07-Feb-2022 |
Proceedings Dated: 07.02.2022
Ar. Neeraj Gautam,
Associate Architectural Executive briefed the facts about the case.
Sh. Mayank Prajapat (AR)
and Sh. M.S. Mittal, Chairman are present on behalf of the promoter.
The promoter has made the requisite
corrections in online DPI and submitted deficit documents except for the copy
of approved zoning plan and service plan and estimates for which the BG of Rs.
10 lakh each has also been submitted in the registry of the Authority on
28.01.2022 with an undertaking for submission of their approved copies within
three months of the grant of registration certificate.
In view of the above facts, the authority has
decided to grant registration to the promoter subject to submission of
remaining deficit documents in the authority within stipulated time. In case
approved zoning plan and approved service plan and estimates are not submitted
in the authority within three months of the date of grant of registration, the
bank guarantee shall be forfeited. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
31-Jan-2022 |
Proceedings Dated: 31.01.2022
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case through video conferencing.
The promoter has applied for approval of zoning plan
and service plans and estimates in the concerned departments and
acknowledgements of the same have been submitted in the authority. The corrections
in online DPI and deficit fee of Rs. ₹10,19,174/- are still pending.
The promoter has submitted a bank guarantee of Rs. 10
lakhs on account of submission of approved zoning plan and Rs. 10 lakhs on
account of submission of approved service plans and estimates within three
months from date of issuance of registration certificate.
By the order of the authority, the promoter is
directed to attend the deficiencies before the next date of hearing
The matter to come up on 07.02.2022 |
ADJOURNMENT |
View Order |
24-Jan-2022 |
Proceedings Dated: 24.01.2022 Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case.
Sh. Mayank Prajapat (AR) joined the proceedings
through VC on behalf of the promoter. The promoter is directed to submit the deficit documents in the authority before the next date of hearing.The matter to come up on 31.01.2022 |
ADJOURNMENT |
View Order |
19-Jan-2022 |
Proceedings Dated: 19.01.2022
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case.
Sh. Mayank Prajapat (AR) joined the proceedings
through VC on behalf of the promoter. The promoter has been advised to submit the
balance approvals within one week or the bank guarantee of Rs. 10 lakhs for
each of the approvals be submitted for obtaining the requisite approvals within
2 months’ time.
The matter to come up on 24.01.2022. |
ADJOURNMENT |
View Order |
17-Jan-2022 |
The matter is adjourned to 19.01.2022. |
EXAMINATION BY AUTHORITY |
View Order |