13-Jun-2022 |
The Authority approves the grant of registration certificate. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
30-May-2022 |
Ms. Neeraj Gautam, Architectural
Executive briefed about the facts of the project.
Sh. Ved Prakash (AR) is present on
behalf of the promoter.
Apart from attending and
rectification of above deficiencies, the promoter is advised to submit that
there are no projects registered with the Authority of the promoter and as such
no QPRs/AR are pending.
The matter to come up on 13.06.2022. |
OBJECTION |
View Order |
23-May-2022 |
Ms. Neeraj Gautam, Architectural
Executive briefed about the facts of the project.Sh. Ved Prakash (AR) and Sh. Sachin Jain
(Director) is present on behalf of the promoter. The promoter has made
requisite changes in the online DPI and had provided of all the allottees but the
hard copy is yet to be submitted. The corrections in form REP-I marked on hard
copy and shared with the promoter. The promoter has applied for revalidation of the building plan and paid the fees to the concerned department. The application
for approval of revalidation of environmental clearance, and service plans and
estimates have been made in the concerned department and the final approval is
still awaited.
The matter to come up on 30.05.2022. |
OBJECTION |
--- |
18-Apr-2022 |
Proceedings Dated: 18.04.2022
Ms. Neeraj Gautam, Architectural
Executive briefed about the facts of the project.
Sh. Ved Prakash (Admin.) and Sh.
Shobit Shukla VP of Kautilya Finance (Financer of the project) are present on
behalf of the promoter.
The promoter Shree Vardhman Mantra is
neither the license holder nor the BIP holder nor the collaborator. The
applicant is requesting for making application in the name of the licensee
company only along with requisite documents. Although the sales made by M/s
Shree Vardhman are against the provisions of the Act. But the same were made
before coming into force of BIP policy under low-cost housing scheme of the
State Government. The project is still ongoing and to set the record right it
would be better that BIP permission is obtained from the competent Authority. A
show cause notice be issued for rejection of the application for grant of
registration under section 5 of the Act of 2016 and read with rule 5 of Haryana
Rules, 2017. |
ADJOURNMENT |
View Order |
11-Apr-2022 |
Proceedings Dated: 11.04.2022
Ms. Neeraj Gautam, Architectural
Executive briefed about the facts of the project.
No one appeared on behalf of the
promoter.
An email dated 11.04.2022 received
from the AR of the promoter for the adjournment of the hearing due to a medical
emergency in the family of the director of the company. The authority granted on
week time for submission of deficit documents.
The matter to come up on
18.04.2022. |
ADJOURNMENT |
View Order |
02-Apr-2022 |
Proceedings Dated: 02.04.2022
Ms. Neeraj Gautam, Architectural
Executive briefed about the facts of the project.
Sh.Ved
Parkash (Admin.) is present on behalf of the promoter. The promoter has earlier
sold units in the name of Shree Vardhman Buildprop Pvt. Ltd. Although, license
was in the name of M/s DSS Infrastructure Pvt. Ltd. It was submitted by the
promoter that the M/s DSS Infrastructure Pvt. Ltd. is a 100% subsidiary of M/s
Shree Vardhman Buildprop Pvt. Ltd. The promoter was asked to submit an
affidavit and proof to that effect. The
promoter is also directed to submit an affidavit that M/s DSS Infrastructure
Pvt. Ltd. shall be responsible for all the obligations and liabilities of M/s
Shree Vardhman Buildprop Pvt. Ltd. As BIP permission is required from the DTCP
accordingly same be obtained within 3 months and all further sales shall be
made by M/s DSS Infrastructure Pvt. Ltd. and requisite accounts be opened
accordingly. As the license is expiring in the month of April itself,
accordingly promoter is directed to obtain renewal of the license. Similarly, the revalidation of building plans
and EC and fire clearance are also required to be submitted. There are large
number of deficiencies as have been pointed above, the promoter requested one
week time for rectifying the deficiencies. The matter to come up on
11.04.2022. |
ADJOURNMENT |
View Order |
31-Mar-2022 |
The matter is adjourned to 02.04.2022 |
ADJOURNMENT |
--- |
28-Mar-2022 |
The matter is adjourned to 31.03.2022 |
OBJECTION |
--- |
07-Mar-2022 |
Proceedings Dated: 07.03.2022
Ar. Neeraj Gautam, Associate
Architectural Executive briefed the facts about the case.
Sh. Shobit Shukla is
present, who however, has no authority to represent on behalf of the promoter.
The deficiencies already stand conveyed to the promoter and one last
opportunity is given for refusal for the permission applied for is being given
failing which further necessary process shall be initiated if the deficiencies
are not rectified within next two weeks.
The matter to come up
on 28.03.2022 |
ADJOURNMENT |
View Order |
14-Feb-2022 |
Proceedings Dated: 14.02.2022
No one was present on the
behalf of the promoter.
Ar. Neeraj Gautam, Associate
Architectural Executive briefed the facts about the case.
The promoter is directed to
submit the deficit documents in the authority before the next date of hearing
The matter to come up
on 07.03.2022 |
ADJOURNMENT |
--- |
10-Jan-2022 |
Proceedings Dated: 10.01.2022
No one was present on the behalf of the promoter.
Ar. Neeraj Gautam, Associate Architectural Executive
briefed the facts about the case. There
are a large number of deficiencies pending. It is noticed that the applicant is
neither the license holder nor the landowner. The application has been made
without any legal capacity. Authority has issued a notice to the promoter dated
15.12.2021 regarding deficiencies in the application and clarification
regarding the legal capacity of the promoter to which no reply has been
received in the authority till date.
In view of the above, the authority has decided to issue a
show-cause notice to the promoter as to why the application of registration
shall not be rejected following the due procedure as provided under section-5 of
the Real Estate (Regulation and Development) Act 2016 and Rule-5 of the Haryana
Real Estate (Regulation and Development) Rules, 2017 with an opportunity of
hearing.
The matter to come up on 14.02.2022 |
ADJOURNMENT |
View Order |
03-Jan-2022 |
Proceedings
dated 03.01.2022
Amid COVID
19 and omicron pandemic, the hearing couldn’t be held on the fixed date. Some planning
executives are found omicron infected. Therefore, the hearing will be held
through video conferencing in the next week.
The matter
is adjourned to 10.01.2022 |
ADJOURNMENT |
--- |
27-Dec-2021 |
Proceedings Dated: 27.12.2021
Ar. Neeraj Gautam, Associate Architectural
Executive briefed the facts about the case.No one was present on the behalf of the promoter.
There are large number of deficiencies
pending. It is brought to the notice of the authority by the architectural
executive that the applicant is neither the license holder nor the land owner.
The application has been made without any legal capacity and payment of deficit
fee of Rs 18,69,692/- needs to be made. No online corrections have been made
till date.
The applicant has not submitted any reply/
clarification regarding deficiencies in application including the clarification
regarding legal capacity of the applicant in the authority till date.
Matter is adjourned to 03.01.2021 |
ADJOURNMENT |
--- |
20-Dec-2021 |
No one was present on behalf of the promoter.Ar. Neeraj Gautam, Associate Architectural Executive briefed the facts about the case.There are large number of deficiencies pending. It is brought to the notice of the authority by the architectural executive that the applicant is neither the license holder nor the land owner. The application has been made without any legal capacity and payment of deficit fee of Rs 18,69,692/- needs to be made. A notice conveying deficiencies in the application and seeking clarification regarding the legal capacity of the applicant has already been issued to the applicant.matter is adjourned to 27.12.2021next date of hearing: 27.12.2021 |
EXAMINATION BY AUTHORITY |
View Order |