9711003249 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com
http://www.cosmosinfra.com
XXXX017C
U70101DL1986PTC022930
COSMOS EXPRESS99 / CASCADE GARDEN
VILLAGE DHANKOT, SECTOR-99
GURGAON
GURUGRAM
9711003244 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com
HARIKISHAN TYAGI
9711003244 (Number Shared by Promoter in Public)
customersupport@cosmosinfra.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Annexure-B- THE APPLICANT IS THE DEVELOPER OF THE PROJECT AND HAS ENTERED INTO A DEVELOPMENT AGREEMENT WITH THE LAND OWNER. THE AGREEMENT IS ENCLOSED.
THE AGREEMENT FOR COLLABORATION HAS BEEN ENTERED AFTER THE GRANT OF LICENSE. CONSEQUENTLY, CHANGE OF DEVELOPER CERTIFICATE HAS BEEN RECEIVED BY THE APPLICANT.
Yes
THE LICENSEE IS DESIROUS ASSIGNING THE RIGHTS OF DEVELOPMENT AND MARKETING TO THE EXTENT OF 45.45% OF THE AFORESAID DEVELOPMENT RIGHTS, MARKETING AND SALE RIGHTS (ALONG WITH ASSOCIATED RESTRICTIONS AND RESPONSIBILITIES) ALONG WITH PROPORTIONATE RIGHTS AND TITLE IN THE TOTAL PROJECT LAND AND ALONG WITH ALL RIGHTS APPURTENANT THERETO (HEREINAFTER REFERRED TO AS THE PART PROJECT) TO THE ASSIGNEE. THIS PART PROJECT IS MORE CLEARLY DEFINED LATER IN THE AGREEMENT. THE AGREEMENTS HAS BEEN ANNEXED IN FOLDER B.
No
Yes
Yes
22362 Lakhs
1698.35 Lakhs
9000 Lakhs
1400 Lakhs
10263.65 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1.238
3
CONSTRUCTION OF ROADS
0.786
4
PAVEMENTS
0.262
5
PARKS AND PLAYGROUNDS
0.497
6
GREEN BELTS
0.324
7
VEHICLE PARKINGS
0.463
8
ELECTRICITY SUB-STATION
0.042
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.038
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.41
12
ANY OTHER
1.313
13
COMMUNITYCENTRE
0.033
14
COMMERCIALCENTRE
0.026
15
RAINWATERHARVESTING
0.009
16
SCHOOL
0.027
Total
5.468
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HARYANA SHAHARI VIKAS PRADHIKARAN, GURGAON
No
WATER SUPPLY
HARYANA SHAHARI VIKAS PRADHIKARAN, GURGAON
Yes
ELECTRICITY
DAKSHIN HARYANA BIJLI VITRAN NIGAM
Yes
SEWAGE DISPOSAL
HARYANA SHAHARI VIKAS PRADHIKARAN, GURGAON
No
STORM WATER DRAINAGE
HARYANA SHAHARI VIKAS PRADHIKARAN, GURGAON
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
147.65
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
156.40
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
44.72
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
225.50
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
63.86
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
20.95
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
185.01
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
45.96
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
40
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
33.00
YET TO BE PREPARED
12
SCHOOL
18
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
PARKING
94.50
YET TO BE PREPARED
16
STP
43.50
YET TO BE PREPARED
17
UNDERGROUND WATER TANK
64.95
YET TO BE PREPARED
18
RAIN WATER
23.00
YET TO BE PREPARED
19
ELECTRIC SUB STATION
193.00
YET TO BE PREPARED
07-07-2017 (date)
07-07-2017 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2) / PODIUM
153.35
2
0
2
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2)/ TYPICAL
153.35
22
4
18
1
3
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER B(TOWER 2)/ PENTHOUSE
234.57
2
2
0
1
4
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PODIUM
91.64
2
0
2
1
5
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PODIUM
100.09
2
1
1
1
6
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/TYPICAL
91.64
22
21
1
1
7
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/TYPICAL
100.09
22
21
1
1
8
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PENTHOUSE
129.28
2
2
0
1
9
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER C(TOWER 1)/PENTHOUSE
140.98
2
2
0
1
10
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PODIUM
66.90
6
5
1
1
11
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PODIUM
78.36
2
0
2
1
12
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/TYPICAL
66.90
66
63
3
1
13
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/TYPICAL
78.36
22
19
3
1
14
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PENTHOUSE
102.28
6
5
1
1
15
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER D(TOWER 4)/PENTHOUSE
115.11
2
0
2
1
16
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PODIUM
94.80
4
1
3
1
17
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PODIUM
78.36
4
1
3
1
18
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/TYPICAL
94.80
44
31
13
1
19
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/TYPICAL
78.36
44
38
6
1
20
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PENTHOUSE
140.08
4
2
2
1
21
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER E(TOWER 5)/PENTHOUSE
115.11
4
2
2
1
22
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER S(SERVICE TOWER)/TYPICAL
40.80
64
17
47
1
23
APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER EWS
16.06
51
0
51
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
TOWER C(TOWER 1)/TYPICAL
21
AS PER ANNEXURE
TOWER C(TOWER 1)/PENTHOUSE
2
AS PER ANNEXURE
TOWER C(TOWER 1)/PENTHOUSE
2
AS PER ANNEXURE
TOWER D(TOWER 4)/PODIUM
5
AS PER ANNEXURE
TOWER D(TOWER 4)/PODIUM
0
AS PER ANNEXURE
TOWER D(TOWER 4)/TYPICAL
63
AS PER ANNEXURE
TOWER D(TOWER 4)/TYPICAL
19
AS PER ANNEXURE
TOWER D(TOWER 4)/PENTHOUSE
5
AS PER ANNEXURE
TOWER D(TOWER 4)/PENTHOUSE
0
AS PER ANNEXURE
TOWER E(TOWER 5)/PODIUM
1
AS PER ANNEXURE
TOWER E(TOWER 5)/PODIUM
1
AS PER ANNEXURE
OWER B(TOWER 2) / PODIUM
0
AS PER ANNEXURE
TOWER B(TOWER 2)/ TYPICAL
4
AS PER ANNEXURE
TOWER B(TOWER 2)/ PENTHOUSE
2
AS PER ANNEXURE
TOWER C(TOWER 1)/PODIUM
0
AS PER ANNEXURE
TOWER C(TOWER 1)/PODIUM
1
AS PER ANNEXURE
TOWER C(TOWER 1)/TYPICAL
21
AS PER ANNEXURE
TOWER E(TOWER 5)/TYPICAL
31
AS PER ANNEXURE
TOWER E(TOWER 5)/TYPICAL
38
AS PER ANNEXURE
TOWER E(TOWER 5)/PENTHOUSE
2
AS PER ANNEXURE
TOWER E(TOWER 5)/PENTHOUSE
2
AS PER ANNEXURE
TOWER S(SERVICE TOWER)/TYPICAL
17
AS PER ANNEXURE
TOWER EWS
0
AS PER ANNEXURE
30-09-2012
30-09-2017
30-09-2021
30-09-2012
25
30-09-2021
FURTHER DETAILS IN REP-1 PART C-X.
AS PER ANNEX IN FOLDER C
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
30-09-2012
0
30-09-2021
300
140
440
67
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
7800
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
50
75
Shops
0
0
0
Plots
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
100
125
150
175
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
175
175
154
Shops
0
0
21
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
42
Water Supply System
19
Sewerage treatment & garbage disposal
24.50
Electricity Supply System
87.50
Storm Water Drainage
17.50
Parks and Playgrounds
17.50
Clubhouse/community centres
15
Shopping area
0
Other
0
construction of circulation road
8.50
Electrical sub station
29
Parking
12
Rain water
4.50
security
42.50
Street Light
7.50
Underground Water tank
48
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
2.00
5.00
Water Supply System
0
0
0
1.00
Sewerage treatment & garbage disposal
0
0
1.00
3.20
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
2.00
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
4.00
4.00
Shopping area
0
0
0
0
Other
0
0
0
0
Renewable Energy Systems
0
0
0
0
Security Systems
0
0
0
8.50
Street Lighting
0
0
0
0.30
Rain Water Harvesting
0
0
0
0
Electrical Substation
0
0
6.0
15.00
Underground Water Tank
0
0
1.00
1.00
STP
0
0
0
0
Parking
0
0
10.00
16.00
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.50
0.50
5.00
5.00
Water Supply System
25.00
31.00
25.00
8.00
Sewerage treatment & garbage disposal
7.00
8.00
12.00
2.00
Electricity Supply System
0
10.00
20.00
35.00
Storm Water Drainage
2.00
1.00
0
8.00
Parks and Playgrounds
2.00
1.00
4.05
6.00
Clubhouse/community centres
4.00
4.00
4
2
Shopping area
0
0
0
0
Other
0
0
0
0
STP
0
0
0
14.00
Underground Water Tank
1.00
1.00
1.95
5.00
Rain Water Harvesting
0
3.00
1.00
1.00
Street Lighting
0
0
0
0
Security and Firefighting Systems
8.50
20.00
16.00
15.00
Renewable Energy Systems
0
0
0
0
Parking
10.00
6.50
5.00
6.00
Electrical Substation
19.00
18.00
25.00
20.00
School
3
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
5.00
18.00
56.15
0
Water Supply System
10.00
16.00
21.40
0
Sewerage treatment & garbage disposal
0
4.55
1.61
0
Electricity Supply System
44.00
20.00
9.00
0
Storm Water Drainage
7.00
5.00
2.22
0
Parks and Playgrounds
10.00
3.00
2.41
0
Clubhouse/community centres
1
1
1
0
Shopping area
0
0
0
0
Other
0
0
0
0
Security and Firefighting Systems
20.00
40.00
14.51
Underground Water Tank
0.50
0
5.50
Rain Water Harvesting
2.00
10.00
1.50
Electrical Substation
23.00
20.00
18.00
Street Lighting
0
0.45
12.70
Renewable Energy Systems
8.00
14.00
11.00
Parking
14.00
5.00
10.00
STP
11.50
9.00
9.00
School
5
5
5
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
350
Total No. of Flats being constructed in the Project
ii. No. of Flats/ Apartments booked
237
No. of Apartments Booked till the Date of Application
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
18021 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
13566 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
4455 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1340 Lakhs
vii. Amount invested in the project upto the date of application
19467.65 Lakhs
Land cost (If any)
1698.35 Lakhs
Apartments
7800 Lakhs
Infrastructure
375 Lakhs
EDC/ Taxes Etc.
9594.30 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
2895 Lakhs
(a) In respect of existing allottees
1971.07 Lakhs
(b) In respect of rest of the project
923.93 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
5784 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
5794 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
118
42
II. WATER SUPPLY SYSTEM
156.40
19
III. STORM WATER DRAINAGE
44.72
17.50
IV. ELECTRICITY SUPPLY SYSTEM
225.50
87.50
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
63.86
24.50
VI. CLUB HOUSE/COMMUNITY CENTRE
40
15
VII. SCHOOL
18
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
45.96
17.50
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
94.50
12
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
185.01
42.50
XVII. OTHER FACILITIES AS PER PROJECT REPORT
408.05
97.5
Yes
Yes
HDFC BANK, 209-214, KAILASH BUILDING, 26, KASTURBA GANDHI MARG, DELHI-110001
30350022549
HDFC0000003
110240001
000003
Pranav Mittal
As per Certificate Attached.
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. ENVIRONMENT CLEARANCE APPROVAL
ALREADY BEEN OBTAINED
24-12-2013
II. AIRPORT HEIGHT CLEARANCE
ALREADY BEEN OBTAINED
16-05-2018
III. FIRE SCHEME APPROVAL
ALREADY BEEN OBTAINED
16-07-2018
IV. SERVICE PLAN ESTIMATES APPROVAL
ALREADY BEEN OBTAINED
21-06-2019
V. LICENSE APPROVAL
ALREADY BEEN OBTAINED
22-07-2011
VI. ZONING PLAN APPROVAL
ALREADY BEEN OBTAINED
27-08-2012
VII. BUILDING PLAN / SITE PLAN APPROVAL
ALREADY BEEN OBTAINED
07-07-2017
Yes
Yes
Possession Date 30.09.2021
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILE,
BALCONY : CERAMIC TILE
2
WALL FINISHING DETAILS
OIL BOUND DISTEMPER
3
KITCHEN DETAILS
FLOORING : CERAMIC TILE
WALL : CERAMIC TILE UPTO 600 MM HEIGHT ABOVE THE PLATFORM
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT