21-Feb-2022 |
Proceedings
dated 21.02.2022
Ms.
Neeraj Gautam, Architectural Executive briefed the facts about the project.
Sh.
Virender Verma (Director) and Parveen Kumar (AR) are present on behalf of the
promoter. The promoter has submitted the hard copy of the corrected online DPI in
the authority today. The promoter has applied for the approvals of fire scheme,
service plans and estimates, tree cutting permission, power line shifting NOC, and environmental clearance in the concerned departments, and the final approvals
are still awaited.
The authority has decided to grant registration to the
promoter subject to the submission of tree cutting permission and power line
shifting NOC within two months from the date of grant of registration and
environmental clearance, approved fire scheme and approved service plans and
estimates within three months from the date of grant of registration.
The promoter shall submit a bank guarantee of Rs 10 lakhs on account of the approved fire
scheme and Rs. 10 lakhs on account of approved service plans and estimates
within seven days from the date of grant of registration. This bank guarantee
shall be forfeited in case the approved fire scheme and approved service plans
and estimates are not submitted in the authority within three months from the
date of grant of registration. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
14-Feb-2022 |
Ms Neeraj gautam, Architectural Executive briefed the facts about the project.Sh. Praveen Kumar (AR) is present on behalf of the promoter. The promoter is directed to submit the deficit documents in the authority before the next date of hearing.The matter to come up on 21.02.2022. |
ADJOURNMENT |
View Order |
07-Feb-2022 |
Proceedings
dated 07.02.2022
Ms.
Neeraj Gautam, Architectural Executive briefed the facts about the project.
Sh.
Virender Verma (Director) and Sh. Parveen Kumar (AR) are present on behalf of
the promoter.
The approvals of fire scheme, service plans and
estimates, environmental clearance, airport height clearance, tree cutting
permission, power line shifting NOC and HUDA construction water NOC are applied
in the respective departments and the final approvals are still awaited.
The
promoter is directed to submit the hard copy of the corrected online DPI along with
other deficit documents in the authority
before the next date of hearing.
The matter to come up on 14.02.2022 |
ADJOURNMENT |
--- |
31-Jan-2022 |
Proceedings
dated 31.01.2022
Ms.
Neeraj Gautam, Architectural Executive briefed the facts about the project
through video conferencing.
Corrections in the online DPI are still pending. The
approvals of fire scheme, service plans and estimates, environmental clearance,
airport height clearance, tree cutting permission, power line shifting NOC and
HUDA construction water NOC are applied in the respective departments and the
final approvals are still awaited.
By the order of the authority, the promoter is
directed to attend the deficiencies before the next date of hearing.
The matter to come up on
07.02.2022 |
EXAMINATION BY AUTHORITY |
--- |