Project Name Project Location Project District Project Tehsil Promoter Name
Sapphire 82A Village Shikohpur , Sector 82 A GURUGRAM Gurgaon Ameya Commercial Projects Pvt. Ltd.
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/566/298/2022/41 DATED 23.05.2022 RERA-GRG-927-2021 05-Apr-2022 28-Mar-2022 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 28-Apr-2022 BY HAND BY HAND
The hearing is fixed for 09.05.2022. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/566/298/2022/41 DATED 23.05.2022 15-Jun-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
23-May-2022 Proceedings dated: 23.05.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case.Sh. Balvinder Kumar (Sr. Architect) is present on behalf of the promoter. Keeping in view, the examination of documents by the Office and confirmation that all pre-requisites for grant of registration have been complied with by the promoter, the authority decides to grant the registration certificate on the condition that the promoter shall submit the approved service plan and estimates within 3 months from the issuance of the registration certificate.Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
16-May-2022 Proceedings dated: 16.05.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Balvinder Kumar (Sr. Architect) is present on behalf of the promoter. In the last hearing dated 09.05.2022, the promoter was directed to submit the Bank Guarantee of Rs 25 lakhs, within a week for the submission of service plan and estimates within 3 months from the issuance of registration certificate. The authority had decided to grant the in-principle registration and at the same, the authority directed the promoter to submit three binded DPI along with the documents mentioned below: 1.       The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 2.       Aks- shajra duly certified by revenue officer six months prior to date of application needs to be submitted. 3.       Form REP-I (A to H) Part-C needs to be corrected. 4.       Board of directors’ report needs to be submitted. A condition shall be imposed that no withdrawal of any amount shall be allowed till submission of approved service plan and estimates. In case of failure to submit the approved service plans and estimates within three months from the date of issuance of registration certificate, then the amount collected from the allottees is liable to be refunded with interest at the prescribed rate and the registration certificate shall be treated as deemed cancelled. The matter to come up for compliance on 16.05.2022 and for issuing registration certificate. The promoter stated that they have submitted the reply today itself which needs to be scrutinized. The matter to come up on 23.05.2022..Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) ADJOURNMENT View Order
09-May-2022 Proceedings dated: 09.05.2022 Sh. Ashish Kush, Planning Executive briefed about the facts of the case. Sh. Balvinder Kumar (Senior Architect) is present on behalf of the promoter. The authority directed the promoter to submit the Bank guarantee of Rs 25 lakhs within a week for the submission of service plan and estimates within 3 months from the issuance of registration certificate. The authority decided to grant the in-principle registration and at the same, the authority directed the promoter to submit three binded DPI alongwith the documents mentioned below: 1.       The annexures in the online application are not uploaded as well as the correction needs to be done in the online (A-H) application. 2.       Aks- shajra duly certified by revenue officer six months prior to date of application needs to be submitted. 3.       Form REP-I (A to H) Part-C needs to be corrected. 4.       Board of directors’ report needs to be submitted. A condition shall be imposed that no withdrawal of any amount shall be allowed till submission of approved service plan and estimates. In case of failure to submit the approved service plans and estimates within three months from the date of issuance of registration certificate, then the amount collected from the allottees is liable to be refunded with interest at the prescribed rate and the registration certificate shall be treated as deemed cancelled. The matter to come up for compliance on 16.05.2022 and for issuing registration certificate.Member (Vijay Kumar Goyal)Chairman (Dr.. K.K. Khandelwal) EXAMINATION BY AUTHORITY View Order