20-Dec-2021 |
Sh. Ashish Kush,
Planning Executive briefed about the facts of the project.
Sh. Ajay Kumar
(Assistant Manager) is present on behalf of the promoter.
The
Authority decided to grant the registration subject to the submission of corrected
online DPI and Bank guarantee of Rs 25 lakhs on account of fire scheme approval
and Bank guarantee of Rs 25 lakhs on account of approved service plan and
estimates. The promoter shall submit the fire scheme approval and approved
service plan estimates within two months from the issuance of registration
respectively. Further, a condition shall be imposed that no withdrawal of any amount shall be allowed till
submission of above documents.
In case above approvals
are not obtained within the time mentioned above than the bank guarantee shall
be forfeited.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |
13-Dec-2021 |
Proceedings dated 13.12.2021.Sh.
Ashish Kush, Planning Executive briefed about the facts of the project.
Sh. Ajay
Kumar (Asstt. Manager) is present on behalf of the promoter.
The
Authority directed the promoter to submit the deficit documents which are
mentioned below: -
1.
The annexures in the online application
are not uploaded as well as the correction needs to be done in the online (A-H)
application.
2.
Fire Scheme approval needs to be
submitted.
3.
Approved Service Plan and Estimates
needs to be submitted.
4.
Approvals / NOC’s from various agencies
for connecting external services like sewerage disposal, Storm water needs to
be submitted.
5. Draft Allotment letter as per the
prescribed format needs to be revised.
6. Draft Builder Buyer Agreement as per the prescribed
format needs to be revised.
The
matter to come up on 20.12.2021. |
ADJOURNMENT |
--- |
07-Dec-2021 |
The matter is adjourned for 13.12.2021 |
ADJOURNMENT |
--- |
06-Dec-2021 |
The hearing is adjourned and matter to come up on 07.12.2021. |
ADJOURNMENT |
--- |
30-Nov-2021 |
The hearing is adjourned and matter to come up on 06.12.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
ADJOURNMENT |
--- |
09-Nov-2021 |
Proceedings
dated: 09.11.2021
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Ajay Kumar (Assistant Manager) is present on behalf of the promoter.
The
AR of the promoter has submitted reply on 08.11.2021 which is to be scrutinized
by the planning executive. Further the AR seeks two weeks’ time for submission
of online DPI and remaining deficit documents.
The
matter to come up on 30.11.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
ADJOURNMENT |
--- |
19-Oct-2021 |
Sh.
Ashish Kush, briefed about the facts of the case.
Sh. Ajay
Kumar (Assistant Manager) present on behalf of the promoter.
The
promoter requested for the time to comply with the deficiencies. The Authority
decided to consider the same and matter to came up on 09.11.2021.Samir Kumar (Member)Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
EXAMINATION BY AUTHORITY |
--- |