Project Name Project Location Project District Project Tehsil Promoter Name
SHREE VARDHMAN MANTRA(RESI.)/ SHOPPING MART SECTOR-67,VILLAGE BADSHAPUR,GURUGRAM GURUGRAM Badshahpur ST SHREE VARDHMAN BUILDPROP PVT LTD
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/575/307/2022/50 DATED 13.06.2022 RERA-GRG-946-2021 02-Dec-2021 06-Oct-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 15-Dec-2021 HARERA/GGM/RPIN/410 sent through mail and speed post
Matter is fixed for first hearing. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/575/307/2022/50 DATED 13.06.2022 21-Jul-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
13-Jun-2022 The Authority approves the grant of registration certificate. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
30-May-2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Ved Prakash (AR) is present on behalf of the promoter. Apart from attending and rectification of above deficiencies, the promoter is advised to submit that there are no projects registered with the Authority of the promoter and as such no QPRs/AR are pending. The matter to come up on 13.06.2022. OBJECTION View Order
23-May-2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project.Sh. Ved Prakash (AR) and Sh. Sachin Jain (Director) is present on behalf of the promoter. The promoter has made requisite changes in the online DPI and had provided of all the allottees but the hard copy is yet to be submitted. The corrections in form REP-I marked on hard copy and shared with the promoter. The promoter has applied for revalidation of the building plan and paid the fees to the concerned department. The application for approval of revalidation of environmental clearance, and service plans and estimates have been made in the concerned department and the final approval is still awaited. The matter to come up on 30.05.2022.  OBJECTION ---
18-Apr-2022 Proceedings Dated: 18.04.2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Ved Prakash (Admin.) and Sh. Shobit Shukla VP of Kautilya Finance (Financer of the project) are present on behalf of the promoter. The promoter Shree Vardhman Mantra is neither the license holder nor the BIP holder nor the collaborator. The applicant is requesting for making application in the name of the licensee company only along with requisite documents. Although the sales made by M/s Shree Vardhman are against the provisions of the Act. But the same were made before coming into force of BIP policy under low-cost housing scheme of the State Government. The project is still ongoing and to set the record right it would be better that BIP permission is obtained from the competent Authority. A show cause notice be issued for rejection of the application for grant of registration under section 5 of the Act of 2016 and read with rule 5 of Haryana Rules, 2017.  ADJOURNMENT View Order
11-Apr-2022 Proceedings Dated: 11.04.2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. No one appeared on behalf of the promoter. An email dated 11.04.2022 received from the AR of the promoter for the adjournment of the hearing due to a medical emergency in the family of the director of the company. The authority granted on week time for submission of deficit documents. The matter to come up on 18.04.2022. ADJOURNMENT View Order
02-Apr-2022 Proceedings Dated: 02.04.2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh.Ved Parkash (Admin.) is present on behalf of the promoter. The promoter has earlier sold units in the name of Shree Vardhman Buildprop Pvt. Ltd. Although, license was in the name of M/s DSS Infrastructure Pvt. Ltd. It was submitted by the promoter that the M/s DSS Infrastructure Pvt. Ltd. is a 100% subsidiary of M/s Shree Vardhman Buildprop Pvt. Ltd. The promoter was asked to submit an affidavit and proof  to that effect. The promoter is also directed to submit an affidavit that M/s DSS Infrastructure Pvt. Ltd. shall be responsible for all the obligations and liabilities of M/s Shree Vardhman Buildprop Pvt. Ltd. As BIP permission is required from the DTCP accordingly same be obtained within 3 months and all further sales shall be made by M/s DSS Infrastructure Pvt. Ltd. and requisite accounts be opened accordingly. As the license is expiring in the month of April itself, accordingly promoter is directed to obtain renewal of the license.  Similarly, the revalidation of building plans and EC and fire clearance are also required to be submitted. There are large number of deficiencies as have been pointed above, the promoter requested one week time for rectifying the deficiencies. The matter to come up on 11.04.2022. ADJOURNMENT View Order
31-Mar-2022 The matter is adjourned to 02.04.2022 ADJOURNMENT ---
28-Mar-2022 The matter is adjourned to 31.03.2022 OBJECTION ---
07-Mar-2022 Proceedings Dated: 07.03.2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Shobit Shukla is present, who however, has no authority to represent on behalf of the promoter. The deficiencies already stand conveyed to the promoter and one last opportunity is given for refusal for the permission applied for is being given failing which further necessary process shall be initiated if the deficiencies are not rectified within next two weeks. The matter to come up on 28.03.2022 ADJOURNMENT View Order
14-Feb-2022 Proceedings Dated: 14.02.2022 No one was present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. The promoter is directed to submit the deficit documents in the authority before the next date of hearing The matter to come up on 07.03.2022 ADJOURNMENT ---
10-Jan-2022 Proceedings Dated: 10.01.2022 No one was present on the behalf of the promoter. Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. There are a large number of deficiencies pending. It is noticed that the applicant is neither the license holder nor the landowner. The application has been made without any legal capacity. Authority has issued a notice to the promoter dated 15.12.2021 regarding deficiencies in the application and clarification regarding the legal capacity of the promoter to which no reply has been received in the authority till date. In view of the above, the authority has decided to issue a show-cause notice to the promoter as to why the application of registration shall not be rejected following the due procedure as provided under section-5 of the Real Estate (Regulation and Development) Act 2016 and Rule-5 of the Haryana Real Estate (Regulation and Development) Rules, 2017 with an opportunity of hearing. The matter to come up on 14.02.2022 ADJOURNMENT View Order
03-Jan-2022 Proceedings dated 03.01.2022 Amid COVID 19 and omicron pandemic, the hearing couldn’t be held on the fixed date. Some planning executives are found omicron infected. Therefore, the hearing will be held through video conferencing in the next week. The matter is adjourned to 10.01.2022 ADJOURNMENT ---
27-Dec-2021 Proceedings Dated: 27.12.2021 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case.No one was present on the behalf of the promoter. There are large number of deficiencies pending. It is brought to the notice of the authority by the architectural executive that the applicant is neither the license holder nor the land owner. The application has been made without any legal capacity and payment of deficit fee of Rs 18,69,692/- needs to be made. No online corrections have been made till date. The applicant has not submitted any reply/ clarification regarding deficiencies in application including the clarification regarding legal capacity of the applicant in the authority till date. Matter is adjourned to 03.01.2021 ADJOURNMENT ---
20-Dec-2021 No one was present on behalf of the promoter.Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case.There are large number of deficiencies pending. It is brought to the notice of the authority by the architectural executive that the applicant is neither the license holder nor the land owner. The application has been made without any legal capacity and payment of deficit fee of Rs 18,69,692/- needs to be made. A notice conveying deficiencies in the application and seeking clarification regarding the legal capacity of the applicant has already been issued to the applicant.matter is adjourned to 27.12.2021next date of hearing: 27.12.2021 EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
28-May-2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project.Sh. Ved Prakash (AR) and Sh. Sachin Jain (Director) is present on behalf of the promoter. The promoter has made requisite changes in the online DPI and had provided of all the allottees but the hard copy is yet to be submitted. The corrections in form REP-I marked on hard copy and shared with the promoter. The promoter has applied for revalidation of the building plan and paid the fees to the concerned department. The application for approval of revalidation of environmental clearance, and service plans and estimates have been made in the concerned department and the final approval is still awaited. The matter to come up on 30.05.2022.  Not Yet
28-Apr-2022 Proceedings Dated: 18.04.2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Ved Prakash (Admin.) and Sh. Shobit Shukla VP of Kautilya Finance (Financer of the project) are present on behalf of the promoter. The promoter Shree Vardhman Mantra is neither the license holder nor the BIP holder nor the collaborator. The applicant is requesting for making application in the name of the licensee company only along with requisite documents. Although the sales made by M/s Shree Vardhman are against the provisions of the Act. But the same were made before coming into force of BIP policy under low-cost housing scheme of the State Government. The project is still ongoing and to set the record right it would be better that BIP permission is obtained from the competent Authority. A show cause notice be issued for rejection of the application for grant of registration under section 5 of the Act of 2016 and read with rule 5 of Haryana Rules, 2017.  Not Yet
15-Mar-2022 Proceedings Dated: 07.03.2022 Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case. Sh. Shobit Shukla is present, who however, has no authority to represent on behalf of the promoter. The deficiencies already stand conveyed to the promoter and one last opportunity is given for refusal for the permission applied for is being given failing which further necessary process shall be initiated if the deficiencies are not rectified within next two weeks. The matter to come up on 28.03.2022 Not Yet