16-Nov-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Shri
Ketan Nanda, AVP and Shri Anish Dham, AVP are present on behalf of the
promoter.
The
promoter submitted the reply today itself in which they submitted pending
approvals and NOCs from various agencies for connecting external services like
water supply, sewerage and storm water drainage as well as electrical load
availability and natural conservation zone NOC.
Online
detailed project information submitted today itself which needs to be examined.
For service plans and estimates examination has been done upto the level of
Chief Engineer and only BG is to be deposited to the DTCP for issuing approval
of service plans and estimates. Architectural control sheet is under approval.
Authority decided to grant registration subject to deposit of BG of Rs. 25 lacs
which shall be encashed in case approved architectural control sheet is not
submitted within two months from today.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
09-Nov-2021 |
Proceedings
dated: 09.11.2021
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Anish Dham (AVP) and Sh. Ketan Nanda (AVP) are present on behalf of the
promoter.
After
scrutiny of the application, major deficiencies were noticed and accordingly
stand conveyed vide letter dated 25.10.2021. The promoter is submitting its
reply today i.e. 09.11.2021. However, the service plan and estimates of the
above colony are still under approval of Engineering division of HSVP. The
demarcation plan of above plotted development is also under approval of
T&CP; Department. Similarly, the architectural control sheets have been
prepared and submitted to the department and the same are also under approval. The
copies of NOCs for water supply, road connectivity, sewer, storm water drainage
and electricity have been submitted today along with corrections in online DPI.
The office to
scrutinize the reply and other documents submitted today and matter to come up
on 16.11.2021.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
EXAMINATION BY AUTHORITY |
View Order |