09-Nov-2021 |
Proceedings dated: 09.11.2021
Ms. Prachi Singh, Planning Executive briefed the
facts about the project.
Sh. Ravi Kant Kumar (Manager Business Development)
is present on behalf of the promoter.
The deficiencies conveyed to the promoter vide
letter dated 18.10.2021 have been rectified except for a few online corrections
in the DPI, REP-I (A to H) and submission of final approval of environment
clearance. The AR submitted that the proposal for grant of EC has been approved
by SEAC and final approval letter is awaited shortly. Further that the proposal
for grant of final approval is fixed before the SEIAA Committee on 15.11.2021
and thus final approval is expected in two months’ time.
Keeping in view the above facts, the authority has decided to grant registration certificate for the project with
the following condition mentioned above and directed the promoter to comply
within three months from issuance of the registration certificate. The promoter
is directed to submit the corrected DPI and REP-I (A to H) within 7 days. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |