Project Name | Project Location | Project District | Project Tehsil | Promoter Name |
---|---|---|---|---|
Godrej Meridien Phase III | Sector 106 | GURUGRAM | Gurgaon | Godrej Real View Developers Private Limited |
Project Registration Number | Project Id | Receiving Date | Online Submission Date | Current Status | Next Date of Hearing | Notice Dispatched | Notice Dispatched On | Notice Tracking Id | Notice Dispatched Remarks | View Notice | Initially Scrutinized Remarks | Details of Project(Form A-H) |
---|---|---|---|---|---|---|---|---|---|---|---|---|
GGM/393/125/2020/09 DATED 10.02.2020 | RERA-GRG-517-2019 | 24-Dec-2019 | 24-Dec-2019 | APPROVED AND CERTIFICATE UPLOADED | NOT REQUIRED | Yes | 04-Jan-2020 | by hand | 1st deficiency notice | 1st deficiency notice sent to the promoter. | View Form(A-H) |
Project Registration Number | Uploading Date | Remarks | View Certificate |
---|---|---|---|
GGM/393/125/2020/09 DATED 10.02.2020 | 20-Feb-2020 | RC Approved and Uploaded |
Date of Hearing | Proceedings of the day | Status | Order |
---|---|---|---|
02-Mar-2020 | Sh. Rahu Soni is present on behalf of the builder authorized through board resolution. As per the approved building plan, 2 phases were registered, and phase III is applied for registration in the authority. The approach to the site is through 24 m wide proposed road and the promoter has obtained the road approach NOC which provide approach to the site through temporary access 18 m wide culvert till the time 24 m wide proposed road is constructed. Hence, the authority approved the registration of project subject to the conditions mentioned in the registration certificate. Also, the authority directed the promoter to submit the affidavit of declaration that the promoter will complete the construction of 24 m wide proposed road before giving possession to the allottees and submit the PERT chart showing the progress of completion of the road within 7 days. | APPROVED AND READY FOR CERTIFICATE ISSUING PROCESS | --- |
02-Mar-2020 | OBJECTION | --- | |
10-Feb-2020 | Sh. Rahu Soni is present on behalf of the builder authorized through a board resolution. As per the approved building plan, 2 phases were registered, and phase III is applied for registration in the authority. The approach to the site is through 24 m wide proposed road which is not constructed till date. Also, the promoter has obtained the road approach NOC which provide approach to the site through temporary access 18 m wide culvert till the time 24 m wide proposed road is constructed. The site is not approachable through 24 m wide proposed road which is running parallel through the project land as well as through the other adjoining project land. Hence, the allottees cannot get access to the site till this 24 m wide proposed road is developed by the promoter as well as by the other adjoining land developers.The matter will be heard on 02.03.2020. | OBJECTION | --- |
27-Jan-2020 | Sh. Rahu Soni is present on behalf of the builder authorized through board resolution. Copy placed on record. Vide notice dated 04.01.2020, deficiencies were pointed out vide no. HARERA/GGM/RPIN/212 dated 04.01.2020. The authorized representative stated that he has brought all the deficiency documents along with a bank draft of Rs. 23,75,000/- as deficiency fee. The office is asked to scrutinize the deficiencies. Mining certificate is not brought on record. The builder is directed to place it on record before starting of the project. | EXAMINATION BY AUTHORITY | --- |
Deficiency Date | Deficiency Remarks | Online Compliance Done | Online Compliance Date | Online Compliance Remarks | Compliance Date | Compliance Remarks |
---|---|---|---|---|---|---|
12-Feb-2020 | Sh. Rahu Soni is present on behalf of the builder authorized through a board resolution. As per the approved building plan, 2 phases were registered, and phase III is applied for registration in the authority. The approach to the site is through 24 m wide proposed road which is not constructed till date. Also, the promoter has obtained the road approach NOC which provide approach to the site through temporary access 18 m wide culvert till the time 24 m wide proposed road is constructed. The site is not approachable through 24 m wide proposed road which is running parallel through the project land as well as through the other adjoining project land. Hence, the allottees cannot get access to the site till this 24 m wide proposed road is developed by the promoter as well as by the other adjoining land developers.The matter will be heard on 02.03.2020. | Not Yet | ||||
01-Feb-2020 | Sh. Rahu Soni is present on behalf of the builder authorized through board resolution. Copy placed on record. Vide notice dated 04.01.2020, deficiencies were pointed out vide no. HARERA/GGM/RPIN/212 dated 04.01.2020. The authorized representative stated that he has brought all the deficiency documents along with a bank draft of Rs. 23,75,000/- as deficiency fee. The office is asked to scrutinize the deficiencies. Mining certificate is not brought on record. The builder is directed to place it on record before starting of the project. | Not Yet |