M-11, MIDDLE CIRCUS CONNAUGHT CIRCUS, NEW DELHI-110001.
01149572787
9871883334 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
http://bptp.com
XXXX540P
U70109DL2006PLC153109
PRIDE FLOORS
SECTOR- 77-78, FARIDABAD.
FARIDABAD
FARIDABAD
8800414400
8800414400 (Number Shared by Promoter in Public)
VINOD2.KUMAR@BPTP.COM
VINOD KUMAR
8800414400
8800414400 (Number Shared by Promoter in Public)
VINOD2.KUMAR@BPTP.COM
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
230806
16-12-2017
93887
INDUSIND BANK LIMITED
HRERA Panchkula
5.22 (Acre)
1
1
152.973 (Acre)
License No. 30 of 2010 (Renewal Applied on June 06, 2018) and License no. 12 of 2012.(Renewal Applied on June 06, 2018).
Yes
5119.31 Lakhs
894.58 Lakhs
2699.16 Lakhs
169.78 Lakhs
1355.79 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
9371
3
CONSTRUCTION OF ROADS
6667
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
5120
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
21158
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
No
ELECTRICITY
DHBVNL
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
20.78
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
11.00
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
24.27
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
26.88
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
2.17
SUBMITTED TO HUDA
6
STREET LIGHTING
2.52
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
4.22
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
72.14
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO HUDA
10
SHOPPING AREA
5.79
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO HUDA
12
SCHOOL
0
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO HUDA
14
ANY OTHER
0
SUBMITTED TO HUDA
09-12-2011 (date)
20-03-2013 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type FLOORS ON PLOTS
158
174
138
36
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
FLOORS ON PLOTS
138
AS ANNEXED.
15-05-2012
31-10-2015
31-12-2022
15-05-2012
70
31-12-2022
AS MENTIONED.
AS ANNEXED.
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
31-12-2022
0
31-12-2022
NA
NA
0
0
0
174
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
2531.47
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
0
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
10
12
13
10
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
10
10
12
11
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
10
12
12
11
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
11
11
12
Shops
0
0
0
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
20.78
Water Supply System
11.00
Sewerage treatment & garbage disposal
2.17
Electricity Supply System
29.40
Storm Water Drainage
24.27
Parks and Playgrounds
72.14
Clubhouse/community centres
0
Shopping area
5.79
Other
4.22
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.35
0.25
0.5
0.25
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0.55
0.25
0.25
0.7
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
2.6
2.25
3.25
1.5
Clubhouse/community centres
0
0
0
0
Shopping area
0.55
0.55
0.45
0.4
Other
0
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0.3
0.4
0.3
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0.25
0.3
0.35
0.45
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
1.35
1.75
2.4
1.25
Clubhouse/community centres
0
0
0
0
Shopping area
0.1
0.47
0.25
0.2
Other
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.25
0
0
0
Water Supply System
0.5
0
0
0.16
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0.2
0.35
0.4
0.35
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
2.1
2.25
1.45
2.35
Clubhouse/community centres
0
0
0
0
Shopping area
0.35
0.15
0.1
0.25
Other
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.3
0.2
0.3
Water Supply System
0.5
0.2
0.2
Sewerage treatment & garbage disposal
0
1
1.17
Electricity Supply System
0.65
0.8
0.35
Storm Water Drainage
0
0.4
0
Parks and Playgrounds
2.79
2.2
3.3
Clubhouse/community centres
0
0
0
Shopping area
0.2
0
0.4
Other
0.2
0.2
0.17
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
174
ii. No. of Flats/ Apartments booked
138
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
6100 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
4800 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
1300 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1300 Lakhs
vii. Amount invested in the project upto the date of application
4900.20 Lakhs
Land cost (If any)
894.58 Lakhs
Apartments
2531.47 Lakhs
Infrastructure
118.36 Lakhs
EDC/ Taxes Etc.
1355.79 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
219.12 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
There is a loan amount which shall be given with bifurcation in physical.As the same has to be done on pro-data basis.
x. Total liabilities against the project up-to-date. (Annex details in folder C)
631.20 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
20.78
17.45
II. WATER SUPPLY SYSTEM
11.00
9.45
III. STORM WATER DRAINAGE
24.27
24.27
IV. ELECTRICITY SUPPLY SYSTEM
29.40
23.21
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
2.17
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
72.14
39.35
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
4.22
3.65
XVII. OTHER FACILITIES AS PER PROJECT REPORT
5.79
0.98
Yes
Yes
YES BANK
101963400000078
00
00
00
Mr. Rakesh Kumar Aggarwal
Mr. Inderbir Singh Bhatia
As Annexed.
Yes
No
Yes
Yes
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. ZONING PLAN
ALREADY BEEN OBTAINED
03-08-2012
II. LICENSE NO. 12 OF 2012
ALREADY BEEN OBTAINED
22-04-2012
III. BUILDING PLAN
ALREADY BEEN OBTAINED
20-03-2013
IV. LICENSE NO. 30 OF 2010
ALREADY BEEN OBTAINED
01-04-2010
V. BUILDING PLAN
ALREADY BEEN OBTAINED
22-10-2012
VI. ENVIRONMENTAL CLEARANCE
ALREADY BEEN OBTAINED
06-09-2013
VII. RENEWAL OF LICENSE NO. 30 OF 2010
APPLIED FOR BUT YET TO RECEIVE
06-06-2018
VIII. LICENSE NO. 12 OF 2012
APPLIED FOR BUT YET TO RECEIVE
06-06-2018
Yes
Yes
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES IN LIVING ROOM & BEDROOM; LAMINATED WOODEN FLOORING/ VITRIFIED TILES IN MASTER BEDROOM.
ANTI-SKID CERAMIC TILES IN KITCHEN.
SELECT GRANITE/MARBLE IN STAIRCASE.
2
WALL FINISHING DETAILS
PAINTED IN PLEASING SHADES OF PLASTIC EMULSION.
PAINT IN LIVING ROOM AND BEDROOM.
3
KITCHEN DETAILS
CERAMIC TILES UPTO 2 FEET ABOVE. WORKING PLATFORM AND THE REST PAINTED IN OIL BOUND DISTEMPER.
GRANITE COUNTER WITH SINGLE BOWL STAINLESS STEEL SINK AND SKIN BOARD.
4
BATHROOM FITTINGS
SELECT CERAMIC TILES.
WHITE SANITARY WARE, GEYSERS AND CONTEMPORARY CHROME PLATED FITTINGS.
5
WOOD WORK ETC
SEASONED HARDWOOD FRAMES WITH PAINTED BOARD SHUTTERS.
6
DOORS AND WINDOS FRAMES
SEASONED HARDWOOD FRAMES WITH PAINTED BOARD SHUTTERS UPVC.
7
GLASS WORK
NOT PROVIDED.
8
ELECTRIC FITTINGS
ELECTRICAL COPPER WIRING IN CONCEAL CONDUITS FOR ALL LIGHT AND POWER POINTS.
9
CONDUCTING AND WIRING DETAILS
ELECTRICAL COPPER WIRING IN CONCEAL CONDUITS FOR ALL LIGHT AND POWER POINTS.
10
CUPBOARD DETAILS
NEED TO FILL LATER
11
WATER STORAGE
NA
12
LIFT DETAILS
NOT APPLICABLE
13
EXTERNAL GLAZINGS
BASIC WINDOWS
13.1
WINDOWS/GLAZINGS
BASIC WINDOWS
14
DOORS
SEASONED WOOD
14.1
MAIN DOORS
SEASONED WOOD.
14.2
INTERNAL DOORS
SEASONED WOOD
15
AIR CONDITIONING
NOT PROVIDED.
16
ELECTRICAL FITTINGS
CONDUIT COPPER ELECTRICAL WIRING FOR ALL LIGHT AND POWER POINTS.
17
CNG PIPE LINE
NOT PROVIDED
18
PROVISION OF WIFI AND BROADBAND FACILITY
NOT PROVIDED.
19
EXTERNAL FINISHING/COLOUR SCHEME
-
20
INTERNAL FINISHING
-
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VITRIFIED TILES
1 . 2
WALLS
PAINTED IN PLEASING SHADES OF EMULSION PAINTS.
1 . 3
CEILING
PAINTED IN PLEASING SHADES OF EMULSION PAINTS.
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOODEN FLOORING/VITRIFIED TILES.
2 . 2
WALLS
PAINTED IN PLEASING SHADES OF PLASTIC EMULSION PAINT
2 . 3
CEILING
PAINTED IN PLEASING SHADES OF PLASTIC EMULSION PAINT
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC TILES
3 . 2
WALLS
SELECT CERAMIC TILES
3 . 3
CEILING
PLASTER WITH WHITE WASH.
3 . 4
COUNTERS
WHITE SANITARY WARES
3 . 5
SANITARY WARE/CP FITTINGS
GEYSERS AND CONTEMPORARY CHROME PLATED FITTING.
3 . 6
FITTING/FIXTURES
WHITE SANITARY WARE.
4 . BED ROOMS
4 . 1
FLOOR
VITRIFIED TILES
4 . 2
WALLS
PAINTED IN PLEASING SHADES OF PLASTIC EMULSION PAINT
4 . 3
CEILING
PLASTER WITH WHITE WASH.
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
CERAMIC TILES
5 . 2
WALLS
SELECT CERAMIC TILES FOR SOME FT.
5 . 3
CEILING
PLASTER WITH WHITE WASH.
5 . 4
COUNTERS
WHITE SANITARY WARE
5 . 5
SANITARY WARE/CP FITTINGS
CONTEMPORARY CHROME PLATED FITTINGS.
5 . 6
FIXTURES
CP FITTINGS WHITE SANITARY FIXTURES.
6 . KITCHEN
6 . 1
FLOOR
ANTI SKID CERAMIC TILES
6 . 2
WALLS
CERAMIC TILES UP TO 2 FT. ABOVE WORKING PLATFORM AND THE REST PAINTED IN OIL BOUND DISTEMPER.
6 . 3
CEILING
OIL BOUND DISTEMPER
6 . 4
COUNTERS
GRANITE COUNTER
6 . 5
FIXTURES
SINGLE BOWL STAINLESS STEEL STINK AND DRAIN BOARD.