Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Central Park Flower Valley - Phase III Sector 29,30, 32 & 33, Sohna, Dist. Gurugram GURUGRAM Sohna St. Patricks Realty Pvt Ltd
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/562/294/2022/37 DATED 16.05.2022 RERA-GRG-997-2021 18-Jan-2022 13-Jan-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 02-Feb-2022 Received by hand 1st deficiency notice
1st deficiency notice sent to the promoter. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/562/294/2022/37 DATED 16.05.2022 31-Oct-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
16-May-2022 Proceedings Dated: 16.05.2022 Sh. Saurabh Bhardwaj (Manager), Sh. Chirag Gehlot (Head Coordination) and Sh. Puneet Sachdeva (AGM) are present on behalf of the promoter. The authority decided to grant registration subject to the submission of bank guarantee of Rs. 25 lakhs on account of approval of revised zoning plan and bank guarantee of Rs. 25 lakhs on account of approval of revised environmental clearance and submission of hard binded copy of DPI and REP-I (A-H) in the authority within one week.  Accordingly, the BG of total Rs. 50 lakhs be submitted with the Authority along with an affidavit that approval of revised zoning plan, approval of revised environmental clearance and renewal of license no. 28 of 2016 shall be submitted within 3 months from the date of issuance of registration certificate. In case of failure to submit the above said approvals within three months, then the Authority shall be free to encash the BG and the registration certificate shall be treated as deemed cancelled.   APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
10-May-2022 Matter to come up on 16.05.2022 OBJECTION ---
14-Mar-2022 The promoter is directed to submit the detailed project information along with other deficit documents. Matter adjourned for 10.05.2022. ADJOURNMENT ---
07-Mar-2022 No one appeared on behalf of the promoter.The deficiencies have been conveyed to the promoter and no reply is submitted by the promoter till date. One last opportunity of hearing is being offered to the promoter to rectify all the deficiencies and submit the reply before next date of hearing. One week time is granted to the promoter to do the needful compliances. Matter to be heard on 14.03.2022. OBJECTION ---
28-Feb-2022 The matter adjourned for 07.03.2022. ADJOURNMENT ---
15-Feb-2022 The matter is adjourned for 28.02.2022 EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
10-May-2022 The promoter is directed to submit the detailed project information along with other deficit documents. Matter adjourned for 10.05.2022. Not Yet
04-Mar-2022 The matter adjourned for 07.03.2022. Not Yet