Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Central Avenue Sector 92 Gurugram, in the Revenue Estate of Village Wazirpur, District Gurugram, Haryana GURUGRAM Harsaru ST GLS Infraprrojects Pvt. Ltd
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/600/332/2022/75 DATED 08.08.2022 RERA-GRG-1076-2022 24-Jun-2022 23-Jun-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 20-Jul-2022 By Hand By Hand
To be placed before the authority for first hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/600/332/2022/75 DATED 08.08.2022 02-Sep-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
08-Aug-2022 Proceedings dated 08.08.2022 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Ashish Drall (Sr.GM) & Sh. Pankaj Sharma (Legal Manager) are present on the behalf of promoter. The AR clarifies that the above application for registration is w.r.t. additional license measuring 1.10625 acres only which has been obtained in continuity to the existing license of 8.26875 acres which is already under development and the date of completion proposed for this additional phase is separately declared under 4(2)(l)(C). Further the promoter is submitting BG for Rs. 10 lakh each for submission of fire scheme and approved service estimates (revised). The office is to check and ensure that there are compliances in respect of the existing project required under the Act. The Authority decides to grant the registration subject to same. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
27-Jul-2022 Proceedings dated 27.07.2022 Sh. Shashank Sharma, Associate Engineer Executive briefed about the facts of the project. Sh. Ashish Drall (Sr.GM) & Sh. Pankaj Sharma (Legal Manager) are present on the behalf of promoter. The AR requests for one week for rectification of the deficiencies and submission of deficit documents as per above. The matter to come up on 08.08.2022. ADJOURNMENT View Order
25-Jul-2022 Due to administrative work of the Authority, the matter is adjourned to 27.07.2022 EXAMINATION BY AUTHORITY View Order