Comprehensive Project Details (Project Extension)
Project Location Details (Project Extension)
Project Name Project Location Project District Project Tehsil Promoter Name
Ild grand Sector 37 c, tehsil and district gurugram, haryana GURUGRAM ALM Infotech city pvt.ltd.
Project Detail
Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks
RERA-GRG-673-2020 17-Mar-2020 17-Mar-2020 EXTENSION APPROVED NOT REQUIRED Not Yet -- 1st deficiency notice on 21.03.2020
Project Listing Details (Project Extension)
Date of Hearing Proceedings of the day Status Order
19-Aug-2021 Proceeding dated 19.08.2021 Mr. Naresh Kumar CA briefed about the project. Mr. Alimuddin (Director), Mr Salman J Akbar (Director), Shahid Khan(Manager accounts), Manoj (Secretary) are present on behalf of promoter. Detailed project information filled by the promoter in online mode have been discussed by the hon’ble members of the authority in the hearing. Online correction has be corrected by the promoter and all the deficit documents which were conveyed to the promoter have been submitted and all the deficiencies are removed by the promoter. The authority keeping in view the facts stated above, decided to grant permission regarding registration of part of the project/phase “ILD GRAND” area admeasuring 5.6975 acres (part of the total licensed area of the project 21.1804 acres developed under the licence no. 13 of 2008, 96 of 2010 & 118 of 2011 ) to remain in force under section 7(3) of Real Estate (Regulation and Development) Act, 2016. EXTENSION APPROVED ---
10-Aug-2021 As per the orders of the Authority, the matter to come up on  19.08.2021 ADJOURNMENT ---
30-Mar-2021 The  matter will be heard dated 10.08.2021 OBJECTION ---
18-Mar-2021 The  matter will be heard dated 30.03.2021 ADJOURNMENT ---
08-Feb-2021 The  matter will be heard dated 18.03.2021 ADJOURNMENT ---
14-Jan-2021 The  matter will be heard dated 08.02.2021 ADJOURNMENT ---
21-Dec-2020 The  matter will be heard dated 14.01.2020. OBJECTION ---
09-Dec-2020 The hearing is adjourned and matter is fixed for 09.12.2020. ADJOURNMENT ---
04-Dec-2020 The hearing is adjourned and matter is fixed for 09.12.2020. ADJOURNMENT ---
02-Dec-2020 The matter is fixed for 04.12.2020. OBJECTION ---
02-Nov-2020 The matter fixed for 02.11.2020    ADJOURNMENT ---
30-Sep-2020 The matter fixed for 02.11.2020    ADJOURNMENT ---
18-Sep-2020 The matter fixed for 30.09.2020    ADJOURNMENT ---
08-Sep-2020 The matter fixed for 18.09.2020    ADJOURNMENT ---
05-Aug-2020 Next date of hearing on 08.09.2020 ADJOURNMENT ---
27-Jul-2020 Adjourned for dated 05.08.2020 ADJOURNMENT ---
20-Jul-2020 Adjourned due to Video Conference technical issue, for dated 28.07.2020 OBJECTION ---
06-Jul-2020 The request of the promoter sent vide email dated 06.07.2020 for adjournment of the hearing has  been considered by the authority and next date of hearing on 20.07.2020 at 3:00 p.m.  OBJECTION ---
23-Jun-2020 This project is a stressed project and the Authority has taken suo-motu cognizance regarding delay in completion of the project. The promoter has assured to submit a mitigation plan during this week. This mitigation plan will be examined by the office and a report be submitted in the next hearing so that decision could be taken. ADJOURNMENT ---
22-Jun-2020 THE MATTER IS ADJOURNED TO 23.06.2020 ADJOURNMENT ---
17-Jun-2020 Next date of hearing on 22.06.2020 OBJECTION ---
10-Jun-2020 The promoter is asked to submit the document regarding their legal capacity in the said project. The promoter is directed to remove the above mentioned deficiencies by 17.06.2020. Otherwise, the authority will issue a show cause notice for rejection under section 6 of the RERA Act 2016 and rule 6 of the HRERA, Rules 2017.  ADJOURNMENT ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
30-Mar-2021 The  matter will be heard dated 30.03.2021 Not Yet
10-Dec-2020 The hearing is adjourned and matter is fixed for 09.12.2020. Not Yet
04-Nov-2020 The matter fixed for 02.11.2020    Not Yet
18-Jul-2020 The request of the promoter sent vide email dated 06.07.2020 for adjournment of the hearing has  been considered by the authority and next date of hearing on 20.07.2020 at 3:00 p.m.  Not Yet
26-Jun-2020 This project is a stressed project and the Authority has taken suo-motu cognizance regarding delay in completion of the project. The promoter has assured to submit a mitigation plan during this week. This mitigation plan will be examined by the office and a report be submitted in the next hearing so that decision could be taken. Not Yet
13-Jun-2020 The promoter is asked to submit the document regarding their legal capacity in the said project. The promoter is directed to remove the above mentioned deficiencies by 17.06.2020. Otherwise, the authority will issue a show cause notice for rejection under section 6 of the RERA Act 2016 and rule 6 of the HRERA, Rules 2017.  Not Yet