11-Apr-2022 |
Proceedings dated: 11.04.2022 Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog (AM-Projects) are resent on behalf of the promoter. The promoter has submitted all the deficit documents except corrections in online REP-I (A-H) and corrections in online detailed project information. The promoter has obtained the part completion certificate on 22.03.2018 for the area applied for registration i.e., 44.178 acres. Therefore, the authority decided to grant registration subject to submission of corrected copy of REP-I (A-H) and DPI within one week. |
APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS |
View Order |
02-Apr-2022 |
Ms.
Neeraj Gautam, Architectural Executive briefed about the facts of the project.
Sh. Suneet Puri (Director) and Sh. Utkarsh Suyog
(AM-Projects) are resent on behalf of the promoter. The AR of the promoter is
directed to attend the deficiencies before the next date of hearing. The matter
is adjourned to 11.04.2022. |
ADJOURNMENT |
View Order |
31-Mar-2022 |
The matter is adjourned to 02.04.2022 |
ADJOURNMENT |
View Order |
28-Mar-2022 |
The matter is adjourned to 31.03.2022 |
OBJECTION |
--- |
14-Mar-2022 |
None
is present on behalf of the promoter. The application for registration was
received on 05.03.2021 and despite conveying deficiencies/observations and
hearing on multiple occasions, the promoter is not coming forward for their
rectification and submission of complete information and hence one last
opportunity is being granted for removal of all deficiencies failing which the
application for registration shall be considered for rejection.
Matter to come up on 28.03.2022 |
OBJECTION |
View Order |
31-Jan-2022 |
The promoter is
directed to submit the deficit documents along with corrected online DPI and
REP-I (Part A-H). Matter adjourned for 14.03.2022. |
ADJOURNMENT |
View Order |
17-Jan-2022 |
Matter adjourned for
31.01.2022. |
ADJOURNMENT |
View Order |
27-Dec-2021 |
Matter adjourned for
17.01.2022. |
OBJECTION |
View Order |
20-Dec-2021 |
Sh.
Sumeet Puri (VP Projects) is present on behalf of the promoter.
A
show cause notice was sent to the promoter on 15.11.2021 as why application for
registration of real estate project shall not be rejected under section 5(b) of
Real Estate (Regulation and Development) Act, 2016 and Rules 5(2) of Haryana
Real Estate (Regulation and Development) Rules, 2017.
The
promoter has submitted the online DPI, which was scrutinized, and corrections
are conveyed to the promoter. The promoter is directed to submit the corrected
copy of online DPI along with other deficit documents.
Matter to come up on 27.12.2021. |
OBJECTION |
View Order |
15-Nov-2021 |
Proceedings
Dated: 15.11.2021
Ms.
Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the
project.
No one appeared on behalf of the promoter.
Deficiencies have already been communicated.
Despite various opportunity needful has not been done. A penalty of Rs.
Ten lac is imposed for noncompliance of the orders of the authority. A show
cause notice be issued to the promoter as why application for registration
shall not be rejected for want of information. Matter to come up on 20.12.2021.
|
OBJECTION |
View Order |
27-Oct-2021 |
Proceedings
Dated: 27.10.2021
Ms.
Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the
project.
Sh.
Hemansh Rastogi (Authorized Signatory) and Sh. Suneet Puri (Director) are
present on behalf of the promoter.
The
promoter is directed to submit the deficit documents along with
hardcopy of online detailed project information.
The matter to come up on 15.11.2021. |
ADJOURNMENT |
View Order |
26-Oct-2021 |
THE MATTER IS ADJOURNED FOR 27.10.2021 |
OBJECTION |
View Order |
11-Oct-2021 |
Proceedings Dated: 11.10.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about
the facts of the project.
Sh. B.K. Malangi (CEO), Sh. Suneet Puri (VP), Sh. Vikash
Aggarwal (DGM Project) and Sh. Hemansh Rastogi
(DGM) are present on behalf of the promoter.
The deficiencies have still not been attended by the
promoter. The promoter is directed to submit the deficit documents along with
online detailed project information.
The matter decided to come up on 26.10.2021. |
OBJECTION |
View Order |
27-Sep-2021 |
Proceedings Dated: 27.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about
the facts of the project.
Sh. Hemansh Rastogi (DGM) is present on behalf of the
promoter.
The promoter has submitted the reply in the
hearing itself which needs to be examined. Matter decided to come up on 11.10.2021. |
OBJECTION |
View Order |
21-Sep-2021 |
Proceedings Dated: 21.09.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about
the facts of the project.
Sh. Hemansh Rastogi (DGM) is present on behalf of the
promoter.
The promoter has not submitted the reply of the
deficiencies. The AR seeks time to rectify the deficiencies in all respect. The
matter is adjourned to 27.09.2021. |
OBJECTION |
View Order |
07-Sep-2021 |
Proceedings Dated: 07.09.2021Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about
the facts of the project.
Sh. Hemansh Rastogi (DGM) is present on behalf of the
promoter.
The AR for promoter submits that the application
for registration of land under phase-I measuring 46.257 acres is being prepared
by filling online DPI and will be completed in next one week. Further the
deficiencies conveyed for phase-II measuring 44.178 acres has been rectified
and a detailed reply has been submitted in the Authority today only i.e., on
07.09.2021 and is to be examined. The matter is adjourned to 21.09.2021. |
OBJECTION |
View Order |
17-Aug-2021 |
Proceedings Dated: 17.08.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed
about the facts of the project.
Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh.
Hemansh R. (DGM) are is present on behalf of the promoter.
The promoter
had filed an application regarding registration of plotted colony project
namely “Westerlies Phase 3” situated at sector 108, Gurugram being developed by
M/s Experion Developers Pvt Ltd was submitted on 05.03.2021 under section 4 of
Real Estate (Regulation and Development), Act 2016.
License
no. 57 of 2013 dated 11.07.2013 valid upto 10.07.2024 on an area admeasuring
100.48125 acres was issued in favor of Experion Realty Pvt Ltd,
Experion Real Estate Developers Pvt Ltd, Moksha Buildtech Pvt Ltd and 8 others in collaboration with M/s
Experion Developers Pvt Ltd.
Total
licensed area is divided into 3 phases which is as follows:
1. Phase
1 area admeasuring 46.257 acres and part completion certificate obtained on
31.07.2017.
2. Phase
2 area admeasuring 44.178 acres and part completion certificate obtained on
22.03.2018.
3. Phase
3 area admeasuring 10.4625 acres and registration certificate obtained vide RC
no. 67 of 2019.
The
promoter has not submitted the reply of the remaining deficiencies neither
submitted any representation nor reply of show cause notice as why
penal proceedings for non-registration shall not be initiated.
The AR
of the promoter assured that necessary registration formalities shall be
completed within 15 days. Authority decided to link penal proceedings already
initiated against the promoter with the registration so that decision is taken
jointly.
The matter to come up on 07.09.2021. |
OBJECTION |
View Order |
27-Jul-2021 |
Proceedings dated: 27.07.2021
Ms. Jyoti Yadav, Coordinator, Planning Branch briefed the
facts about the project.
None present on behalf of the promoter and nor any reply on
account of non-registration notice dated 11.11.2020 has been given. One last
opportunity be given to the promoter failing which necessary legal penal action
will be initiated.
The matter to come up on17.08.2021 |
OBJECTION |
View Order |
01-Jul-2021 |
Proceedings dated: 01.07.2021
Ms. Jyoti Yadav (Planning Coordinator) briefed the facts about the project.
Sh. Suneet Puri (Vice President), Sh. Hemansh Rastogi (DGM) are present on
behalf of the promoter.The promoter submitted the reply on 23.06.2021 which was scrutinized, and remaining
deficiencies are conveyed to the promoter.
Promoter
is also advised to reply to show cause as why penal proceedings for
non-registration shall not be initiated. Matter was discussed at length and
promoter is advised to apply the whole project as one single unit giving
information of the parts for which CC has been obtained including the
additional licensed area. Regarding late fee the promoter is advised to give a
representation and meanwhile processing fee and registration fee be deposited.
Necessary online information be submitted at https://hrera.in/app1/signup.
The matter to come up on 27.07.2021. |
ADJOURNMENT |
View Order |
30-Jun-2021 |
The matter is Adjourned for 01.07.2021. |
OBJECTION |
--- |
03-May-2021 |
Due to Covid-19 pandemic, authority meeting could not be held. Now, the authority has decided to fix the matter on 30.06.2021. |
OBJECTION |
View Order |
26-Apr-2021 |
Proceedings dated: 26.04.2021 Ms Jyoti Yadav, Coordinator Planning Branch briefed about the facts of the case. Sh. Suneet Puri, Vice President appeared on behalf of the promoter. The promoter has submitted some documents and reply to the deficiencies today itself. Office to examine the documents and reply and submit before the Authority before next date of hearing on 03.05.2021.Dr. K.K.Khandelwal (Chairman)Samir Kumar (Member)Vijay Kumar Goyal (Member) (through video conferencing) |
OBJECTION |
View Order |
30-Mar-2021 |
Sh. Suneet Puri, Vice President is present on behalf of the promoter, who submits that out of total license area of 100.48 acres the part completion certificate for 46.257 acres was obtained on 31.07.2017 which was two days after coming into operation of the HARERA Rules, 2017 and hence a view was taken in the Authority to not insist on registration of this phase with a condition that the developer get registered the entire remaining area of the colony. The developer has now applied for registration of 44.178acres of land but it was noted that as per latest orders of the Hon'ble High Court in case of Appeal no 52 of 2018, the developer is required to seek registration for the entire project and hence advised to apply for the same accordingly. Matter will be heard on 26.04.2021 |
EXAMINATION BY AUTHORITY |
View Order |