| 04-Oct-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh. Bharat Kumar (Director) is
present on behalf of the promoter.
The Promoter M/s Spaze Towers Pvt. Ltd. who is a license Holder applied for the
extension of registration of real estate project namely “Tristaar”
located at Sector-92, Gurugram under section 6 of the Real Estate (Regulations
and Development) Act, 2016 vide central receipt no. 10513/20038 dated
21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-523-2019
and online generated for project extension temp id RERA-GRG-883-2021. The
project area for registration is same as that of the licensed area i.e. 2.71875
acres. License no – 72 of 2013 dated 27.07.2013. The application for extension
of registration was scrutinized and 1st deficiency notice vide no.
HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021 was issued to the
promoter with an opportunity of being heard on 20.07.2021. The promoter
submitted a reply on 13.07.2021 which was scrutinized, and remaining deficiencies
were conveyed to the promoter.
On 20.07.2021, the promoter submitted a
request for the adjournment and the authority grants the same and fixed the
matter for 03.08.2021. No reply was submitted by the promoter after the last
hearing. On 03.08.2021, the hearing was adjourned and fixed for 10.08.2021. On
10.08.2021, the matter was adjourned for 12.08.2021. On 12.08.2021, the matter
was adjourned for 17.08.2021. On 17.08.2021, The LR of the promoter submitted that
the application for grant of extension of registration was submitted in the
Authority on 12.01.2021 and in support of that she is submitting the online
receipt of the application which was taken on record. Later on due to expiry of
DD file was returned with certain observations and was submitted on 21.01.2021.
The date for submission of application for grant of extension of registration
be treated as 12.01.2021 and accordingly standard fee for late submission of
application be calculated. On the request of the AR of the promoter two weeks’
time was granted for attending deficiencies. The matter to come up on
31.08.2021. On 31.08.2021, the matter is adjourned and fixed for 07.09.2021. On
07.09.2021, It was decided that regarding standard fee for late submission of
application calculation be made and the same be deposited within a week and the
matter was fixed for 21.09.2021. On 21.09.2021, the promoter request for
one-week time and the authority grants the same and matter is fixed for
27.09.2021. On 27.09.2021, the authority directed the promoter to submit the
deficit fee- Rs 6,96,639/- and Pert Chart. The matter to come up on 04.10.2021.
The Occupation Certificate of the project has
already been received on 03.05.2021. The Authority decided to grant extension
subject to authentication of online DPI and submission of deficit fee of Rs.
6,96,639/- and giving the date for completion of the project. Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
EXTENSION APPROVED |
--- |
| 27-Sep-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh. Chandra Shekhar Sharma
(DGM Legal) is present on behalf of the promoter.
The Promoter M/s Spaze
Towers Pvt. Ltd. who is a license Holder
applied for the extension of registration of real estate project namely
“Tristaar” located at Sector-92, Gurugram under section 6 of the Real Estate
(Regulations and Development) Act, 2016 vide central receipt no. 10513/20038
dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H) is RERA
-GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the
licensed area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was scrutinized and 1st deficiency
notice vide notice no. HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021
was issued to the promoter with an opportunity of being heard on 20.07.2021.
The promoter submitted a reply on 13.07.2021 which was scrutinized and
remaining deficiencies were conveyed to the promoter.
On 20.07.2021, the promoter
submitted a request for the adjournment and the authority grants the same and
fixed the matter for 03.08.2021. No reply was submitted by the promoter after
the last hearing. On 03.08.2021, the hearing was adjourned and fixed for
10.08.2021. On 10.08.2021, the matter was adjourned for 12.08.2021. On
12.08.2021, the matter was adjourned for 17.08.2021. On 17.08.2021, The LR of
the promoter submitted that the application for grant of extension of
registration was submitted in the Authority on 12.01.2021 and in support of
that she is submitting the online receipt of the application which was taken on
record. Later on due to expiry of DD file was returned with certain
observations and was submitted on 21.01.2021. The date for submission of
application for grant of extension of registration be treated as 12.01.2021 and
accordingly standard fee for late submission of application be calculated. On
the request of the AR of the promoter two weeks’ time was granted for attending
deficiencies. The matter to come up on 31.08.2021. On 31.08.2021, the
matter is adjourned and fixed for 07.09.2021.
Regarding standard fee for
late submission of application calculation be made and the same be deposited
within a week and matter is fixed for 21.09.2021. On 21.09.2021, the promoter
request for one week time and the authority grants the same and matter is fixed
for 27.09.2021.
The authority directed the
promoter to submit the deficit fee- Rs 6,96,639/- and Pert Chart. The matter to
come up on 04.10.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
| 21-Sep-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh. Chander Shekhar Sharma
(DGM Legal) and Ms. Priyanka Aggarwal, LR are present on behalf of the
promoter.
The Promoter M/s Spaze
Towers Pvt. Ltd. who is a license Holder
applied for the extension of registration of real estate project namely
“Tristaar” located at Sector-92, Gurugram under section 6 of the Real Estate
(Regulations and Development) Act, 2016 vide central receipt no. 10513/20038
dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H) is RERA
-GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the
licensed area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was scrutinized and 1st deficiency
notice vide notice no. HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021
was issued to the promoter with an opportunity of being heard on 20.07.2021.
The promoter submitted a reply on 13.07.2021 which was scrutinized and
remaining deficiencies were conveyed to the promoter.
On 20.07.2021, the promoter
submitted a request for the adjournment and the authority grants the same and
fixed the matter for 03.08.2021. No reply was submitted by the promoter after
the last hearing. On 03.08.2021, the hearing was adjourned and fixed for
10.08.2021. On 10.08.2021, the matter was adjourned for 12.08.2021. On
12.08.2021, the matter was adjourned for 17.08.2021. On 17.08.2021, The LR of
the promoter submitted that the application for grant of extension of
registration was submitted in the Authority on 12.01.2021 and in support of
that she is submitting the online receipt of the application which was taken on
record. Later on due to expiry of DD file was returned with certain
observations and was submitted on 21.01.2021. The date for submission of
application for grant of extension of registration be treated as 12.01.2021 and
accordingly standard fee for late submission of application be calculated. On
the request of the AR of the promoter two weeks’ time was granted for attending
deficiencies. The matter to come up on 31.08.2021. On 31.08.2021, the
matter is adjourned and fixed for 07.09.2021.
Regarding standard fee for
late submission of application calculation be made and the same be deposited
within a week and matter is fixed for 21.09.2021. On 21.09.2021, the promoter
request for one week time and the authority grants the same and matter is fixed
for 27.09.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
OBJECTION |
--- |
| 07-Sep-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh. Chander Shekhar Sharma
(DGM Legal) and Ms. Priyanka Aggarwal, LR are present on behalf of the
promoter.
The Promoter M/s Spaze
Towers Pvt. Ltd. who is a license Holder
applied for the extension of registration of real estate project namely
“Tristaar” located at Sector-92, Gurugram under section 6 of the Real Estate
(Regulations and Development) Act, 2016 vide central receipt no. 10513/20038
dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H) is RERA
-GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the
licensed area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was scrutinized and 1st deficiency notice
vide notice no. HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021 was
issued to the promoter with an opportunity of being heard on 20.07.2021. The
promoter submitted a reply on 13.07.2021 which was scrutinized and remaining
deficiencies were conveyed to the promoter.
On 20.07.2021, the promoter
submitted a request for the adjournment and the authority grants the same and
fixed the matter for 03.08.2021. No reply was submitted by the promoter after
the last hearing. On 03.08.2021, the hearing was adjourned and fixed for
10.08.2021. On 10.08.2021, the matter was adjourned for 12.08.2021. On
12.08.2021, the matter was adjourned for 17.08.2021. On 17.08.2021, The LR of
the promoter submitted that the application for grant of extension of
registration was submitted in the Authority on 12.01.2021 and in support of
that she is submitting the online receipt of the application which was taken on
record. Later on due to expiry of DD file was returned with certain
observations and was submitted on 21.01.2021. The date for submission of
application for grant of extension of registration be treated as 12.01.2021 and
accordingly standard fee for late submission of application be calculated. On
the request of the AR of the promoter two weeks’ time was granted for attending
deficiencies. The matter to come up on 31.08.2021. On 31.08.2021, the
matter is adjourned and fixed for 07.09.2021.
Regarding standard fee for
late submission of application calculation be made and the same be deposited
within a week.
The matter to come up on
21.09.2021..Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
| 31-Aug-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Chander Shekhar Sharma (DGM Legal) and Ms. Priyanka Aggarwal, LR are present on
behalf of the promoter.
The Promoter M/s Spaze Towers Pvt. Ltd. who is a license holder applied for the
extension of registration of real estate project
namely “Tristaar” located at Sector-92, Gurugram under section 6 of the Real
Estate (Regulations and Development) Act, 2016 vide central receipt no.
10513/20038 dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H)
is RERA -GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the licensed
area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was received on 21.06.2021 and was scrutinized
and 1st deficiency notice vide notice no.
HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021 was issued to the
promoter with an opportunity of being heard on 20.07.2021. The promoter
submitted a reply on 13.07.2021 which was scrutinized and deficiencies are
mentioned below:
1.
Deficit fee- Rs 15,68,136/-
2.
Corrections in form REP-V
needs to be done.
3.
PERT chart needs to be
revised.
4.
List of sold/ unsold
inventory needs to be submitted along with particulars mentioned in sold
inventory i.e. unit no, carpet area,
name of customer, tower no., total sale value of unit, amount to be received
from customer up to date i.e. 15.06.2021.
On 20.07.2021, the promoter submitted a
request for the adjournment and the authority grants the same and fixed the
matter for 03.08.2021. No reply was submitted by the promoter after the last
hearing. On 03.08.2021, the hearing was adjourned and fixed for 10.08.2021. On
10.08.2021, the matter was adjourned for 12.08.2021. On
12.08.2021, the matter was adjourned and fixed for 17.08.2021.
The
LR of the promoter submitted that the application for grant of extension of
registration was submitted in the Authority on 12.01.2021 and in support of
that she is submitting the online receipt of the application which was taken on
record. Later on due to expiry of DD file was returned with certain
observations and was submitted on 21.01.2021. The date for submission of
application for grant of extension of registration be treated as 12.01.2021 and
accordingly standard fee for late submission of application be calculated.
On
the request of the AR of the promoter two weeks time was granted for attending
deficiencies.
The matter to come up on 31.08.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal). The matter adjourned from 31.08.2021 to 07.09.2021. |
OBJECTION |
--- |
| 17-Aug-2021 |
Sh.
Ashish Kush, Planning Executive briefed the facts about the project.
Sh.
Chander Shekhar Sharma (DGM Legal) and Ms. Priyanka Aggarwal, LR are present on
behalf of the promoter.
The Promoter M/s Spaze Towers Pvt. Ltd. who is a license holder applied for the
extension of registration of real estate project
namely “Tristaar” located at Sector-92, Gurugram under section 6 of the Real
Estate (Regulations and Development) Act, 2016 vide central receipt no.
10513/20038 dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H)
is RERA -GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the licensed
area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was received on 21.06.2021 and was scrutinized
and 1st deficiency notice vide notice no.
HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated 30.06.2021 was issued to the
promoter with an opportunity of being heard on 20.07.2021. The promoter
submitted a reply on 13.07.2021 which was scrutinized and deficiencies are
mentioned below:
1.
Deficit fee- Rs 15,68,136/-
2.
Corrections in form REP-V
needs to be done.
3.
PERT chart needs to be
revised.
4.
List of sold/ unsold
inventory needs to be submitted along with particulars mentioned in sold
inventory i.e. unit no, carpet area,
name of customer, tower no., total sale value of unit, amount to be received
from customer up to date i.e. 15.06.2021.
On 20.07.2021, the promoter submitted a
request for the adjournment and the authority grants the same and fixed the
matter for 03.08.2021. No reply was submitted by the promoter after the last
hearing. On 03.08.2021, the hearing was adjourned and fixed for 10.08.2021. On
10.08.2021, the matter was adjourned for 12.08.2021. On
12.08.2021, the matter was adjourned and fixed for 17.08.2021.
The
LR of the promoter submitted that the application for grant of extension of
registration was submitted in the Authority on 12.01.2021 and in support of
that she is submitting the online receipt of the application which was taken on
record. Later on due to expiry of DD file was returned with certain
observations and was submitted on 21.01.2021. The date for submission of
application for grant of extension of registration be treated as 12.01.2021 and
accordingly standard fee for late submission of application be calculated.
On
the request of the AR of the promoter two weeks time was granted for attending
deficiencies.
The matter to come up on 31.08.2021.Member (Samir Kumar)Member (Vijay Kumar Goyal)Chairman (Dr. K.K. Khandelwal) |
ADJOURNMENT |
--- |
| 12-Aug-2021 |
Matter adjourned for 17.08.2021 |
ADJOURNMENT |
--- |
| 10-Aug-2021 |
Matter adjourned for 12.08.2021 |
ADJOURNMENT |
--- |
| 03-Aug-2021 |
Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 10.08.2021. |
ADJOURNMENT |
--- |
| 20-Jul-2021 |
Sh. Ashish Kush, Planning Executive briefed the
facts about the project.
No one is present on behalf of the promoter.
The Promoter M/s Spaze Towers Pvt. Ltd. who is a license Holder applied for the
extension of registration of real estate project
namely “Tristaar” located at Sector-92, Gurugram under section 6 of the Real
Estate (Regulations and Development) Act, 2016 vide central receipt no.
10513/20038 dated 21.06.2021 and RPIN-342. The Temp I.D. of REP – I (Part A-H)
is RERA -GRG-PROJ-523-2019 and online generated for project extension temp id
RERA-GRG-883-2021. The project area for registration is same as that of the
licensed area i.e. 2.71875 acres. License no – 72 of 2013 dated 27.07.2013. The
application for extension of registration was scrutinized and 1st
deficiency notice vide notice no. HARERA/GGM/REP/RC/247/2017/EXT/342/2021 dated
30.06.2021 was issued to the promoter with an opportunity of being heard on
20.07.2021. The promoter submitted a reply on 13.07.2021 which was scrutinized
and deficiencies are mentioned below:
1.
Deficit fee- Rs 15,68,136/-
2.
Corrections in form REP-V needs to be
done.
3.
PERT chart needs to be revised.
4.
List of sold/ unsold inventory needs to
be submitted along with particulars mentioned in sold inventory i.e. unit no, carpet area, name of customer, tower
no., total sale value of unit, amount to be received from customer up to date
i.e. 15.06.2021.
Due to unavoidable circumstances concerning directors not able to attend
the hearing and promoter request has been received from the promoter on
19.07.2021 for the adjournment of two weeks. The Authority considered the
request for the adjournment and matter to come up on 03.08.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman) |
EXAMINATION BY AUTHORITY |
--- |