| 28-Sep-2022 |
Ms. Asha, Chartered Accountant briefed about the
project.
Sh. Narender Singh
(CS), Sh. Anil Kailey (Consultant) and Sh. Vikaram Kumar (Accountant) are
present on behalf of the promoter.
In View of the
recommendation made above the Authority has decided to permit the registration
certificate remain in force. On the basis of facts narrated above in the brief
by the chartered accountant and after considering the reason for delay in
completing the project within the time declared by the promoter under section
4(2)(l)(C) and even after lapse of admissible extension time of one year and
also giving an opportunity of hearing in this regard to the promoter in the
preceding hearings Authority decided to impose penalty of Rs. 25 Lakh for
violation of section 4 to be deposited as mentioned in the recommendation of
the expert/consultant assign the work of examining due diligence report. This
will be without prejudice to the rights of the individual allottees under
section 18(1) of the RERA Act which shall continue to be governed by the BBAs
signed with individual allottees. |
EXTENSION APPROVED |
View Order |
| 13-Sep-2022 |
Sh. Naresh Kumar,
Chartered Accountant and Ms. Asha, Chartered
Accountant briefed about the project.
None is
present on behalf of the promoter. An email request dated 13.09.2022 has been
received from the promoter requesting for an adjournment. It is seen that a
large number of deficiencies (including compliance under section 4(2)(l)(D) of
the Act for the year 2020-21) still exist. It is also observed that deficit
fees of Rs. 4,72,372/- has also not been deposited by the promoter.
One last opportunity
of 2 weeks is granted to the promoter to complete the pending documentation and
deposit the requisite fee. The promoter must deposit the deficit fee within one
week.
The matter to come
up on 28.09.2022. |
ADJOURNMENT |
--- |
| 02-Aug-2022 |
MATTER IS ADJOURNED TO 13.09.2022. |
ADJOURNMENT |
--- |
| 08-Sep-2021 |
The matter will be adjourned and heared on 02.08.2022 |
ADJOURNMENT |
--- |
| 20-Jul-2021 |
The matter will be fixed as on 08-09-2021 |
EXAMINATION BY AUTHORITY |
--- |