| 15-Mar-2022 |
Proceedings Dated: 15.03.2022
Sh. Rahul Sharma (Manager-Compliance) is present on
behalf of the promoter. Regarding
penalty for late submission of REP-I (Part A to H) after 31.12.2019 as per show
cause notice RERA-GRG-5452-2019, the AR of the promoter submits that he was not
able to file the form within prescribed time due to COVID-19 pandemic. As per
order no. 9/3 -2020 HARERA/GGM (Admn.) dated 26.05.2020, the Authority granted
relaxation of six months due to COVID-19 relaxation. Therefore, the promoter is
directed to submit the late fee of Rs. 15,50,000/- in the Authority.
The Authority decided to grant extension of
registration under section 6 of Real Estate (Regulation and
Development) Act, 2016 subject to submission of late fee of Rs. 15,50,000/-
before issuance of extension certificate. |
EXTENSION APPROVED |
--- |
| 07-Mar-2022 |
Sh. Rahul Sharma (Manager)
is present on behalf of the promoter. Regarding renewal of building plan, the
AR of the promoter submits that the compounding fee of building plan has been
submitted in the competent authority and subsequently obtained the provisional
OC for 4 towers namely T-20, T-21, T-24 and T-25. Copy of the receipt of compounding
fee and the copy of provisional OC has already been submitted by the promoter
in the Authority. Regarding deficit fee of Rs. 11, 03, 765/-, it has been
submitted by the AR of the promoter that the said fee has been deposited on
25.01.2022 vide RTGS No. RTGS/INDBR22022012500478617. Corrections in online DPI
and REP-I (Part A-H) has been conveyed to the promoter and marked on the
submitted copy. The promoter is directed to submit the corrected copy in the
authority before next date of hearing. Matter will be heard on 15.03.2022. |
OBJECTION |
--- |
| 25-Jan-2022 |
The
matter adjourned for 07.03.2022. |
OBJECTION |
--- |
| 30-Nov-2021 |
Matter adjourned for 25.01.2022. |
OBJECTION |
--- |
| 09-Nov-2021 |
Proceedings Dated: 09.11.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about
the facts of the project.
No one appeared on behalf of the promoter. An
email dated 09.11.2021 sent by the promoter requesting three weeks’ time for
the submission of deficit documents. Matter adjourned for 30.11.2021. |
ADJOURNMENT |
--- |
| 02-Nov-2021 |
The matter will be heard 09.11.2021. |
OBJECTION |
--- |
| 12-Oct-2021 |
Proceedings Dated: 12.10.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma (Manager) is present on behalf of the
promoter.
The deficiencies have still not been attended by
the promoter. The promoter is directed to submit the online detailed project
information along with deficit documents which were conveyed vide 1st
deficiency notice dated 21.04.2021. The matter to come up on 02.11.2021. |
OBJECTION |
--- |
| 27-Sep-2021 |
Proceedings Dated: 27.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma (Manager) is present on behalf of the
promoter.
The promoter is directed to submit the deficit
documents before next date of hearing. Matter adjourned for 12.10.2021. |
OBJECTION |
--- |
| 21-Sep-2021 |
Proceedings Dated: 21.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma (Manager) is present on behalf of the
promoter.
The promoter requested for one week time to
submit the reply. The matter decided to come up on 27.09.2021. |
OBJECTION |
--- |
| 07-Sep-2021 |
Proceedings Dated: 07.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma (Manager) is present on behalf of the
promoter.
The promoter requested for 3 weeks’ time. The
matter to come up on 21.09.2021. |
OBJECTION |
--- |
| 17-Aug-2021 |
Proceedings Dated: 17.08.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. Rahul Sharma (Manager) is present on behalf of the
promoter.
An application regarding extension of registration of group
housing colony project namely “Park Terra” situated at sector 37D, Gurugram
being developed by M/s Countrywide Promoters Pvt Ltd was submitted on
15.04.2021 under section 6 of Real Estate (Regulation and Development), Act
2016.
The application for extension of registration was scrutinized by
the authority and deficiencies were noticed, which were conveyed to the
promoter vide notice no. HARERA/GGM/RPIN/326 dated 21.04.2021 with directions
to remove the deficiencies within 7 days. Also, an opportunity of online
hearing was offered on 10.05.2021 at 02:00 pm in the office of HARERA,
Gurugram.
The promoter has not submitted the reply of 1st deficiency notice
till date.
On the request of the AR promoter, three weeks time is granted for
removing the deficiencies.
The matter to come up on 07.09.2021. |
ADJOURNMENT |
--- |
| 12-Aug-2021 |
Matter adjourned for 17.08.2021 |
ADJOURNMENT |
--- |
| 10-Aug-2021 |
Matter adjourned for 12.08.2021 |
OBJECTION |
--- |
| 10-May-2021 |
Due to
Covid-19 pandemic, authority meeting could not be held. Now, the authority has
decided to fix the matter on 10.08.2021. The promoter has not submitted the
reply of 1st deficiency notice till date. |
EXAMINATION BY AUTHORITY |
--- |