| 29-Sep-2021 |
Sh. Naresh Kumar briefed about the facts of the project. Mr. Ashok
Kumar managing director of the company and Ms. Aditi Sharma Company Secretary
are present on behalf of the promoter. The promoter has obtained In-Principal Approval of
Beneficial Interest Permission from the DTCP
and requested to submitted the final BIP with in 3 months from the date
of grant of permission under section 7(3). Keeping in view of the above and
recommendation made by the expert/consultant and chartered accountant of the
authority, the authority has decided to grant the registration of the project. |
EXTENSION APPROVED |
--- |
| 24-Sep-2021 |
The matter is adjourned and
to be taken up on 29.09.2021. |
ADJOURNMENT |
--- |
| 08-Sep-2021 |
Sh. Naresh Kumar
briefed about the facts of the project. Mr. Ashok Kumar managing director of
the company and Ms. Aditi Sharma Company Secretary are present on behalf of the
promoter. The Promoter is directed to submit the deficit documents with in 15
days. The matter is to be taken up on 24.09.2021. |
ADJOURNMENT |
--- |
| 01-Sep-2021 |
Sh. Naresh
Kumar briefed about the facts of the project. Mr. Ashok Kumar managing director
of the company and Ms. Aditi Sharma Company Secretary are present on behalf of
the promoter. The online detailed project information was filled by the promoter which was discussed in
the hearing. Further, some discrepancies
were noted in the Detailed Project Information by the authority and the
promoter was directed to resolve or remove the same. The matter is to be taken
up on 08.09.2021. |
EXAMINATION BY AUTHORITY |
--- |