| 29-Jun-2020 |
There are two
licenses in this project granted by Director Town & Country Planning vide
No. 163 of 2014 and 164 of 2014. The validity of licenses has expired on
11.9.2019. The promoter has applied for renewal of license on 19.9.2019
although the license has not been renewed so far. Building plans approval had
also expired on 19.12.2019. No information has been provided regarding
revalidation of building plans. The deficit fee is of Rs. 12, 36,173/-. It is surprising that even
after six years of license approved service plans and estimates have not been
submitted. There are other deficiencies also which needs to be attended by the
promoter as has been conveyed vide notice dated 11.6.2020. Keeping in view the
interest of the allottees and for completion of the project the Authority
decided to grant extension up to 31.1.2021.
The promoter has stated that NGT banned the construction activity for 20
days. Due to restriction migrant workers disperse from the site as the
contractor would not pay the wages to them. Scarcity of quality material is the
another cause of the delay in the project execution. Although the promoter has
not been able to prove that delay is not on part of his default, accordingly
the promoter is liable to all legal consequences for the delay in handing over
the project. The promoter is directed to complete the deficiencies within three
months otherwise penal action under section 63 shall be initiated against the
promoter. |
EXTENSION APPROVED |
--- |
| 29-Jun-2020 |
|
OBJECTION |
--- |
| 22-Jun-2020 |
There are two
licenses in this project granted by Director Town & Country Planning vide
No. 163 of 2014 and 164 of 2014. The validity of licenses has expired on
11.9.2019. The promoter has applied for renewal of license on 19.9.2019
although the license has not been renewed so far. Building plans approval had
also expired on 19.12.2019. No information has been provided regarding
revalidation of building plans. The deficit fee is of Rs. 12, 36,173/-. It is surprising that even
after six years of license approved service plans and estimates have not been
submitted. There are other deficiencies also which needs to be attended by the
promoter as has been conveyed vide notice dated 11.6.2020. Keeping in view the
interest of the allottees and for completion of the project the Authority
decided to grant extension up to 31.1.2021.
The promoter has stated that NGT banned the construction activity for 20
days. Due to restriction migrant workers disperse from the site as the
contractor would not pay the wages to them. Scarcity of quality material is the
another cause of the delay in the project execution. Although the promoter has
not been able to prove that delay is not on part of his default, accordingly
the promoter is liable to all legal consequences for the delay in handing over
the project. The promoter is directed to complete the deficiencies within three
months otherwise penal action under section 63 shall be initiated against the
promoter. |
OBJECTION |
--- |
| 11-Jun-2020 |
The matter is
adjourned to 22.06.2020 at 3: 00 p.m. |
ADJOURNMENT |
--- |
| 30-Mar-2020 |
Next date of hearing on 11.06.2020. |
ADJOURNMENT |
--- |
| 02-Mar-2020 |
The promoter was conveyed vide letter no.
HARERA/GGM/REP/RC/108/2017/EXT/230/2020 dated 11.02.2020 deficiencies to the
promoter. Three weeks’ time is given to the promoter as last and final opportunity for
removal of all the deficiencies and next date of hearing is fixed on 30.03.2020. |
EXAMINATION BY AUTHORITY |
--- |