19-Jan-2022 |
Sh. Ashish Kush, Planning
Executive briefed about the facts of the case.
Sh. Balvinder
Kumar (Senior Architect) joined the proceedings through VC on behalf of the
promoter.
The promoter submitted the
Bank guarantee on 07.01.2022 of Rs 25 lacs on account of submission of approved
service plan and estimates within three months of the issuance of registration
certificate.
The
authority decides to grant the registration certificate subject to the
corrections in online DPI. Further, a condition
shall be imposed that no withdrawal of any amount shall be allowed till
submission of above documents.
In case of failure to submit
the approved service estimates and plans within three months from the date of
issuance of registration certificate, then the amount collected from the
allottees is liable to be refunded with interest at the prescribed rate and the
registration certificate shall be treated as deemed cancelled.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
17-Jan-2022 |
The matter is Adjourned to 19.01.2022. |
ADJOURNMENT |
View Order |
10-Jan-2022 |
Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh. Balvinder
(Sr. Architect) is present on behalf of the promoter.
On
examining the online DPI, some discrepancies are observed which has been
conveyed to the promoter. While examining the bank undertaking, it is observed
that the document found not to be in order. Therefore, authority directed Sh.
Shiv rattan Tanwar to get the bank undertaking verified from the concerned bank
as well as directed the promoter to do the same. Further, the authority
directed the promoter to submit the corrected online DPI. The matter to come up
on 17.01.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
View Order |
21-Dec-2021 |
Proceedings
dated: 21.12.2021.
Sh. Ashish Kush,
Planning Executive briefed about the facts of the case.
Sh. Balvinder
(Sr. Architect) is present on behalf of the promoter.
The promoter
stated that they have submitted the fire scheme approval. The AR of the
promoter submitted that the service plan and estimates approval may take some
time and they are willing to give an undertaking along with a bank guarantee of
Rs. 25 lakhs to submit the approval within 2 months of grant of registration.
The online DPI has not been filled up. After doing the needful hard copy PDF
file of online information be submitted to the Authority along with correction
in the A to H format.
The
matter to come up on 10.01.2022.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
View Order |
23-Nov-2021 |
The hearing is
adjourned and matter to come up on 21.12.2021. |
ADJOURNMENT |
View Order |
09-Nov-2021 |
Proceedings
dated: 09.11.2021
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh. Balvinder
(Senior Architecture) is present on behalf of the promoter.
The reply to the deficiency notice has been submitted today i.e.
09.11.2021. The approval of fire clearance is still awaited along with approval
of service plan and estimates. The corrections in online DPI and form A to H are
to be made by the AR and thereafter to be cross checked/confirmed by planning
executive. In meanwhile, the AR is required to submit copy of fire scheme approval
and service plan and estimates as well. The AR seeks two weeks’ time for their
submission.
The matter to come up on 23.11.2021.Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |