18-Jan-2021 |
During personal hearing, Sh. Dinesh
Sharma is present on behalf of the promoter. The promoter has submitted the
reply of deficiency notice dated 14.01.2021 which was scrutinized and found
that all the deficiencies have been fulfilled by the promoter except approved
service estimates and plans, fire scheme approval and environment clearance for
which application already filed in the concerned department. Registration fee,
processing fee is duly paid by the promoter. Online correction has been got
corrected by the promoter. Therefore, the authority has decided to grant provisional
registration certificate and direct the promoter to submit the approved service
estimates and plans, fire scheme approval within 3 months from the date of
grant of registration certificate and copy of environment clearance within 1
year from the date of grant of registration certificate. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
--- |