21-Nov-2022 |
Sh.
Sumeet, Engineer Executive and Ms. Asha, Chartered Accountant briefed about the
facts of the project.
Sh.
Praveen Kumar (AR) is present on behalf of the promoter.
Approved
as proposed. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
27-Oct-2022 |
The promoter is directed to rectify the deficiencies and submit the deficit fee if any. The matter is adjourned for 21.11.2022. |
ADJOURNMENT |
View Order |
26-Oct-2022 |
The coram is not complete. So the matter is adjourned for 27.10.2022. |
OBJECTION |
View Order |
11-Oct-2022 |
The major deficiencies Architectural
Control sheet & Approval for external services. The promoter is further advised to rectify the deficiencies and submit
the deficient document apart from filing information in REP-I A to H format and
detailed project information. Matter to
come up on 26.10.2022. |
ADJOURNMENT |
View Order |
27-Sep-2022 |
Sh. Sumeet, Engineer Executive briefed about the facts of the project and following major deficiencies have pointed out i.e. (1)
Standard Designs / Architectural Control
Sheets. (2.) Approval/
NOCs for external services. The matter is adjourned for 11.10.2022. |
ADJOURNMENT |
View Order |
19-Sep-2022 |
Sh.
Sumeet, Engineer Executive briefed about the facts of the project.
Sh.
Pawan Kumar (Advocate-AR) is present on behalf of the promoter.
Deficiencies have already been
communicated. Promoter is advised to rectify the deficiencies and submit
deficient documents, as detailed above.
Matter to come up on 27.09.2022 |
EXAMINATION BY AUTHORITY |
View Order |