HRERA GurugramTemp Project Id : RERA-GRG-PROJ-276-2019
Submission Date : 30-07-2019 11:54:45 AM
Applicant Type : Company
Project Type: ONGOING




COSMOS INFRA ENGINEERING INDIA PVT LTD
5 A,C,D, 5TH FLOOR, VANDHNA BUILDING, 11 TOLSTOY MARG, NEW DELHI 110001
01123463500
9711003249 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com
http://www.cosmosinfra.com
XXXX017C
U70101DL1986PTC022930
 
 


 
 


 
 


 
 







COSMOS EXPRESS99 / CASCADE GARDEN
VILLAGE DHANKOT, SECTOR-99
GURGAON
GURUGRAM
9711003244 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com
HARIKISHAN TYAGI
9711003244 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
110089629-07-2017375000HDFC BANKHRERA Gurugram
226035511-06-2018283110HDFC BANKHRERA Gurugram
394213803-10-20191671424RBL BANKHRERA Gurugram







5.468 (Acre)
37358.373
1.75
13.320 (Acre)
70 of 2011 dt. 22.07.2011 and 82 of 2012 dt. 27.08.2012
No
Address     4, BATTERY LANE, RAJPUR ROAD. CIVIL LINES, NEW DELHI 110054
Annexure-B- THE APPLICANT IS THE DEVELOPER OF THE PROJECT AND HAS ENTERED INTO A DEVELOPMENT AGREEMENT WITH THE LAND OWNER. THE AGREEMENT IS ENCLOSED.
THE AGREEMENT FOR COLLABORATION HAS BEEN ENTERED AFTER THE GRANT OF LICENSE. CONSEQUENTLY, CHANGE OF DEVELOPER CERTIFICATE HAS BEEN RECEIVED BY THE APPLICANT.
Yes
THE LICENSEE IS DESIROUS ASSIGNING THE RIGHTS OF DEVELOPMENT AND MARKETING TO THE EXTENT OF 45.45% OF THE AFORESAID DEVELOPMENT RIGHTS, MARKETING AND SALE RIGHTS (ALONG WITH ASSOCIATED RESTRICTIONS AND RESPONSIBILITIES) ALONG WITH PROPORTIONATE RIGHTS AND TITLE IN THE TOTAL PROJECT LAND AND ALONG WITH ALL RIGHTS APPURTENANT THERETO (HEREINAFTER REFERRED TO AS THE PART PROJECT) TO THE ASSIGNEE. THIS PART PROJECT IS MORE CLEARLY DEFINED LATER IN THE AGREEMENT. THE AGREEMENTS HAS BEEN ANNEXED IN FOLDER B.
No
Yes
Yes







22362 Lakhs
1698.35 Lakhs
9000 Lakhs
1400 Lakhs
10263.65 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.238
3CONSTRUCTION OF ROADS0.786
4PAVEMENTS0.262
5PARKS AND PLAYGROUNDS0.497
6GREEN BELTS0.324
7VEHICLE PARKINGS0.463
8ELECTRICITY SUB-STATION0.042
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.038
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.41
12ANY OTHER1.313
13COMMUNITYCENTRE0.033
14COMMERCIALCENTRE0.026
15RAINWATERHARVESTING0.009
16SCHOOL0.027
Total5.468




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA SHAHARI VIKAS PRADHIKARAN, GURGAONNo
WATER SUPPLYHARYANA SHAHARI VIKAS PRADHIKARAN, GURGAONYes
ELECTRICITYDAKSHIN HARYANA BIJLI VITRAN NIGAMYes
SEWAGE DISPOSALHARYANA SHAHARI VIKAS PRADHIKARAN, GURGAONNo
STORM WATER DRAINAGEHARYANA SHAHARI VIKAS PRADHIKARAN, GURGAONNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS147.65SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM156.40SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE44.72SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM225.50YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL63.86SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING20.95SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING185.01YET TO BE PREPARED
8PLAYGROUNDS AND PARKS45.96SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE40YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM33.00YET TO BE PREPARED
12SCHOOL18YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PARKING94.50YET TO BE PREPARED
16STP43.50YET TO BE PREPARED
17UNDERGROUND WATER TANK64.95YET TO BE PREPARED
18RAIN WATER23.00YET TO BE PREPARED
19ELECTRIC SUB STATION193.00YET TO BE PREPARED


07-07-2017 (date)
07-07-2017 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2) / PODIUM153.352021
2APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2)/ TYPICAL153.35224181
3APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2)/ PENTHOUSE234.572201
4APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PODIUM91.642021
5APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PODIUM100.092111
6APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/TYPICAL91.64222111
7APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/TYPICAL100.09222111
8APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PENTHOUSE129.282201
9APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PENTHOUSE140.982201
10APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PODIUM66.906511
11APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PODIUM78.362021
12APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/TYPICAL66.90666331
13APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/TYPICAL78.36221931
14APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PENTHOUSE102.286511
15APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PENTHOUSE115.112021
16APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PODIUM94.804131
17APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PODIUM78.364131
18APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/TYPICAL94.804431131
19APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/TYPICAL78.36443861
20APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PENTHOUSE140.084221
21APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PENTHOUSE115.114221
22APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER S(SERVICE TOWER)/TYPICAL40.806417471
23APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER EWS16.06510511






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TOWER C(TOWER 1)/TYPICAL21AS PER ANNEXURE
TOWER C(TOWER 1)/PENTHOUSE2AS PER ANNEXURE
TOWER C(TOWER 1)/PENTHOUSE2AS PER ANNEXURE
TOWER D(TOWER 4)/PODIUM5AS PER ANNEXURE
TOWER D(TOWER 4)/PODIUM0AS PER ANNEXURE
TOWER D(TOWER 4)/TYPICAL63AS PER ANNEXURE
TOWER D(TOWER 4)/TYPICAL19AS PER ANNEXURE
TOWER D(TOWER 4)/PENTHOUSE5AS PER ANNEXURE
TOWER D(TOWER 4)/PENTHOUSE0AS PER ANNEXURE
TOWER E(TOWER 5)/PODIUM1AS PER ANNEXURE
TOWER E(TOWER 5)/PODIUM1AS PER ANNEXURE
OWER B(TOWER 2) / PODIUM0AS PER ANNEXURE
TOWER B(TOWER 2)/ TYPICAL4AS PER ANNEXURE
TOWER B(TOWER 2)/ PENTHOUSE2AS PER ANNEXURE
TOWER C(TOWER 1)/PODIUM0AS PER ANNEXURE
TOWER C(TOWER 1)/PODIUM1AS PER ANNEXURE
TOWER C(TOWER 1)/TYPICAL21AS PER ANNEXURE
TOWER E(TOWER 5)/TYPICAL31AS PER ANNEXURE
TOWER E(TOWER 5)/TYPICAL38AS PER ANNEXURE
TOWER E(TOWER 5)/PENTHOUSE2AS PER ANNEXURE
TOWER E(TOWER 5)/PENTHOUSE2AS PER ANNEXURE
TOWER S(SERVICE TOWER)/TYPICAL17AS PER ANNEXURE
TOWER EWS0AS PER ANNEXURE


30-09-2012
30-09-2017
30-09-2021
30-09-2012
25
30-09-2021
FURTHER DETAILS IN REP-1 PART C-X.
AS PER ANNEX IN FOLDER C


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
30-09-2012
0
30-09-2021


300
140
440
67
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments7800
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments05075
Shops000
Plots000

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments100125150175
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments175175154
Shops0021
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements42
Water Supply System19
Sewerage treatment & garbage disposal24.50
Electricity Supply System87.50
Storm Water Drainage17.50
Parks and Playgrounds17.50
Clubhouse/community centres15
Shopping area0
Other0
construction of circulation road8.50
Electrical sub station29
Parking12
Rain water4.50
security42.50
Street Light7.50
Underground Water tank48

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements002.005.00
Water Supply System0001.00
Sewerage treatment & garbage disposal001.003.20
Electricity Supply System0000
Storm Water Drainage002.000
Parks and Playgrounds0000
Clubhouse/community centres004.004.00
Shopping area0000
Other0000
Renewable Energy Systems0000
Security Systems0008.50
Street Lighting0000.30
Rain Water Harvesting0000
Electrical Substation006.015.00
Underground Water Tank001.001.00
STP0000
Parking0010.0016.00

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.500.505.005.00
Water Supply System25.0031.0025.008.00
Sewerage treatment & garbage disposal7.008.0012.002.00
Electricity Supply System010.0020.0035.00
Storm Water Drainage2.001.0008.00
Parks and Playgrounds2.001.004.056.00
Clubhouse/community centres4.004.0042
Shopping area0000
Other0000
STP00014.00
Underground Water Tank1.001.001.955.00
Rain Water Harvesting03.001.001.00
Street Lighting0000
Security and Firefighting Systems8.5020.0016.0015.00
Renewable Energy Systems0000
Parking10.006.505.006.00
Electrical Substation19.0018.0025.0020.00
School3

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements5.0018.0056.150
Water Supply System10.0016.0021.400
Sewerage treatment & garbage disposal04.551.610
Electricity Supply System44.0020.009.000
Storm Water Drainage7.005.002.220
Parks and Playgrounds10.003.002.410
Clubhouse/community centres1110
Shopping area0000
Other0000
Security and Firefighting Systems20.0040.0014.51
Underground Water Tank0.5005.50
Rain Water Harvesting2.0010.001.50
Electrical Substation23.0020.0018.00
Street Lighting00.4512.70
Renewable Energy Systems8.0014.0011.00
Parking14.005.0010.00
STP11.509.009.00
School555












Particulars Remarks, if any
i. No. of Flats/Apartments constructed350Total No. of Flats being constructed in the Project
ii. No. of Flats/ Apartments booked237No. of Apartments Booked till the Date of Application
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter18021 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter13566 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter4455 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter1340 Lakhs
vii. Amount invested in the project upto the date of application19467.65 Lakhs
Land cost (If any)1698.35 Lakhs
Apartments7800 Lakhs
Infrastructure375 Lakhs
EDC/ Taxes Etc.9594.30 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession2895 Lakhs
(a) In respect of existing allottees1971.07 Lakhs
(b) In respect of rest of the project923.93 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
5784 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 5794 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS11842
II. WATER SUPPLY SYSTEM156.4019
III. STORM WATER DRAINAGE44.7217.50
IV. ELECTRICITY SUPPLY SYSTEM225.5087.50
V. SEWAGE TREATMENT & GARBAGE DISPOSAL63.8624.50
VI. CLUB HOUSE/COMMUNITY CENTRE4015
VII. SCHOOL180
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.45.9617.50
XIII. COVERED PARKING00
XIV. OPEN PARKING94.5012
XV. GARAGES00
XVI. SECURITY SYSTEM185.0142.50
XVII. OTHER FACILITIES AS PER PROJECT REPORT408.0597.5









Yes
Yes
HDFC BANK, 209-214, KAILASH BUILDING, 26, KASTURBA GANDHI MARG, DELHI-110001
30350022549
HDFC0000003
110240001
000003
Pranav Mittal
As per Certificate Attached.











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ENVIRONMENT CLEARANCE APPROVALALREADY BEEN OBTAINED24-12-2013
II. AIRPORT HEIGHT CLEARANCE ALREADY BEEN OBTAINED16-05-2018
III. FIRE SCHEME APPROVAL ALREADY BEEN OBTAINED16-07-2018
IV. SERVICE PLAN ESTIMATES APPROVAL ALREADY BEEN OBTAINED21-06-2019
V. LICENSE APPROVAL ALREADY BEEN OBTAINED22-07-2011
VI. ZONING PLAN APPROVAL ALREADY BEEN OBTAINED27-08-2012
VII. BUILDING PLAN / SITE PLAN APPROVAL ALREADY BEEN OBTAINED07-07-2017








Yes


Yes


Possession Date 30.09.2021













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE, BALCONY : CERAMIC TILE
2WALL FINISHING DETAILSOIL BOUND DISTEMPER
3KITCHEN DETAILSFLOORING : CERAMIC TILE WALL : CERAMIC TILE UPTO 600 MM HEIGHT ABOVE THE PLATFORM
4BATHROOM FITTINGSWALL : CERAMIC TILE UPTO 2100 MM HEIGHT, FLOORING : CERAMIC TILE
5WOOD WORK ETCALMIRAH IN KITCHEN AND BEDROOMS
6DOORS AND WINDOS FRAMESALL FLUSH DOOR FINISHED WITH PAINTS, HARDWOOD DOOR FRAME, WINDOW HARD WOOD
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSPROVISION OF SUFFICIENT LIGHTS & POWER POINT IN ALL ROOMS. TV & TELEPHONE SOCKETS IN DRAWING ROOM
9CONDUCTING AND WIRING DETAILSCOPPER WIRING IN CONCEALED CONDUIT
10CUPBOARD DETAILSALMIRAH IN KITCHEN AND BEDROOMS
11WATER STORAGEUNDER GROUND & OVER HEAD TANKS
12LIFT DETAILSPASSENGER & SERVICES LIFT IN ALL TOWERS
13EXTERNAL GLAZINGSNIL
13.1WINDOWS/GLAZINGSHARDWOOD WITH GLASS
14DOORSFLUSH DOOR WITH PAINT
14.1MAIN DOORSFLUSH DOOR WITH PAINT
14.2INTERNAL DOORSFLUSH DOOR WITH PAINT
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSPROVISION OF SUFFICIENT LIGHTS & POWER POINT IN ALL ROOMS. TV & TELEPHONE SOCKETS IN DRAWING ROOM.
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMEPAINT FINISH
20INTERNAL FINISHINGOBD PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD PAINT
1 . 3 CEILINGOBD PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSOBD PAINT
2 . 3 CEILINGOBD PAINT
2 . 4 MODULAR WARDROBESWOODEN WARDROBES
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES
3 . 2 WALLSCERAMIC TILE UPTO 2100 MM HEIGHT
3 . 3 CEILINGFALSE CEILING
3 . 4 COUNTERSFINISHING WITH GRANITE
3 . 5 SANITARY WARE/CP FITTINGSSTANDARD BRAND FITTINGS
3 . 6 FITTING/FIXTURESSTANDARD BRAND FITTINGS
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOBD PAINT
4 . 3 CEILINGOBD PAINT
4 . 4 WARDROBESWOODEN WARDROBES
5 . TOILET
5 . 1 FLOORCERAMIC TILES
5 . 2 WALLSCERAMIC TILE UPTO 2100 MM HEIGHT
5 . 3 CEILINGFALSE CEILING
5 . 4 COUNTERSFINISHING WITH GRANITE
5 . 5 SANITARY WARE/CP FITTINGSSTANDARD BRAND FITTINGS
5 . 6 FIXTURESSTANDARD BRAND FITTINGS
6 . KITCHEN
6 . 1 FLOORCERAMIC TILES
6 . 2 WALLSCERAMIC TILE UPTO 600 MM HEIGHT ABOVE THE PLATFORM
6 . 3 CEILINGOBD PAINT
6 . 4 COUNTERS600 MM WIDE, FINISH WITH GRANITE
6 . 5 FIXTURESSTANDARD BRAND
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGCERAMIC TILE UPTO 2100MM HEIGHT CEILING : OBD PAINT
7 . 3 TOILETWALL : CERAMIC TILE UPTO 2100 MM HEIGHT, FLOORING: CERAMIC TILE
7 . 4 BALCONYMS RAILING FINISH WITH PAINT
8 . SIT-OUTS
8 . 1 FLOORCERAMIC TILES
8 . 2 WALLS & CEILINGOBD PAINT
8 . 3 RAILINGSMS RAILING FINISH WITH PAINT
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT11-10-2019 View Document
2SUPERIMPOSED PLAN12-10-2019 ------
3DEMARCATION PLAN11-10-2019 View Document
4NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT27-07-2019 View Document
5A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-07-2019 View Document
6ZONING PLAN27-07-2019 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN27-07-2019 View Document
8COPY OF LICENSE ALONG WITH SCHEDULE OF LAND27-07-2019 View Document
9IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN27-07-2019 View Document
10DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD30-07-2019 View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT30-07-2019 View Document
12DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.30-07-2019 View Document
13SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN30-07-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 PROJECT CONTINUATION- RC/REP/HARERA/GGM/62 OF 2019/7(3)/31/2023/08 DATED 29.03.2023 06-09-2023 View Document