Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Shree Vardhman | Sector 2, Sohna | GURUGRAM | Sohna | Shree Vardhman Developers Pvt Ltd |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/403/135/2020/19 DATED 04.08.2020 | RERA-GRG-666-2020 | 12-Mar-2020 | 12-Mar-2020 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 20-Mar-2020 | received by hand | 1st deficiency notice | 1st deficiency notice sent to the prmoter | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/403/135/2020/19 DATED 04.08.2020 | 13-Aug-2020 | RC Approved and Project Certificate Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
04-Aug-2020 | Registration certificate issued to the promoter. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
29-Jul-2020 | Next date | OBJECTION | --- |
29-Jun-2020 | The application for registration of the project was considered by the authority. The authorized representative of the promoter appeared online. The deficiencies communicated earlier have been rectified except approval of the service plans and estimates and electrical load availability certificate. The authority decided to approve registration of project subject to submission of approved service plans and estimates and electric load availability certificate within a month. The matter will be heard on 29.07.2020. | OBJECTION | --- |
23-Jun-2020 | The affidavit regarding bank accounts submitted does not carry any Account No. It seems that it has been attested/notarized erroneously. Similarly, Bank undertaking neither signed by the bank authority nor provided required details. The deficiencies still remains were communicated to the promoter as per the agenda note and the promoter was advised to complete the necessary pre requisite for registration by Monday 29th June, 2020 otherwise notice for rejection shall be issued under section 5 of the Act. | ADJOURNMENT | --- |
22-Jun-2020 | the matter is adjourned to 23.06.2020 | OBJECTION | --- |
08-Jun-2020 | Sh. Sandeep Jain is present on behalf of the builder authorized through a board resolution. The promoter is directed to submit the chart of allotment of different size-wise 186 plots. The promoter has a collaboration agreement with M/s Subhash Chandra (Landowner) in the ratio 65:35. (65% Shree Vardhman and 35% of Subhash Chandra). The allotment letter and BBA should contain signs of both the parties i.e. Shree Vardhman Pvt Ltd and Subhash Chandra. The promoter is directed to s submit a copy of allotment letter, application form, and brochures. The promoter is also directed to submit the reply of deficiencies conveyed to you vide notice dated 20.03.2020. Now, this case is fixed for hearing on 22.6.2020. | ADJOURNMENT | --- |
30-Mar-2020 | Adjournment for next date 08.06.2020 | EXAMINATION BY AUTHORITY | --- |
Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
---|---|---|---|---|---|---|
30-Jun-2020 | The application for registration of the project was considered by the authority. The authorized representative of the promoter appeared online. The deficiencies communicated earlier have been rectified except approval of the service plans and estimates and electrical load availability certificate. The authority decided to approve registration of project subject to submission of approved service plans and estimates and electric load availability certificate within a month. The matter will be heard on 29.07.2020. | Not Yet | ||||
26-Jun-2020 | The affidavit regarding bank accounts submitted does not carry any Account No. It seems that it has been attested/notarized erroneously. Similarly, Bank undertaking neither signed by the bank authority nor provided required details. The deficiencies still remains were communicated to the promoter as per the agenda note and the promoter was advised to complete the necessary pre requisite for registration by Monday 29th June, 2020 otherwise notice for rejection shall be issued under section 5 of the Act. | Not Yet | ||||
13-Jun-2020 | Sh. Sandeep Jain is present on behalf of the builder authorized through a board resolution. The promoter is directed to submit the chart of allotment of different size-wise 186 plots. The promoter has a collaboration agreement with M/s Subhash Chandra (Landowner) in the ratio 65:35. (65% Shree Vardhman and 35% of Subhash Chandra). The allotment letter and BBA should contain signs of both the parties i.e. Shree Vardhman Pvt Ltd and Subhash Chandra. The promoter is directed to s submit a copy of allotment letter, application form, and brochures. The promoter is also directed to submit the reply of deficiencies conveyed to you vide notice dated 20.03.2020. Now, this case is fixed for hearing on 22.6.2020. | Not Yet |