23-May-2022 |
Proceedings
dated: 23.05.2022 Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.Sh.
Balvinder Kumar (Sr. Architect) is present on behalf of the promoter.
Keeping in view, the
examination of documents by the Office and confirmation that all pre-requisites
for grant of registration have been complied with by the promoter, the
authority decides to grant the registration certificate on the condition that
the promoter shall submit the approved service plan and estimates within 3
months from the issuance of the registration certificate.Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
16-May-2022 |
Proceedings
dated: 16.05.2022 Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh.
Balvinder Kumar (Sr. Architect) is present on behalf of the promoter.
In the last hearing dated 09.05.2022, the promoter
was directed to submit the Bank Guarantee of Rs 25 lakhs, within a week for the
submission of service plan and estimates within 3 months from the issuance of
registration certificate.
The
authority had decided to grant the in-principle registration and at the same,
the authority directed the promoter to submit three binded DPI along with the
documents mentioned below:
1.
The annexures in the online application
are not uploaded as well as the correction needs to be done in the online (A-H)
application.
2.
Aks- shajra duly certified by revenue officer six months prior to
date of application needs to be submitted.
3.
Form REP-I (A to
H) Part-C needs to be corrected.
4.
Board of
directors’ report needs to be submitted.
A condition shall be imposed that no withdrawal
of any amount shall be allowed till submission of approved service plan and
estimates.
In case of failure to submit
the approved service plans and estimates within three months from the date of
issuance of registration certificate, then the amount collected from the
allottees is liable to be refunded with interest at the prescribed rate and the
registration certificate shall be treated as deemed cancelled.
The matter to come up for
compliance on 16.05.2022 and for issuing registration certificate.
The promoter stated that they
have submitted the reply today itself which needs to be scrutinized.
The matter to come up on
23.05.2022..Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) |
ADJOURNMENT |
View Order |
09-May-2022 |
Proceedings
dated: 09.05.2022
Sh. Ashish Kush, Planning
Executive briefed about the facts of the case.
Sh. Balvinder
Kumar (Senior Architect) is present on behalf of the promoter.
The
authority directed the promoter to submit the Bank guarantee of Rs 25 lakhs within
a week for the submission of service plan and estimates within 3 months from
the issuance of registration certificate.
The
authority decided to grant the in-principle registration and at the same, the
authority directed the promoter to submit three binded DPI alongwith the documents
mentioned below:
1.
The annexures in the online application
are not uploaded as well as the correction needs to be done in the online (A-H)
application.
2.
Aks- shajra duly certified by revenue officer six months prior to
date of application needs to be submitted.
3.
Form REP-I (A to
H) Part-C needs to be corrected.
4.
Board of
directors’ report needs to be submitted.
A condition shall be imposed that no withdrawal
of any amount shall be allowed till submission of approved service plan and
estimates.
In case of failure to submit
the approved service plans and estimates within three months from the date of
issuance of registration certificate, then the amount collected from the
allottees is liable to be refunded with interest at the prescribed rate and the
registration certificate shall be treated as deemed cancelled.
The matter to come up for compliance on
16.05.2022 and for issuing registration certificate.Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) |
EXAMINATION BY AUTHORITY |
View Order |