Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
PURI THE ARAVALLIS | Sector 61, Village Ullawas | GURUGRAM | Wazirabad ST | Puri Construction Private Limited |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/592/324/2022/67 DATED 18.07.2022 | RERA-GRG-1049-2022 | 10-Jun-2022 | 08-Jun-2022 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Not Yet | -- | 1st deficiency notice sent to the promoter. | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/592/324/2022/67 DATED 18.07.2022 | 26-Aug-2022 | RC Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
18-Jul-2022 | Proceedings dated: 18.07.2022 Sh. J.S Sindhu, Executive Engineer (Monitoring) briefed about the facts of the project. Sh. Himanshu Juneja (Legal Head) and Ms. Smriti Rani (Assistant Manager Legal) are present on behalf of the promoter. Approved as proposed. Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
11-Jul-2022 | Proceeding dated 11.07.2022.Sh. J.S. Sindhu briefed the facts of the project.Due to paucity of time the matter is adjourned for 18.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) | EXAMINATION BY AUTHORITY | --- |