09-Aug-2022 |
Sh. Sumeet, Engineer Executive briefed about the facts of the case.Sh. Abhishek Gupta (AGM) and Sh. Piyush Aggarwal (President) are present on behalf of the promoter.Approved, as proposed.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
08-Aug-2022 |
Sh. Sumeet, Engineer Executive briefed about the facts of the case.Sh. Abhishek Gupta (AGM-Strategy Planning) and Sh. Piyush Aggarwal (President) are present on behalf of the promoter.Due to paucity of time, the matter is adjourned to 09.08.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
01-Aug-2022 |
Ms. Geeta Rathee Singh, Sr. Legal Officer and Sh. Sumeet, Engineer Executive briefed about the facts of the case.Sh. Abhishek Gupta (AGM-Strategy Planning) and Sh. Piyush Aggarwal (President) are present on behalf of the promoter.The AR of the promoter requests for one week time to rectify the remaining deficiencies.The matter to come up on 08.08.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
--- |
18-Jul-2022 |
Sh. Sumeet, Engineer
Executive briefed about the facts of the case.Sh. Abhishek
Gupta (AGM-Strategic Planning) is present on behalf of the promoter.The AR stated
that they have submitted the reply today itself which needs to be scrutinized
by Sh. Sumeet, Engineer Executive.
The matter to
come up on 01.08.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
EXAMINATION BY AUTHORITY |
--- |