04-Apr-2022 |
Proceedings
dated: 04.04.2022.
Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh. Bhupender Kumar
(Manager) and Sh. Himanshu Gupta (Legal representative) is present on behalf of
the promoter.
The promoter stated that the
online DPI got corrected.
The
Authority directed the promoter to submit the corrected online DPI and an
undertaking regarding the Storm Water Drainage. The Authority decided to grant
the registration certificate on the condition that the promoter shall submit
the binded DPI within 3 days.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
21-Mar-2022 |
Proceedings dated: 21.03.2022 The matter is adjourned and fixed for 04.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
View Order |
14-Mar-2022 |
Proceedings
dated: 14.03.2022.
Ms.
Jyoti Yadav, Coordinator Planning Branch briefed about the facts of the case.
Sh.
Bhupinder Kumar (Manager), Sh. Sumit Khanna(Manager) and Sh. Himanshu Gupta
(Legal Associate) are present on behalf of the promoter, who informs that the
detailed reply to the deficiencies notice dated 07.03.2022 has been submitted
in the Authority two day back and rectification in form A to H and online DPI
has also been made which are under scrutiny. The concerned Planning Executive
is directed to complete the process of scrutiny in one week and to put up in
the next meeting for further consideration. The AR to bring one hard copy of
DPI during next meeting for perusal of the Authority.
The matter to come up on 21.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K Khandelwal) |