Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
ComMERCIAl COLoNY (SS OMNIA) SECTOR 86, BADHA, GURUGRAM GURUGRAM SS GROUP PVT LTD
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-836-2021 12-Mar-2021 12-Mar-2021 EXTENSION APPROVED NOT REQUIRED Not Yet -- 1st deficiency notice sent on 10.03.2021
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
23-Aug-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project.  The Promoter M/s SS Group Pvt. Ltd. who is a license holder applied for the extension of registration of real estate project namely “SS Omnia” located at Sector-86, Gurugram under section 6 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 9767/16859 dated 28.02.2021 and RPIN-304. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-383-2021 and online generated for project extension temp id RERA-GRG-836-2021. The project area for registration is same as that of the licensed area i.e. 2.91875 acres. License no – 94 of 2017 dated 28.08.2017.  The Authority decided to grant the extension on the condition that the promoter shall submit the renewal of license, revalidated building plan approval and details of all three accounts- Master Account, Separate RERA compliant account, Free account within 2 months from the date of grant of extension certificate.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)                                                                                                                                                                                                                                                                                                                                                       EXTENSION APPROVED ---
20-Jul-2021 Sh. Ashish Kush, Planning Executive briefed the facts about the project. None is present on behalf of the promoter. The Promoter M/s SS Group Pvt. Ltd. who is a license holder applied for the extension of registration of real estate project namely “SS Omnia” located at Sector-86, Gurugram under section 6 of the Real Estate (Regulations and Development) Act, 2016 vide central receipt no. 9767/16859 dated 28.02.2021 and RPIN-304. The Temp I.D. of REP – I (Part A-H) is RERA -GRG-PROJ-383-2021 and online generated for project extension temp id RERA-GRG-836-2021. The project area for registration is same as that of the licensed area i.e. 2.91875 acres. License no – 94 of 2017 dated 28.08.2017. The application for extension of registration was scrutinized and 1st deficiency notice vide notice no. HARERA/GGM/REP/RC/94/2017/EXT/304/2021 dated 10.03.2021 was issued to the promoter with an opportunity of being heard on 22.03.2021. On 22.03.2021 the promoter requested for 20 days for removing the deficiencies. The authority decided to send show cause notice and matter is fixed for 12.04.2021. On 12.04.2021, no one is present on behalf of the promoter. The authority to issue show cause notice and matter is fixed for 17.05.2021. On 12.04.2021, the promoter submitted the reply. After scrutiny of the reply following deficiencies are observed which are mentioned below: 1.      Licence no. 113 of 2013 dated 30.12.2013 valid up to 29.12.2019. Renewal of license need to be submitted. 2.      Booking list of units sold to the allottees as on date of the application applied for extension which includes name of the allottees, flat no., tower no., carpet area/super area, date of booking.  3.      Details of unsold units need to be provided. 4.      Renewal of BR-III need to be submitted. 5.      Details of all the three escrow accounts needs to be provided i.e. Master Account, Separate RERA Compliant account, Free Account. 6.      Details of units sold needs to be provided i.e. Name of customer, tower no., Total sale Value of units, Amount received from customer, Amount to be received from customer up to date i.e. 31.12.2020.   7.      Details of financial progress in REP-V form no matched with the REP-1 (A to H) Part-C. Expenditure up to the date of registration needs to be filled correctly. 8.      Audit report under section 4(2)(l)(D) for the financial year 2018-19 and 2019-20 needs to be provided as per new format. 9.      Online application REP-I (A-H) needs to be corrected. On 17.05.2021 the hearing is adjourned due to COVID-19 and matter is fixed for 20.07.2021. The Authority considered the reasons for delay in completing the project. Following three reasons for delay have been mentioned as under: 1.      Effect of COVID-19 Pandemic. 2.      Due to delay in obtaining environmental clearance, the completion of the project got delayed 3.      Due to non-payment of dues by the allottees, the realization could not be made on time and so the construction got slowed.    Regarding COVID-19 additional six months have already been allowed. Still the project is not complete. Environmental clearance is to be obtained by the promoter before registration. Although, the Interim RERA Panchkula allowed the registration and promoter is duty bound to obtain environmental clearance. This reason has no force as the date of commencement of the project has been mentioned as 04.02.2015 and environmental clearance has been obtained on 24.10.2017 whereas the project was registered by RERA as ongoing project on 28.08.2017. That is the promoter already started construction on 04.02.2015 even before obtaining environmental clearance. When the revised timelines were submitted by the promoter at the time of registration with RERA it was known to the promoter that environmental clearance is not there. Environmental clearance was obtained within 2 months of registration. Accordingly, this argument also has no force. The resources for the project are to be arranged by the promoter and there is not even a single complaint filed with the Authority where the promoter has come to the Authority for issuing directions to the allottees to make payment along with interest at the prescribed rate. No supporting documents have been given by the promoter to justify the reason as the project has been delayed because of non payment of allotment by the allottees.   The reasons for delay in implementing the project and failure to complete the same within the time period declared by the promoter under section 4(2)(l)(C)  found not to be reasonable and with sufficient cause. Show cause notice be issued as why penal proceeding be not issued for violation of section 4 and for not completing the project within the period declared by the promoter under section 4(2)(l)(C). The matter to come up on 23.08.2021.Vijay Kumar Goyal (Member)Dr. K.K. Khandelwal (Chairman)                                                                                                                                                                                                                                                                                                                                                       ADJOURNMENT ---
17-May-2021 The hearing is adjourned and fixed for 20.07.2021.                                                                                                                                                                                                                                                                                                                                                             OBJECTION ---
12-Apr-2021 Proceedings dated  12.04.2021No one is present on behalf of the promoter. Mr. Ashish Kush, Planning Executive briefed the facts of the case. The application for grant of extension of registration was considered by the Authority on 22.03.2021 and 12.04.2021. Deficiencies conveyed to the promoter on 10.03.2021 on the earlier hearing 20 days period was requested for rectifying the defects. No reply has been received so far and position of defects remains as such as has been conveyed to the promoter and also mentioned in the today's agenda. No one appeared on behalf of the promoter and also no communication received. The Authority decided to issue a show cause notice for rejection of application for extension  under section 6 read with proviso to rule 6(3)  To remove the defects otherwise application for grant of extension shall be rejected. If you have to say any in the matter you are by given an opportunity of hearing in the matter on 17.05.2021. After the hearing authorised representative of the promoter submitted a reply on the reception counter  which may be taken on record to be examined by the office. As per the statement of the authorised representative even now all the deficiencies have not been removed. In the show cause notice the deficiencies still remain to be attended be mentioned.  Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member)                                                                                                                                                                                                                                                                                                                                                                       OBJECTION ---
22-Mar-2021 Ms. Aditi Sharma, Company Secretary is present on behalf of the promoter with due authorization. Deficiencies have already been conveyed to the promoter. No reply has been received so far. The promoter requested for twenty days time for removing the deficiencies.  License has expired, building plans validity also expired. The time period declared by the promoter under section 4(2)(l)(C) has expired on 27.8.2020. A grace period of six months due to COVID situation was granted to the promoter which also expired on 27.2.2021. The reason quoted by the promoter for not completing the project in time do not seems to be reasonable after considering the grace period allowed to the promoter. The delay solely on the part of the promoter. A show cause notice to be issued to the promoter  for violation of section 4 punishable under section 60 for not completing the project within the declared time as per section 4(2)(l)(C) and initiating penal proceedings where penalty may extend upto 5% of the estimated cost of the real estate project as determined by the Authority.    EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
12-Apr-2021 Proceedings dated  12.04.2021No one is present on behalf of the promoter. Mr. Ashish Kush, Planning Executive briefed the facts of the case. The application for grant of extension of registration was considered by the Authority on 22.03.2021 and 12.04.2021. Deficiencies conveyed to the promoter on 10.03.2021 on the earlier hearing 20 days period was requested for rectifying the defects. No reply has been received so far and position of defects remains as such as has been conveyed to the promoter and also mentioned in the today's agenda. No one appeared on behalf of the promoter and also no communication received. The Authority decided to issue a show cause notice for rejection of application for extension  under section 6 read with proviso to rule 6(3)  To remove the defects otherwise application for grant of extension shall be rejected. If you have to say any in the matter you are by given an opportunity of hearing in the matter on 17.05.2021. After the hearing authorised representative of the promoter submitted a reply on the reception counter  which may be taken on record to be examined by the office. As per the statement of the authorised representative even now all the deficiencies have not been removed. In the show cause notice the deficiencies still remain to be attended be mentioned.  Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member)                                                                                                                                                                                                                                                                                                                                                                       Not Yet
22-Mar-2021 Ms. Aditi Sharma, Company Secretary is present on behalf of the promoter with due authorization. Deficiencies have already been conveyed to the promoter. No reply has been received so far. The promoter requested for twenty days time for removing the deficiencies.  License has expired, building plans validity also expired. The time period declared by the promoter under section 4(2)(l)(C) has expired on 27.8.2020. A grace period of six months due to COVID situation was granted to the promoter which also expired on 27.2.2021. The reason quoted by the promoter for not completing the project in time do not seems to be reasonable after considering the grace period allowed to the promoter. The delay solely on the part of the promoter. A show cause notice to be issued to the promoter  for violation of section 4 punishable under section 60 for not completing the project within the declared time as per section 4(2)(l)(C) and initiating penal proceedings where penalty may extend upto 5% of the estimated cost of the real estate project as determined by the Authority.    Not Yet