Signatureglobal City 37D II Village-Gadoli Kalan, Sector-37D, Gurugram GURUGRAM Gurgaon Rose Building Solutions Private Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/545/277/2022/20 DATED 31.03.2022 RERA-GRG-1022-2022 18-Feb-2022 17-Feb-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 07-Mar-2022 HARERA/GGM/RPIN/440 notice dispatched to the AR
first hearing View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/545/277/2022/20 DATED 31.03.2022 25-Aug-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
31-Mar-2022 Proceedings dated 31.03.2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Ajay Kumar (AGM) are present on the behalf of the promoter. The requisite corrections in online DPI and REP-I (Part A-H) have been made.  The approval of service plans and estimates has been only recommended by CE-I of HSVP to DTCP, Haryana and final approval is still awaited. The promoter undertakes to submit the approved service plans and estimates in the authority within 90 days from the date of grant of registration. The promoter submits that the escrow agreement with the bank is not executed yet and it will be submitted to the authority as and when executed with the bank. The authority decides to grant the registration subject to the submission of bank guarantee/security cheque of Rs. 25 lakhs on account of approved service plans and estimates within seven days and submission of escrow agreement executed with the bank within 15 days from the date of grant of registration. This bank guarantee/ security cheque shall be forfeited in case of failure to submit the approved service plans and estimates to the authority by the promoter within three months from the date of grant of registration. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
28-Mar-2022 The matter is adjourned to 31.03.2022 ADJOURNMENT ---
21-Mar-2022 The matter is adjourned to 28.03.2022 OBJECTION ---
14-Mar-2022 Proceedings dated 14.03.2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Anurag Srivastava (GM) and Sh. Ajay Kumar (AGM) are present on the behalf of the promoter. The AR of the promoter informs that the requisite corrections in form A to H and online DPI have been made and a hard copy of the same is also being submitted today for scrutiny of the concerned Planning Executive. Further, regarding the submission of the copy of the loan sanction letter, the AR clarified that there is no bank loan on this specified project and has submitted a non-encumbrance certificate as well as TSR.  However, the CA of the Authority has raised the issue that as per MCA record, there is a loan of Rs. 60 crores against the applicant promoter company.  The AR is required to submit a copy of said loan sanction letter to enable confirmation that this loan is not against the instant applied project. The AR further clarifies that the approval of the service plan and estimates stand submitted to DTCP and have been technically okayed by the CE of HSVP and are likely to be approved by DTCP shortly. The promoter is yet to submit a copy Escrow agreement executed with the bank. The matter to come up on 21.03.2022. EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
17-Mar-2022 Proceedings dated 14.03.2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Anurag Srivastava (GM) and Sh. Ajay Kumar (AGM) are present on the behalf of the promoter. The AR of the promoter informs that the requisite corrections in form A to H and online DPI have been made and a hard copy of the same is also being submitted today for scrutiny of the concerned Planning Executive. Further, regarding the submission of the copy of the loan sanction letter, the AR clarified that there is no bank loan on this specified project and has submitted a non-encumbrance certificate as well as TSR.  However, the CA of the Authority has raised the issue that as per MCA record, there is a loan of Rs. 60 crores against the applicant promoter company.  The AR is required to submit a copy of said loan sanction letter to enable confirmation that this loan is not against the instant applied project. The AR further clarifies that the approval of the service plan and estimates stand submitted to DTCP and have been technically okayed by the CE of HSVP and are likely to be approved by DTCP shortly. The promoter is yet to submit a copy Escrow agreement executed with the bank. The matter to come up on 21.03.2022. Not Yet