Comprehensive Project Details
Project Location Details
Project Name Project Location Project District Project Tehsil Promoter Name
Signature Global Park IV Village Hariyahara, sector-36 GURUGRAM Sohna SIGNATUREGLOBAL HOMES PRIVATE LIMITED
Project Detail
Project Registration Number Project Id Receiving Date Online Submission Date Current Status Next Date of Hearing Notice Dispatched Notice Dispatched On Notice Tracking Id Notice Dispatched Remarks View Notice Initially Scrutinized Remarks Details of Project(Form A-H)
GGM/401/133/2020/17 DATED 20.07.2020 RERA-GRG-580-2020 28-Jan-2020 27-Jan-2020 APPROVED AND CERTIFICATE UPLOADED NOT REQUIRED Not Yet -- Deficiencies conveyed. View Form(A-H)
Project Approval Status
Project Registration Number Uploading Date Remarks View Certificate
GGM/401/133/2020/17 DATED 20.07.2020 10-Aug-2020 Project RC Approved and Certificate Uploaded
Project Listing Details
Date of Hearing Proceedings of the day Status Order
20-Jul-2020 Project RC Approved  APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS ---
13-Jul-2020 hearing adjourned to 20.07.2020 OBJECTION ---
29-Jun-2020 The application for registration of the project was considered by the authority. The Planning Assistant briefed about the project.  There are certain clarification which are likely to be obtained from the promoter such as the promoter has submitted the non-encumbrance certificate whereas on the other part, project land is mortgaged by the company has been mentioned.  The promoter has submitted reply of the show cause notice dated 29.5.2020 on 26.6.2020.  The reply needs to be examined.  The deficiencies if any remain even after this reply same shall be communicated to the promoter immediately so that before next date compliance is done otherwise the application for   registration shall be rejected.  Matter is fixed for 13th of July 2020 at 3-00 PM online.   OBJECTION ---
09-Mar-2020 Show cause hearing on 29.06.2020 ADJOURNMENT ---
24-Feb-2020 The Hearing is Adjourned for 09.03.2020 on request of promoter EXAMINATION BY AUTHORITY ---
Project Deficiency Details
Deficiency Date Deficiency Remarks Online Compliance Done Online Compliance Date Online Compliance Remarks Compliance Date Compliance Remarks
30-Jun-2020 The application for registration of the project was considered by the authority. The Planning Assistant briefed about the project.  There are certain clarification which are likely to be obtained from the promoter such as the promoter has submitted the non-encumbrance certificate whereas on the other part, project land is mortgaged by the company has been mentioned.  The promoter has submitted reply of the show cause notice dated 29.5.2020 on 26.6.2020.  The reply needs to be examined.  The deficiencies if any remain even after this reply same shall be communicated to the promoter immediately so that before next date compliance is done otherwise the application for   registration shall be rejected.  Matter is fixed for 13th of July 2020 at 3-00 PM online.   Not Yet
04-Jun-2020 Show cause hearing on 29.06.2020 Not Yet