Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
WESTERLIES SECTOR 108 GURUGRAM Gurgaon EXPERION DEVELOPERS PVT. LTD.
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/511/243/2021/79 DATED 15.11.2021 RERA-GRG-774-2020 02-Jul-2021 16-Mar-2021 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Yes 06-Jul-2021 received by hand 1st deficiency notice
1st deficiency notice sent to th promoter View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/511/243/2021/79 DATED 15.11.2021 28-May-2022 RC Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
15-Nov-2021 Proceedings Dated: 15.11.2021 Sh. Vikas (Advocate), Ms. Bhoomika Chopra (Company Secretary), Sh. Vikram Mehta (AR) are present on behalf of the promoter. The authorized representatives of the promoter are taking things lightly and despite several opportunities necessary online information has not been filled up. The AR assured the authority that within one-week necessary information in the online format shall be corrected and submitted to the authority for examination along with other deficit documents which are mentioned in agenda note. As far as zoning plan approval is concerned same is pending with the director as informed by AR. During the course of proceedings, it was mentioned by AR that zoning plan has also been approved by the DTCP, Haryana. The authority decided to grant registration. The promoter is asked to submit PDF print out of the final online information.  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
27-Oct-2021 Proceedings Dated: 27.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. Rakshit Srivastava (Advocate), Ms. Bhoomika Chopra (Company Secretary), Sh. Vikram Mehta (AR) and Sh. Suneet Puri (Director) are present on behalf of the promoter. The AR of the promoter is submitting today the deficit documents along with other requisite details. The hard copy of DPI shall also be submitted after corrections/editing. The matter to come up on 15.11.2021. ADJOURNMENT ---
26-Oct-2021 THE MATTER IS ADJOURNED FOR 27.10.2021 OBJECTION ---
11-Oct-2021 Proceedings Dated: 11.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary), Sh. Suneet Puri (Director), Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter. Documents have been submitted today itself which are to be examined by office. Zoning plan is yet to be approved by DTCP. Although the copy of the zoning plan forwarded from DTP Gurugram to DTCP has been submitted. The matter decided to come up on 26.10.2021. OBJECTION ---
27-Sep-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The promoter has again not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 11.10.2021. OBJECTION ---
21-Sep-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The promoter has not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 27.09.2021. OBJECTION ---
07-Sep-2021 Proceedings Dated: 07.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The reply to the deficiencies conveyed vide e-mail dated 06.07.2021 was received in the Authority on 03.09.2021, the same has been scrutinized and noticed that all the deficiencies not yet rectified including submission of service plan and estimates, renewal of EC, NOC of electric load. Further neither the details in online DPI have been provided and thus the application remains incomplete. The deficiencies notice has been issued to the promoter applicant on 07.09.2021 and the AR seeks 2 weeks’ time to rectify the deficiencies in all respect. The matter is adjourned to 21.09.2021.  OBJECTION ---
17-Aug-2021 Proceedings Dated: 17.08.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh. Hemansh R. (DGM) are is present on behalf of the promoter. An application regarding registration of plotted colony project namely “Westerlies Phase 4” situated at sector 108, Gurugram being developed by M/s Experion Developers Pvt Ltd was submitted on 02.07.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. The present application pertains to 172 residential plots forming additional plotted license no. 114 of 2019 dated 12.09.2019 measuring 16.03125 acres, being developed by M/s Experion Developers Pvt Ltd. The promoter has not submitted the reply of 1st deficiency notice sent on 05.07.2021. The AR of the promoter assured that necessary registration formalities shall be completed within 15 days. Authority decided to link penal proceedings already initiated against the promoter with the registration so that decision is taken jointly. The matter to come up on 07.09.2021. OBJECTION ---
27-Jul-2021 Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator Planning Branch briefed the facts about the project. Sh. Rakshit Srivastava (Advocate) is present on behalf of the promoter. The Advocate for the company has given in writing seeking adjournment. The matter to come up on 17.08.2021. EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
16-Oct-2021 Proceedings Dated: 11.10.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary), Sh. Suneet Puri (Director), Sh. Hemansh Rastogi (DGM) are present on behalf of the promoter. Documents have been submitted today itself which are to be examined by office. Zoning plan is yet to be approved by DTCP. Although the copy of the zoning plan forwarded from DTP Gurugram to DTCP has been submitted. The matter decided to come up on 26.10.2021. Not Yet
04-Oct-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The promoter has again not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 11.10.2021. Not Yet
24-Sep-2021 Proceedings Dated: 21.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The promoter has not submitted the reply of the deficiencies. The AR seeks time to rectify the deficiencies in all respect. The matter is adjourned to 27.09.2021. Not Yet
10-Sep-2021 Proceedings Dated: 07.09.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Ms. Bhoomika Chopra (Company Secretary) is present on behalf of the promoter. The reply to the deficiencies conveyed vide e-mail dated 06.07.2021 was received in the Authority on 03.09.2021, the same has been scrutinized and noticed that all the deficiencies not yet rectified including submission of service plan and estimates, renewal of EC, NOC of electric load. Further neither the details in online DPI have been provided and thus the application remains incomplete. The deficiencies notice has been issued to the promoter applicant on 07.09.2021 and the AR seeks 2 weeks’ time to rectify the deficiencies in all respect. The matter is adjourned to 21.09.2021.  Not Yet
18-Aug-2021 Proceedings Dated: 17.08.2021 Ms. Jyoti Yadav, Coordinator, Planning Branch briefed about the facts of the project. Sh. B.K.Malagi (CEO), Sh. Suneet P. (VP) and Sh. Hemansh R. (DGM) are is present on behalf of the promoter. An application regarding registration of plotted colony project namely “Westerlies Phase 4” situated at sector 108, Gurugram being developed by M/s Experion Developers Pvt Ltd was submitted on 02.07.2021 under section 4 of Real Estate (Regulation and Development), Act 2016. The present application pertains to 172 residential plots forming additional plotted license no. 114 of 2019 dated 12.09.2019 measuring 16.03125 acres, being developed by M/s Experion Developers Pvt Ltd. The promoter has not submitted the reply of 1st deficiency notice sent on 05.07.2021. The AR of the promoter assured that necessary registration formalities shall be completed within 15 days. Authority decided to link penal proceedings already initiated against the promoter with the registration so that decision is taken jointly. The matter to come up on 07.09.2021. Not Yet
02-Aug-2021 Proceedings dated: 27.07.2021 Ms. Jyoti Yadav, Coordinator Planning Branch briefed the facts about the project. Sh. Rakshit Srivastava (Advocate) is present on behalf of the promoter. The Advocate for the company has given in writing seeking adjournment. The matter to come up on 17.08.2021. Not Yet