13-Jul-2021 |
An application
regarding registration of residential floors project namely “Signature Global
City 37D Phase-1” situated at Village Gadauli Sector-37D, Distt. Gurugram being
developed by M/s Signature Global Developers Pvt. Ltd. was submitted on
25.06.2021 under section 4 of Real Estate (Regulation and Development), Act
2016. This application for registration is a part of the affordable residential
plotted colony under DDJAY which falls under license no. 08 of 2021 for area
admeasuring 20.589 acres dated 05.03.2021 valid up to 04.03.2026 being issued
in favour of M/s Lalwani Brothers Buildcon LLP and M/s Unistay Hospitality Pvt.
Ltd. in collaboration M/s Signature Global Developers Pvt. Ltd. The project
comprises of 324 plots out of which 166 plots are frozen and 158 plots are
unfrozen.
The application
submitted by the promoter for the said project contains 158 unfrozen plots on
which total of 632 units and 212 commercial units on are to be constructed.
On scrutiny of the application, some of the
major deficiencies/observations were observed which were conveyed to the
promoter vide notice no. HARERA/GGM/RPIN/344 dated 02.07.2021. The promoter has
submitted the reply dated 09.07.2021 and 12.07.2021 for the deficiencies after
scrutiny of the reply following deficiencies are still pending: -
1. Copy of approved service plans and
estimates/sanction letter needs to be provided.
2. Copy of approved environmental clearance needs to be
provided.
3. Copy of approved fire scheme approval/sanction
letter for commercial area need to be provided.
4. Copy of building plan (BR-III) of residential
plots i.e., Type C79-80 and commercial area i.e., 0.824 acres needs to be
provided.
5.
An undertaking from the company that 10% of the total receipt in Separate
RERA compliant account has been credited to the Haryana Government treasury
against the EDC dues until it is fully paid.
The Authority decided to grant conditional registration
certificate for the project with the following conditions mentioned above and directed
the promoter to comply within three months from issuance of the registration
certificate.
The promoter is advised to submit detailed project
information duly binded and also fill up online DPI information at
hrera.in/app1/sign_up within 7 days. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |