Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Westerlies Phase-2 SECTOR 108 GURUGRAM Kadipur ST Experion Developers Private Limited
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/694/426/2023/38 DATED 02.02.2023 RERA-GRG-795-2021 05-Mar-2021 12-Jan-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 28-May-2021 By hand By hand
1st deficiency notice sent to the promoter View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/694/426/2023/38 DATED 02.02.2023 10-Feb-2023 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
11-Apr-2022 Proceedings dated: 11.04.2022 Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The promoter has submitted all the deficit documents except corrections in online REP-I (A-H) and corrections in online detailed project information.  The promoter has obtained the part completion certificate on 22.03.2018 for the area applied for registration i.e., 44.178 acres. Therefore, the authority decided to grant registration subject to submission of corrected copy of REP-I (A-H) and DPI within one week.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS View Order
02-Apr-2022 Ms. Neeraj Gautam, Architectural Executive briefed about the facts of the project. Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The AR of the promoter is directed to attend the deficiencies before the next date of hearing. The matter is adjourned to 11.04.2022. ADJOURNMENT View Order
31-Mar-2022 The matter is adjourned to 02.04.2022 ADJOURNMENT View Order
28-Mar-2022 The matter is adjourned to 31.03.2022 OBJECTION ---
14-Mar-2022 None is present on behalf of the promoter. The application for registration was received on 05.03.2021 and despite conveying deficiencies/observations and hearing on multiple occasions, the promoter is not coming forward for their rectification and submission of complete information and hence one last opportunity is being granted for removal of all deficiencies failing which the application for registration shall be considered for rejection.   Matter to come up on 28.03.2022 OBJECTION View Order
31-Jan-2022 The promoter is directed to submit the deficit documents along with corrected online DPI and REP-I (Part A-H). Matter adjourned for 14.03.2022. ADJOURNMENT View Order
17-Jan-2022 Matter adjourned for 31.01.2022. ADJOURNMENT View Order
27-Dec-2021 Matter adjourned for 17.01.2022. OBJECTION View Order
20-Dec-2021 Sh. Sumeet Puri (VP Projects) is present on behalf of the promoter. A show cause notice was sent to the promoter on 15.11.2021 as why application for registration of real estate project shall not be rejected under section 5(b) of Real Estate (Regulation and Development) Act, 2016 and Rules 5(2) of Haryana Real Estate (Regulation and Development) Rules, 2017. The promoter has submitted the online DPI, which was scrutinized, and corrections are conveyed to the promoter. The promoter is directed to submit the corrected copy of online DPI along with other deficit documents. Matter to come up on 27.12.2021. OBJECTION View Order
15-Nov-2021 Proceedings Dated: 15.11.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. No one appeared on behalf of the promoter. Deficiencies have already been communicated.  Despite various opportunity needful has not been done. A penalty of Rs. Ten lac is imposed for noncompliance of the orders of the authority. A show cause notice be issued to the promoter as why application for registration shall not be rejected for want of information. Matter to come up on 20.12.2021.   OBJECTION View Order
27-Oct-2021 Proceedings Dated: 27.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (Authorized Signatory) and Sh. Suneet Puri (Director) are present on behalf of the promoter. The promoter is directed to submit the deficit documents along with hardcopy of online detailed project information. The matter to come up on 15.11.2021.   ADJOURNMENT View Order
26-Oct-2021 THE MATTER IS ADJOURNED FOR 27.10.2021 OBJECTION View Order
11-Oct-2021 Proceedings Dated: 11.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K. Malangi (CEO), Sh. Suneet Puri (VP), Sh. Vikash Aggarwal (DGM Project) and Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter. The deficiencies have still not been attended by the promoter. The promoter is directed to submit the deficit documents along with online detailed project information. The matter decided to come up on 26.10.2021. OBJECTION View Order
27-Sep-2021 Proceedings Dated: 27.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has submitted the reply in the hearing itself which needs to be examined. Matter decided to come up on 11.10.2021. OBJECTION View Order
21-Sep-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 27.09.2021. OBJECTION View Order
07-Sep-2021 Proceedings Dated: 07.09.2021Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The AR for promoter submits that the application for registration of land under phase-I measuring 46.257 acres is being prepared by filling online DPI and will be completed in next one week. Further the deficiencies conveyed for phase-II measuring 44.178 acres has been rectified and a detailed reply has been submitted in the Authority today only i.e., on 07.09.2021 and is to be examined. The matter is adjourned to 21.09.2021.  OBJECTION View Order
17-Aug-2021 Proceedings Dated: 17.08.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh. Hemansh R. (DGM) are is present on behalf of the promoter. The promoter had filed an application regarding registration of plotted colony project namely “Westerlies Phase 3” situated at sector 108, Gurugram being developed by M/s Experion Developers Pvt Ltd was submitted on 05.03.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. License no. 57 of 2013 dated 11.07.2013 valid upto 10.07.2024 on an area admeasuring 100.48125 acres was issued in favor of Experion Realty Pvt Ltd, Experion Real Estate Developers Pvt Ltd, Moksha Buildtech Pvt Ltd and 8 others in collaboration with M/s Experion Developers Pvt Ltd.   Total licensed area is divided into 3 phases which is as follows: 1.   Phase 1 area admeasuring 46.257 acres and part completion certificate obtained on 31.07.2017. 2.   Phase 2 area admeasuring 44.178 acres and part completion certificate obtained on 22.03.2018. 3.   Phase 3 area admeasuring 10.4625 acres and registration certificate obtained vide RC no. 67 of 2019.   The promoter has not submitted the reply of the remaining deficiencies neither submitted any representation nor reply of show cause notice as why penal proceedings for non-registration shall not be initiated. The AR of the promoter assured that necessary registration formalities shall be completed within 15 days. Authority decided to link penal proceedings already initiated against the promoter with the registration so that decision is taken jointly. The matter to come up on 07.09.2021.  OBJECTION View Order
27-Jul-2021 Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed the facts about the project. None present on behalf of the promoter and nor any reply on account of non-registration notice dated 11.11.2020 has been given. One last opportunity be given to the promoter failing which necessary legal penal action will be initiated.  The matter to come up on17.08.2021  OBJECTION View Order
01-Jul-2021 Proceedings dated: 01.07.2021 Ms. Jyoti Yadav (Planning Coordinator) briefed the facts about the project. Sh. Suneet Puri (Vice President), Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter.The promoter submitted the reply on 23.06.2021 which was scrutinized, and remaining deficiencies are conveyed to the promoter. Promoter is also advised to reply to show cause as why penal proceedings for non-registration shall not be initiated. Matter was discussed at length and promoter is advised to apply the whole project as one single unit giving information of the parts for which CC has been obtained including the additional licensed area. Regarding late fee the promoter is advised to give a representation and meanwhile processing fee and registration fee be deposited. Necessary online information be submitted at https://hrera.in/app1/signup.   The matter to come up on 27.07.2021. ADJOURNMENT View Order
30-Jun-2021 The matter is Adjourned for 01.07.2021.         OBJECTION ---
03-May-2021 Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 30.06.2021.                                                                                                                                                                                               OBJECTION View Order
26-Apr-2021 Proceedings dated: 26.04.2021 Ms Jyoti Yadav, Coordinator Planning Branch briefed about the facts of the case. Sh.  Suneet Puri, Vice President appeared on behalf of the promoter. The promoter has submitted some documents and reply to the deficiencies today itself. Office to examine the documents and reply and submit before the Authority before next date of hearing on 03.05.2021.Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member) (through video conferencing)                                                                                                                                                                                                                        OBJECTION View Order
30-Mar-2021 Sh. Suneet Puri, Vice President is present on behalf of the promoter, who submits that out of total license area of 100.48 acres the part completion certificate for 46.257 acres was obtained on 31.07.2017  which was two days after coming into operation of the HARERA Rules, 2017 and hence a view was taken in the Authority to not insist on registration of this phase with a condition that the developer get registered the entire remaining area of the colony. The developer has now applied for registration of 44.178acres of land but it was noted that as per latest orders of the Hon'ble High Court in case of Appeal no 52 of 2018, the developer is required to seek registration for the entire project and hence advised to apply for the same accordingly. Matter will be heard on 26.04.2021 EXAMINATION BY AUTHORITY View Order
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
26-Mar-2022 None is present on behalf of the promoter. The application for registration was received on 05.03.2021 and despite conveying deficiencies/observations and hearing on multiple occasions, the promoter is not coming forward for their rectification and submission of complete information and hence one last opportunity is being granted for removal of all deficiencies failing which the application for registration shall be considered for rejection.   Matter to come up on 28.03.2022 Not Yet
05-Mar-2022 The promoter is directed to submit the deficit documents along with corrected online DPI and REP-I (Part A-H). Matter adjourned for 14.03.2022. Not Yet
23-Dec-2021 Sh. Sumeet Puri (VP Projects) is present on behalf of the promoter. A show cause notice was sent to the promoter on 15.11.2021 as why application for registration of real estate project shall not be rejected under section 5(b) of Real Estate (Regulation and Development) Act, 2016 and Rules 5(2) of Haryana Real Estate (Regulation and Development) Rules, 2017. The promoter has submitted the online DPI, which was scrutinized, and corrections are conveyed to the promoter. The promoter is directed to submit the corrected copy of online DPI along with other deficit documents. Matter to come up on 27.12.2021. Not Yet
04-Dec-2021 Proceedings Dated: 15.11.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. No one appeared on behalf of the promoter. Deficiencies have already been communicated.  Despite various opportunity needful has not been done. A penalty of Rs. Ten lac is imposed for noncompliance of the orders of the authority. A show cause notice be issued to the promoter as why application for registration shall not be rejected for want of information. Matter to come up on 20.12.2021.   Not Yet
10-Nov-2021 Proceedings Dated: 27.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (Authorized Signatory) and Sh. Suneet Puri (Director) are present on behalf of the promoter. The promoter is directed to submit the deficit documents along with hardcopy of online detailed project information. The matter to come up on 15.11.2021.   Not Yet
16-Oct-2021 Proceedings Dated: 11.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K. Malangi (CEO), Sh. Suneet Puri (VP), Sh. Vikash Aggarwal (DGM Project) and Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter. The deficiencies have still not been attended by the promoter. The promoter is directed to submit the deficit documents along with online detailed project information. The matter decided to come up on 26.10.2021. Not Yet
04-Oct-2021 Proceedings Dated: 27.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has submitted the reply in the hearing itself which needs to be examined. Matter decided to come up on 11.10.2021. Not Yet
24-Sep-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The promoter has not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 27.09.2021. Not Yet
10-Sep-2021 Proceedings Dated: 07.09.2021Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Hemansh Rastogi (DGM) is present on behalf of the promoter. The AR for promoter submits that the application for registration of land under phase-I measuring 46.257 acres is being prepared by filling online DPI and will be completed in next one week. Further the deficiencies conveyed for phase-II measuring 44.178 acres has been rectified and a detailed reply has been submitted in the Authority today only i.e., on 07.09.2021 and is to be examined. The matter is adjourned to 21.09.2021.  Not Yet
18-Aug-2021 Proceedings Dated: 17.08.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh. Hemansh R. (DGM) are is present on behalf of the promoter. The promoter had filed an application regarding registration of plotted colony project namely “Westerlies Phase 3” situated at sector 108, Gurugram being developed by M/s Experion Developers Pvt Ltd was submitted on 05.03.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. License no. 57 of 2013 dated 11.07.2013 valid upto 10.07.2024 on an area admeasuring 100.48125 acres was issued in favor of Experion Realty Pvt Ltd, Experion Real Estate Developers Pvt Ltd, Moksha Buildtech Pvt Ltd and 8 others in collaboration with M/s Experion Developers Pvt Ltd.   Total licensed area is divided into 3 phases which is as follows: 1.   Phase 1 area admeasuring 46.257 acres and part completion certificate obtained on 31.07.2017. 2.   Phase 2 area admeasuring 44.178 acres and part completion certificate obtained on 22.03.2018. 3.   Phase 3 area admeasuring 10.4625 acres and registration certificate obtained vide RC no. 67 of 2019.   The promoter has not submitted the reply of the remaining deficiencies neither submitted any representation nor reply of show cause notice as why penal proceedings for non-registration shall not be initiated. The AR of the promoter assured that necessary registration formalities shall be completed within 15 days. Authority decided to link penal proceedings already initiated against the promoter with the registration so that decision is taken jointly. The matter to come up on 07.09.2021.  Not Yet
02-Aug-2021 Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed the facts about the project. None present on behalf of the promoter and nor any reply on account of non-registration notice dated 11.11.2020 has been given. One last opportunity be given to the promoter failing which necessary legal penal action will be initiated.  The matter to come up on17.08.2021  Not Yet
19-Jul-2021 Proceedings dated: 01.07.2021 Ms. Jyoti Yadav (Planning Coordinator) briefed the facts about the project. Sh. Suneet Puri (Vice President), Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter.The promoter submitted the reply on 23.06.2021 which was scrutinized, and remaining deficiencies are conveyed to the promoter. Promoter is also advised to reply to show cause as why penal proceedings for non-registration shall not be initiated. Matter was discussed at length and promoter is advised to apply the whole project as one single unit giving information of the parts for which CC has been obtained including the additional licensed area. Regarding late fee the promoter is advised to give a representation and meanwhile processing fee and registration fee be deposited. Necessary online information be submitted at https://hrera.in/app1/signup.   The matter to come up on 27.07.2021. Not Yet
15-Jun-2021 Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 30.06.2021.                                                                                                                                                                                               Not Yet
26-Apr-2021 Proceedings dated: 26.04.2021 Ms Jyoti Yadav, Coordinator Planning Branch briefed about the facts of the case. Sh.  Suneet Puri, Vice President appeared on behalf of the promoter. The promoter has submitted some documents and reply to the deficiencies today itself. Office to examine the documents and reply and submit before the Authority before next date of hearing on 03.05.2021.Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member) (through video conferencing)                                                                                                                                                                                                                        Not Yet
17-Apr-2021 Sh. Suneet Puri, Vice President is present on behalf of the promoter, who submits that out of total license area of 100.48 acres the part completion certificate for 46.257 acres was obtained on 31.07.2017  which was two days after coming into operation of the HARERA Rules, 2017 and hence a view was taken in the Authority to not insist on registration of this phase with a condition that the developer get registered the entire remaining area of the colony. The developer has now applied for registration of 44.178acres of land but it was noted that as per latest orders of the Hon'ble High Court in case of Appeal no 52 of 2018, the developer is required to seek registration for the entire project and hence advised to apply for the same accordingly. Matter will be heard on 26.04.2021 Not Yet