Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Market city Sector - 89,90 ,gurugram GURUGRAM ORRIS INFRASTRUCTURE PVT LTD
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-955-2021 19-Oct-2021 19-Oct-2021 EXTENSION APPROVED NOT REQUIRED Yes 27-Oct-2021 BY MAIL BY MAIL
The hearing is fixed for 09.11.2021.
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
06-Apr-2022 Proceedings dated: 06.04.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Rasendra Pathak (AR) is present on behalf of the promoter. The promoter stated that they have submitted the fees for the revalidation of the building plans and a copy of same also submitted in the Authority. As well as an affidavit regarding service plan and estimate that there is no change in the development of commercial component alongwith corrected (A-H) also submitted. The Authority decided to grant the extension of registration.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) EXTENSION APPROVED ---
30-Mar-2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Rasendra Pathak (AR) is present on behalf of the promoter. The remaining deficiencies are mentioned below: 1.         Renewal of building plans needs to be submitted. 2.         Copy of approved service plans and estimates needs to be submitted. 3.         The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. The Authority directed the promoter to submit the affidavit regarding service plan and estimate alongwith the deficit documents and matter is adjourned for 06.04.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) ADJOURNMENT ---
09-Mar-2022 Proceedings dated: 09.03.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Rasendra Pathak (AR) is present on behalf of the promoter. The remaining deficiencies are mentioned below: 1.         Corrections in form REP-V needs to be done. 2.         Renewal of building plans needs to be submitted. 3.         PERT chart needs to be revised. 4.         Copy of approved service plans and estimates needs to be submitted. 5.         The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 6.         Financial Viability of the project needs to be provided. 7.         Details of financial progress in REP-V form needs to be corrected. The Authority directed the promoter to remove the deficiencies and correct the online DPI and Online (A-H). The matter to come up on 30.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) ADJOURNMENT ---
25-Jan-2022 The matter is adjourned for 09.03.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) ADJOURNMENT ---
22-Dec-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rasendra Pathak (Asstt. Manager) is present on behalf of the promoter. Following remaining deficiencies are mentioned below: 1.         Corrections in form REP-V needs to be done. 2.        Renewal of building plans needs to be submitted. 3.        PERT chart needs to be revised. 4.        Copy of approved service plans and estimates needs to be submitted. 5.        The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 6.         Financial Viability of the project needs to be provided. 7.         Details of financial progress in REP-V form needs to be corrected. The authority directed the promoter to submit the above-mentioned deficiencies along with the corrected online DPI within a week. The promoter failed to submit requisite information and also failed to establish that there were reasonable circumstances responsible for delay and there is no fault of the promoter. The authority decided to issue a show cause notice to the promoter for violation of section 4(2)(l)(C) punishable under section 60 for failure to complete the project within declared time period and to initiate penal proceeding against the promoter. The matter to come up on 25.01.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) ADJOURNMENT ---
30-Nov-2021 The authority directed the promoter to submit the deficit documents and matter to come up on 22.12.2021. ADJOURNMENT ---
09-Nov-2021 Proceedings dated: 09.11.2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Rasendra Kumar Pathak (Assistant Manager) is present on behalf of the promoter. The AR of the promoter seeks three weeks’ time for submission of online DPI and remaining deficit documents. The matter to come up on 30.11.2021.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) EXAMINATION BY AUTHORITY ---