18-Jul-2022 |
Sh.
Sumeet, Engineer Executive briefed about the facts of the case.
Sh.
Rajnish Dutt (Head CRM), Sh. Eshendra Tiwari (Manager CRM) and Ms. Priyanka
Aggarwal (AR) are present on behalf of the promoter.
The
authority decided to grant the registration certificate.
Member (Vijay Kumar Goyal)
Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
11-Jul-2022 |
Proceedings
dated: 11.07.2022.
Sh.
Sumeet, Engineering Executive briefed about the facts of the
case.
Sh.
Rajnish Dutt (Head CRM), Sh. Eshendra Tiwari (Manager CRM) and Ms. Priyanka
Aggarwal (AR) are present on behalf of the promoter.
The
AR submits that the corrections in the form A to H is submitted today only
which needs to be checked by EE.
The
matter to come up on 18.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
27-Jun-2022 |
Proceedings
dated: 27.06.2022.
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Rajnish Dutt (Head CRM), Sh. Eshendra Tiwari (Manager CRM) and Ms. Priyanka
Aggarwal (AR) are present on behalf of the promoter.
The
authority directed the promoter to submit the corrected online DPI and
corrected online form (A-H).
The
matter to come up on 11.07.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
13-Jun-2022 |
Proceedings
dated: 13.06.2022.
Sh.
Rajnish Dutt (Head CRM) and Sh. Eshendra Tiwari (Manager CRM) are present on
behalf of the promoter.
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
The
promoter needs to rectify the remaining deficiencies mentioned below:
1.
The annexures in the online application
are not uploaded as well as the correction needs to be done in the online (A-H)
application.
2.
Online DPI needs
to be corrected.
3.
Draft
Allotment letter is not as per the prescribed format needs to be submitted.
4.
Draft
Builder Buyer Agreement is not as per the prescribed format needs to be
submitted.
5.
Other cost as
mentioned in DPI is 34.88% of total cost which seems abnormal in normal course
of business. Hence, it needs to be corrected.
6.
Escrow agreement executed with the bank needs to be submitted.
7.
Financial resources of the project need to be corrected.
The
coram is incompleted. The matter is adjourned for 27.06.2022. |
ADJOURNMENT |
--- |
30-May-2022 |
Proceedings
dated: 30.05.2022. Sh. Ashish
Kush, Planning Executive briefed about the facts of the case.
Ms.
Priyanka Aggarwal (Advocate) is present on behalf of the
promoter.
Apart from rectification of the above deficiencies the
promoter is advised to submit a certificate from the concerned branch regarding
submission of the annual audit report of project accounts in respect of
projects registered till 31.03.2021 and QPRs of the projects of the promoter
till last quarter is to be submitted. The
promoter requested for registration of the project in two phases as for Tower
B, C and D. OC was obtained on 16.01.2018, accordingly, same be treated as
deemed phase-I and for Tower A which is yet to be constructed and on which
additional FAR available because of GRIHA is to be used is to be registered as
a separate phase but completion date for the whole project will remain same as
declared as per section 4(2)(l)(C) both
for phase-I and II.
The matter to come up on 13.06.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
09-May-2022 |
Proceedings
dated: 09.05.2022.
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Rajnish Dutt (CRM Head) is present on behalf of the promoter.
On
04.04.2020, the authority decided to issue a show cause notice as why the
application for grant of registration shall not be rejected on account of
deficiencies. The matter to come up on 09.05.2022.
The
promoter failed to comply with the deficiencies conveyed earlier as well as in
show cause notice vide no. HARERA/GGM/RPIN/432/Show Cause dated 08.04.2022.
The AR
of the promoter requested for one last opportunity of 3 weeks time for
rectification of the remaining deficiencies and submission of deficient
documents.
The
matter to come up on 30.05.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
04-Apr-2022 |
Proceedings
dated: 04.04.2022.
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Rajnish Dutt (Head CRM) and Sh. Eshendra Tiwari (Manager CRM) are present on
behalf of the promoter.
The
Authority directed to issue a show cause notice as why the application for
grant of registration shall not be rejected on account of deficiencies as
mentioned above as per provisions of section 5(2)(b) of the Act, 2016 read with
rule 5(2) of Haryana Rules, 2017. If promoter has to say anything in the matter
he may represent before the authority on 09.05.2022 at 3.00 PM in the office of
the authority or rectify deficiencies before that date. Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
07-Mar-2022 |
Proceedings
dated: 07.03.2022.
Sh.
Ashish Kush, Planning Executive briefed about the facts of the case.
Sh.
Rajnish Dutt (Head- CRM) and Sh. Eshendra Tiwari (Manager- CRM) are present on
behalf of the promoter, who requests for 3 weeks’ time for rectification of the
deficiencies and submission of complete documents as the main promoter is out
of country and all the requisite documentation shall be completed within next 3
weeks. The Authority decided to adjourn the matter and the matter to come up on
04.04.2022. Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
21-Feb-2022 |
Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh. Rajneesh Dutt
(CRM Head), Gurvinder Singh (Project Head) are present on behalf of the
promoter.
After scrutiny of
the reply dated 18.02.2022, it was noticed that there are large number of deficiencies
which are still pending. The Authority directed the promoter to submit the
deficit documents.
The matter to
come up on 07.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |