Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
ZARA ROMA SECTOR-95B GURUGRAM Harsaru ST Mega Infratech Private Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/582/314/2022/57 DATED 27.06.2022 RERA-GRG-1030-2022 09-Mar-2022 09-Mar-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 24-Mar-2022 HARERA/GGM/RPIN/447 Dispatched to AR
First Hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/582/314/2022/57 DATED 27.06.2022 25-Aug-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
27-Jun-2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh. Karunesh Virmani and Sh. Ajay Bharti (Director) and Sh. Pawan Kumar (Project Engineer)  are  present on behalf of the promoter. During the last hearing, the promoter was asked to submit BGs of Rs. 25 lakh each for submission of pending approval of service plan and estimates as well as approval of fire plans. The Associate Architectural Executive confirms that the requisite BGs have been submitted to the Authority as per the above details. Further, the promoter was required to submit pending QPRs and annual audit reports in respect of the existing registered projects. The promoter submits that up-to-date QPRs of the existing project as well annual audit reports have been uploaded on the website as well hard copies submitted in the registry of Authority and a certificate of the concerned branch in charge has also been placed in the office file. The Associate Architectural Executive confirms that no other compliance is pending, and the case fulfills the requirement for the registration of the project, and accordingly the Authority decides to grant the registration.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
06-Jun-2022 The Coram is incomplete. The matter is adjourned to 27.06.2022. ADJOURNMENT ---
30-May-2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh. Rajeev Srivastava (GM (P)), Sh. Manoj Kumar (Billing Engineer), Sh. Karunesh Virmani and Sh. Ajay Bharti (Director) are  present on behalf of the promoter. Bank Guarantee amounting to Rs. 25 lakh is to be submitted as a guarantee to obtain service estimates and plan approval within three months otherwise bank guarantee shall be encashed/forfeited. A certificate from the concerned branch regarding submission of the annual audit report of project accounts in respect of projects registered till 31.03.2021 and QPRs of the projects of the promoter till last quarter is to be submitted.  The matter to come up on 06.06.2022. ADJOURNMENT ---
23-May-2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh.Rajiv Srivastava (GM) is present on behalf of the promoter.Corrections in online DPI have been made by the promoter and the hard copy of the same is yet to be submitted. On request of the promoter, the hearing date for the registration of the project is preponed from 30.05.2022 to 23.05.2022. The promoter has made the application for the approval of the fire scheme and service plans and estimates in the concerned departments and the final approvals are still awaited. The promoter has also submitted an undertaking from the bank regarding not affecting the rights and interest of allottees as per section 11(4)(h) of Act, 2016 vide dak ID 32335 dated 10.05.2022.The promoter is directed to submit a bank guarantee of Rs 25 lakhs on account of the approved fire scheme and Rs. 25 lakhs on account of approved service plans and estimates in the Authority within one week from the date of grant of registration. The same shall be forfeited by the Authority, in case, the requisite documents are not submitted to the Authority within the stipulated time. The promoter has been directed to submit the status of submission of QPRs and compliance of Section 4(2)(l)(D) in respect of other registrations of the promoter and its associate companies within three days and the office to submit confirmed status on next date.Matter to come up for compliance on 30.05.2022. ADJOURNMENT ---
25-Apr-2022 Proceedings dated 25.04.2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh.Rajiv Srivastava (GM) is present on behalf of the promoter. Corrections in Online DPI have been made by the promoter and the hard copy of the same is yet to be submitted. Corrections in Part C of REP-I are still pending. It is noted that exclusive charge by way of equitable mortgage on project land (undivided share) and building (Developer’s share) has been created and the sold and unsold receivables corresponding to the upcoming project have been hypothecated. Further, the collaboration agreement registered between the landowner and the developer is revocable. As per clause 32.1.c of the above agreement, “In the event after the allotment of flats in the Affordable Housing Project, the DEVELOPER doesn’t commence work on the said land for a period of 6 months or abandons the works, this agreement may be terminated at the sole option of the OWNER by issuing a written notice to DEVELOPER and on termination, the non-refundable amount of Rs. 5 crores paid by the DEVELOPER to OWNER shall stand forfeited. Any works done on the said land shall vest with the OWNER and the OWNER may take over the project and get the project completed, or the said land cleared, at the sole risk and cost of the DEVELOPER.” Keeping in view the above observations, the Authority decides that a show-cause notice be issued for rejection of the application for grant of registration under section 5 of the Act of 2016 and read with rule 5 of Haryana Rules, 2017. If the promoter has to say in this regard, an opportunity of hearing is given to the promoter on 30.05.2022.  OBJECTION ---
18-Apr-2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh. Rajeev Srivastava (GM), Sh. Daleep Kumar (CA), Sh. Pawan Kumar (PE) and Sh. Manoj Kumar (BE) are present on behalf of the promoter. The reply was submitted today which needs to be scrutinized. Accordingly, the matter to come up on 25.04.2022. ADJOURNMENT ---
04-Apr-2022 Sh. Pawan Kumar (AR) is present on behalf of the promoter. Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. The promoter is directed to submit the deficit documents in the authority before the next date of hearing. The matter to come up on 18.04.2022 EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
19-Apr-2022 Ms. Neeraj Gautam, Associate Architectural Executive briefed the facts of the case. Sh. Rajeev Srivastava (GM), Sh. Daleep Kumar (CA), Sh. Pawan Kumar (PE) and Sh. Manoj Kumar (BE) are present on behalf of the promoter. The reply was submitted today which needs to be scrutinized. Accordingly, the matter to come up on 25.04.2022. Not Yet