Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
SMARTWORLD ORCHARD | Sector -61, Gurugram Manesar Urban Complex, Gurugram, Haryana | GURUGRAM | Wazirabad ST | Suposhaa Realcon Private Limited |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/616/348/2022/91 DATED 04.10.2022 | RERA-GRG-1039-2022 | 01-Sep-2022 | 01-Sep-2022 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Not Yet | -- | First Hearing | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/616/348/2022/91 DATED 04.10.2022 | 15-Oct-2022 | This registration certificate supersedes the earlier registration no. 73 of 2021 dated 27.10.2021 granted for the part of land of the present application without amending the date of completion of the project. Now onwards QPRs shall be based on A-H information in REP-I for the whole project. |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
04-Oct-2022 | Proceedings dated 04.10.2022 : Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefed the facts of the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma (AR) are present on behalf of the promoter. Approved as proposed. A condition be incorporated in the registration certificate that in the eventuality of final outcome in the matter decided against the land owners/license holders and/or collaborator in the matter pending in Hon’ble Supreme Court in CA No. 8977 of 2014 titled as Jai Narayan @ Jai Bhagwan & others V/s State of Haryana and final outcome of CBI investigation under process, then the promoter is obligated to refund the amount received from allottees along with interest at the prescribed rate without prejudice to any other remedy including compensation. (Sanjeev Kumar Arora) Member, HARERA, Gurugram (Ashok Sangwan) Member, HARERA, Gurugram (Dr. K.K. Khandelwal) Chairman, HARERA, Gurugram. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | View Order |
27-Sep-2022 | Ar. Neeraj Gautam (Associate Architectural Executive) briefed about the facts of the project and following major deficiencies have pointed out i.e. Public notice issued and last date of receiving objections is 29.09.2022. The matter is adjourned for 04.10.2022. | ADJOURNMENT | View Order |
19-Sep-2022 | Ar. Neeraj Gautam (Associate Architectural Executive) and Ms. Asha (Chartered Accountant) briefedthe facts of the case. Sh. Abhijeet Singh (AR) and Sh. Manik Sharma(AR) are present on behalf of the promoter. Although the AR submits that the approval of revised lay out plan has been obtained from DTCP after obtaining objections from the existing allottees in pursuance to the policy dated 25.01.2021 issued by Principal Secretary to Govt. Haryana T&CP; Department. The AR submits that the consent of 2/3rd allottees prior to revision were obtained and shall be submitted in the Authority. Further a list of the changes in the revised plan viz a viz earlier sanctioned plan shall also be submitted duly marked on the plan for inspection of the allottees and one-week public notice shall be issued by the Authority in two news papers at the cost of the applicant promoter. Deficit fee, if any be also paid before the next date of hearing along with proof of having deposited the deficit fee. The matter to come up on 27.09.2022. | EXAMINATION BY AUTHORITY | View Order |