| Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
|---|---|---|---|---|
| Green court | Sector-90, village- hayatpur, gurugram | GURUGRAM | Aster infrahome pvt. ltd. |
| Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| RERA-GRG-635-2020 | 14-Feb-2020 | 14-Feb-2020 | EXTENSION APPROVED | NOT REQUIRED | Not Yet | -- | 1st deficiency notice sent on 10.02.2020 |
| Date of Hearing | Proceedings of the day | Status | Order |
|---|---|---|---|
| 29-Jun-2020 | Extension approved. | EXTENSION APPROVED | View Order |
| 11-Jun-2020 | The request of the promoter sent vide email dated 09.06.2020 for adjournment of the hearing. The matter is adjourned to 22.06.2020 at 3:00 p.m. | ADJOURNMENT | --- |
| 20-May-2020 | Next date of hearing on 11.06.2020 | OBJECTION | --- |
| 16-Mar-2020 | This matter relates to grant of extension of registration of project Green Court (Affordable Group Housing Project), Sector 190, Gurugram measuring 10.0125 acres. The promoter is a licensee who was granted licence No. 61 of 2014 and No. 62 of 2014 valid up to 6.7.2019. The application for extension was considered by the authority and deficiencies in the application were conveyed on 10.2.2020 and promoter was also given personal hearing on 2.3.2020. The promoter was given second hearing on 16.3.2020 and promoter submitted the following documents: 1. License no.61 of 2014 expired on 06.07.2019 renewal of the same not on record, however renewal application dated 06.07.2019 along with renewal fee (Online payment vide Transaction No. TCP1138419617737 dated 17.06.2019) has been enclosed. 2. License no.62 of 2014 expired on 06.07.2019 renewal of the same not on record, however renewal application dated 06.07.2019 along with renewal fee (Online payment vide Transaction No. TCP1138419617738 dated 17.06.2019) has been enclosed. 3. Online application REP-I A to H need to be corrected. 4. Deficit fee Rs. 14,80,105/- 5. Booking list of flats sold to the allottees as on date of the application applied for extension which includes name of the allottees, flat no., tower no., carpet area/super area, date of booking. 6. Details of unsold flats need to be provided. 7. The promoter mention in explanatory note that 85% approx. work is completed however as for as expenditure is concerned only 63% expenditure is incurred that need to be clarify. 8. Board Resolution for extension of the project need to be required. 9. Part -V-C Marketing details: Total carpet area and total sale value need to be clarified. 10. Estimated cost of infrastructure and EDC, IDC need to be clarified. The deficiencies in the extension form were removed. There is no EDC/IDC outstanding amount as per the information sheet submitted by the promoter. The promoter also submitted list of sold and unsold inventories. The photographs regarding completion of project were also submitted by the promoter. The promoter has not deposited deficient fee of Rs. 14.05 lakh as has been conveyed to him at the time of first hearing. The promoter is advised to deposit the deficient fee within one week. | ADJOURNMENT | --- |
| 02-Mar-2020 | No one appeared for the personal hearing. So the matter is adjourned to next date on 16.03.2020. | EXAMINATION BY AUTHORITY | --- |
| Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
|---|---|---|---|---|---|---|
| 20-May-2020 | This matter relates to grant of extension of registration of project Green Court (Affordable Group Housing Project), Sector 190, Gurugram measuring 10.0125 acres. The promoter is a licensee who was granted licence No. 61 of 2014 and No. 62 of 2014 valid up to 6.7.2019. The application for extension was considered by the authority and deficiencies in the application were conveyed on 10.2.2020 and promoter was also given personal hearing on 2.3.2020. The promoter was given second hearing on 16.3.2020 and promoter submitted the following documents: 1. License no.61 of 2014 expired on 06.07.2019 renewal of the same not on record, however renewal application dated 06.07.2019 along with renewal fee (Online payment vide Transaction No. TCP1138419617737 dated 17.06.2019) has been enclosed. 2. License no.62 of 2014 expired on 06.07.2019 renewal of the same not on record, however renewal application dated 06.07.2019 along with renewal fee (Online payment vide Transaction No. TCP1138419617738 dated 17.06.2019) has been enclosed. 3. Online application REP-I A to H need to be corrected. 4. Deficit fee Rs. 14,80,105/- 5. Booking list of flats sold to the allottees as on date of the application applied for extension which includes name of the allottees, flat no., tower no., carpet area/super area, date of booking. 6. Details of unsold flats need to be provided. 7. The promoter mention in explanatory note that 85% approx. work is completed however as for as expenditure is concerned only 63% expenditure is incurred that need to be clarify. 8. Board Resolution for extension of the project need to be required. 9. Part -V-C Marketing details: Total carpet area and total sale value need to be clarified. 10. Estimated cost of infrastructure and EDC, IDC need to be clarified. The deficiencies in the extension form were removed. There is no EDC/IDC outstanding amount as per the information sheet submitted by the promoter. The promoter also submitted list of sold and unsold inventories. The photographs regarding completion of project were also submitted by the promoter. The promoter has not deposited deficient fee of Rs. 14.05 lakh as has been conveyed to him at the time of first hearing. The promoter is advised to deposit the deficient fee within one week. | Not Yet |