Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
GARDENCITY CENTRAL Sector 84, Gurugram, Haryana GURUGRAM Gurgaon DLF Home Developers Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
Not Yet Approved/Certificate Not Uploaded Yet RERA-GRG-951-2021 18-Oct-2021 14-Oct-2021 Extension Certificate Uploaded NOT REQUIRED Yes 26-Oct-2021 BY HAND BY HAND
The hearing is fixed for 09.11.2021. View Form(A-H)
Project Listing Details
Date of Hearing Proceedings of the day Status Order
16-Nov-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Shri Ketan Nanda, AVP and Shri Anish Dham, AVP are present on behalf of the promoter. The promoter submitted the reply today itself in which they submitted pending approvals and NOCs from various agencies for connecting external services like water supply, sewerage and storm water drainage as well as electrical load availability and natural conservation zone NOC. Online detailed project information submitted today itself which needs to be examined. For service plans and estimates examination has been done upto the level of Chief Engineer and only BG is to be deposited to the DTCP for issuing approval of service plans and estimates. Architectural control sheet is under approval. Authority decided to grant registration subject to deposit of BG of Rs. 25 lacs which shall be encashed in case approved architectural control sheet is not submitted within two months from today.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
09-Nov-2021 Proceedings dated: 09.11.2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. Sh. Anish Dham (AVP) and Sh. Ketan Nanda (AVP) are present on behalf of the promoter. After scrutiny of the application, major deficiencies were noticed and accordingly stand conveyed vide letter dated 25.10.2021. The promoter is submitting its reply today i.e. 09.11.2021. However, the service plan and estimates of the above colony are still under approval of Engineering division of HSVP. The demarcation plan of above plotted development is also under approval of T&CP; Department. Similarly, the architectural control sheets have been prepared and submitted to the department and the same are also under approval. The copies of NOCs for water supply, road connectivity, sewer, storm water drainage and electricity have been submitted today along with corrections in online DPI. The office to scrutinize the reply and other documents submitted today and matter to come up on 16.11.2021.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) EXAMINATION BY AUTHORITY View Order