Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
M3M SOULITUDE Sector-89, Gurugram Manesar Urban Complex, Gurugram, Haryana. GURUGRAM Harsaru ST Aawam Residency Private Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/501/233/2021/69 DATED 25.10.2021 RERA-GRG-940-2021 21-Oct-2021 19-Oct-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 22-Oct-2021 By Hand 1st Deficiency Notice
1ST HEARING ON 25.10.2021 View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/501/233/2021/69 DATED 25.10.2021 16-Nov-2021 RC Approved and Certificate Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
25-Oct-2021 An application regarding registration of residential floors project namely “M3M SOULITUDE” situated at Village-Dhunela, Sector-89, Gurugram being developed by M/s Aawam Residency Pvt. Ltd. was submitted on 21.10.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. This application for registration is a part of the affordable residential plotted colony under DDJAY which falls under license no. 32 of 2021 for area admeasuring 52.275 acres dated 03.07.2021 valid up to 02.07.2026 being issued in favour of M/s Adhikaansh Realtors Pvt. Ltd. and M/s Aawam Residency Pvt. Ltd. in collaboration with M/s Aawam Residency Pvt. Ltd. The whole license area i.e. 52.275 acres  comprises of 930 out of which M/s Aawam Residency Pvt. Ltd. applied for registration of residential floors on 216 no. unfreeze plots allotted to as per collaboration agreement executed between M/s Aawam Residency Pvt. Ltd. and M/s Aadhikash Realtors Pvt. Ltd. vide vasika no. 3875 dated 11.02.2021,  vasika no. 1870 dated 12.07.2021 and vasika no. 2523 dated 07.09.2021. On scrutiny of the application, some of the major deficiencies/observations were observed which were conveyed to the promoter vide notice no. HARERA/GGM/RPIN/ 393 dated 22.10.2021. The promoter has submitted the reply dated 25.10.2021 which was scrutinized and found that all the deficiencies are fulfilled by the promoter except the following mentioned below: - 1.      Copy of approved environmental clearance needs to be provided. 2.      Annual report the financial year 2020-21needs to be submitted. The Authority has decided to grant registration certificate for the project with the condition of submission of approved environment clearance and annual report the financial year 2020-21 within three months from issuance of the registration certificate. The promoter is advised to submit detailed project information duly binded and also fill up online DPI information at hrera.in/app1/sign_up within 7 days. APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---