08-Aug-2022 |
Proceedings dated 08.08.2022
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh. Ashish Drall (Sr.GM) & Sh. Pankaj Sharma (Legal
Manager) are present on the behalf of promoter.
The AR clarifies that the above application for
registration is w.r.t. additional license measuring 1.10625 acres only which
has been obtained in continuity to the existing license of 8.26875 acres which
is already under development and the date of completion proposed for this
additional phase is separately declared under 4(2)(l)(C). Further the promoter
is submitting BG for Rs. 10 lakh each for submission of fire scheme and
approved service estimates (revised). The office is to check and ensure that
there are compliances in respect of the existing project required under the Act.
The Authority decides to grant the registration subject to same. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
27-Jul-2022 |
Proceedings dated 27.07.2022
Sh. Shashank Sharma, Associate
Engineer Executive briefed about the facts of the
project.
Sh. Ashish Drall (Sr.GM) & Sh. Pankaj Sharma (Legal
Manager) are present on the behalf of promoter.
The AR requests for one week for
rectification of the deficiencies and submission of deficit documents as per
above.
The matter to come up on 08.08.2022. |
ADJOURNMENT |
View Order |
25-Jul-2022 |
Due to administrative work of the Authority, the matter is adjourned to 27.07.2022 |
EXAMINATION BY AUTHORITY |
View Order |