and 33, Sohna GURUGRAM Sohna Central Park Flower Valley
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/624/356/2022/99 DATED 27.10.2022 RERA-GRG-1084-2022 13-Jul-2022 23-Jun-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Not Yet -- First Hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/624/356/2022/99 DATED 27.10.2022 17-May-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
27-Oct-2022 Approved as proposed. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
26-Oct-2022 The coram is not complete. So the matter is adjourned for 27.10.2022. ADJOURNMENT View Order
11-Oct-2022 The major deficiencies are Building plan approvals of 6 plots and Bank Undertaking. The promoter is further advised to rectify the deficiencies and submit the deficient document apart from filing information in REP-I A to H format and detailed project information.  Matter to come up on 26.10.2022. ADJOURNMENT View Order
27-Sep-2022           1          Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case & major deficiencies have been pointed out i.e. (1). Building plan approvals of 6 plots.           (2). Bank Undertaking. The matter is adjourned for 11.10.2022. ADJOURNMENT View Order
19-Sep-2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Gulshan Kumar (Assistant Manager) and Sh. Saurabh Bhardwaj (Manager) are present on behalf of the promoter. Deficiencies have already been communicated. Promoter is advised to rectify the deficiencies and submit deficient documents, as detailed above. The matter to come up on 27.09.2022. OBJECTION View Order
05-Sep-2022 Proceedings dated:  05.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Gulshan Kumar (Assistant Manager) is present on behalf of the promoter, who submits that approval of building plans in respect of six number of plot could not be still obtained due to some technical glitch in the site of DTCP and hence requests for an adjournment for submission of deficit building plans and hard copy of other documents. The matter to come up on19.09.2022. ADJOURNMENT View Order
17-Aug-2022 Proceedings dated 17.08.2022 Ms. Geeta Rathee Singh, Sr. Legal Officer and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Gulshan Kumar (Assistant Manager) is present on behalf of the promoter. The AR submits that the building plans have been approved for all the units except for six plots which are also under approval and final permission shall be submitted within next one week and request for short adjournment for their submission. The matter to come up on 05.09.2022. OBJECTION View Order
01-Aug-2022 Proceedings dated 01.08.2022Ms. Geeta Rathee Singh, Sr. Legal Officer, and Ar. Neeraj Gautam, Associate Architectural Executive, briefed the factsof the case.Sh. Gulshan Kumar (Assistant Manager) and Sh. Saurabh Bhardwaj (Manager) are present on behalf of thepromoter.The AR of the promoter seeks 2 weeks' time for submission of the deficit documents including hard copies of theDPI and other relevant approvals. Meanwhile the office is directed to check the status of penal proceedings ifpending in respect of the above project and to put up the same.The matter to come up on 17.08.2022. EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
13-Sep-2022 Proceedings dated:  05.09.2022 Ar. Neeraj Gautam, Associate Architectural Executive and Ms. Asha, Chartered Accountant briefed the facts of the case. Sh. Gulshan Kumar (Assistant Manager) is present on behalf of the promoter, who submits that approval of building plans in respect of six number of plot could not be still obtained due to some technical glitch in the site of DTCP and hence requests for an adjournment for submission of deficit building plans and hard copy of other documents. The matter to come up on19.09.2022. Not Yet
02-Aug-2022 Proceedings dated 01.08.2022Ms. Geeta Rathee Singh, Sr. Legal Officer, and Ar. Neeraj Gautam, Associate Architectural Executive, briefed the factsof the case.Sh. Gulshan Kumar (Assistant Manager) and Sh. Saurabh Bhardwaj (Manager) are present on behalf of thepromoter.The AR of the promoter seeks 2 weeks' time for submission of the deficit documents including hard copies of theDPI and other relevant approvals. Meanwhile the office is directed to check the status of penal proceedings ifpending in respect of the above project and to put up the same.The matter to come up on 17.08.2022. Not Yet