HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1965-2026
Submission Date : 09-02-2026 02:10:57 PM
Applicant Type : Company
Project Type: NEW




ALPHA CORP DEVELOPMENT LIMITED
602, 6TH FLOOR, TOWER-J, WORLD TRADE CENTRE, NAUROJI NAGAR, NEW DELHI-110029
01148311111
8130074912 (Number Shared by Promoter in Public)
secretarial@alphacorp.in
https://alphacorp.in
XXXX259Q
U45201PB2003PLU045680
 
 


 
 


 
 


 
 


 
 


 
 


 
 







ALPHA JASMINE ENCLAVE
VILLAGE-TIKRI, SECTOR-29
KARNAL
KARNAL
9996003883 (Number Shared by Promoter in Public)
avi.r@alphacorp.in
AVI RANA
9996003883 (Number Shared by Promoter in Public)
avi.r@alphacorp.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12273206-02-2026129120HDFC BANK LIMITEDHRERA Panchkula







6.38125 (Acre)
Plotted Development
100
6.38125 (Acre)
222 OF 2025 DATED 14/11/2025
Yes







3151.78 Lakhs
1914.98 Lakhs
0.00 Lakhs
949.67 Lakhs
287.13 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 15207.1170
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.00
3CONSTRUCTION OF ROADS 5870.2146
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 2016.500
6GREEN BELTS 0.00
7VEHICLE PARKINGS 0.00
8ELECTRICITY SUB-STATION 0.00
9CLUB HOUSE 0.00
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 2586.0000
12ANY OTHER 144.1300
Total25823.9616




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)No
WATER SUPPLYHARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)No
ELECTRICITYHARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)No
SEWAGE DISPOSALHARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)No
STORM WATER DRAINAGEHARYANA SHAHARI VIKAS PRADHIKARAN (HSVP)No




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS109.73YET TO BE PREPARED
2WATER SUPPLY SYSTEM111.65YET TO BE PREPARED
3STORM WATER DRAINAGE47.21YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM129.24YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL50.54YET TO BE PREPARED
6STREET LIGHTING26.77YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS4.50YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MAINTENANCE CHARGES136.72YET TO BE PREPARED
16HORTICULTURE8.07YET TO BE PREPARED
17OTHER INFRASTRUCTURES STP UGT RECHARGE PITS ETC169.75YET TO BE PREPARED


14-11-2025 (date)
NA (date)
01-04-2026
13-11-2032
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 110.2950 12
2 120.9160 1
3 134.2000 1
4 88.2000 1
5 115.8600 1
6 112.5400 1
7 149.9400 5
8 149.9400 5
9 112.0650 5
10 103.6950 1
11 120.4500 1
12 109.0005 6
13 105.8300 1
14 109.0050 7
15 149.9400 1
16 149.3200 1
17 149.2500 1
18 139.6000 1
19 96.1500 1
20 85.4000 4
21 125.4560 8
22 105.1750 2
23 133.8000 1
24 77.9500 1
25 105.1750 2
26 83.6500 1
27 105.1750 1
28 124.3200 1
29 149.3500 1
30 149.4500 1
31 149.5500 1
32 149.6500 1
33 149.7500 1
34 149.1500 1
35 104.0500 1
36 98.8500 1
37 118.8500 1
38 120.4000 1
39 140.6500 1
40 122.7000 1
41 137.6000 1
42 136.5500 1
43 117.7500 1
44 118.0000 1
45 126.9500 1
46 127.6500 1
47 128.3000 1
48 129.0000 1
49 125.6500 1
50 130.4500 1
51 131.2000 1
52 131.8500 1
53 131.5000 1
54 129.7500 1
55 127.9500 1
56 126.2000 1
57 124.4500 1
58 122.6500 1
59 120.8500 1
60 119.1000 1
61 117.3000 1
62 115.5500 1
63 107.7000 1
64 83.4000 1
65 142.6500 1
66 143.9000 1
67 145.1500 1
68 146.4000 1
69 147.6500 1
70 148.9500 1
71 150.0000 1
72 141.0000 1
73 87.8500 1
Total119


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots81.64

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots00.3065.910

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0065.910

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0065.910

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots3.491.503.493.49

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System5.585.585.585.58
Sewerage treatment & garbage disposal2.532.532.532.53
Electricity Supply System0000
Storm Water Drainage2.362.362.362.36
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other7.757.757.757.75
Horticulture0000
Maintenance Charges6.846.846.846.84
Street Lighting0000
Other Infrastructures STP UGT Recharge Pits etc000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System11.1711.1711.1711.17
Sewerage treatment & garbage disposal5.055.055.055.05
Electricity Supply System0000
Storm Water Drainage4.724.724.724.72
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other7.757.757.757.75
Other Infrastructures STP UGT Recharge Pits etc16.9816.9816.9816.98
Horticulture0000
Maintenance Charges6.846.846.846.84
Street Lighting0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System5.585.585.585.58
Sewerage treatment & garbage disposal2.532.532.532.53
Electricity Supply System6.49000
Storm Water Drainage2.362.362.362.36
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other7.757.757.757.75
Horticulture0.81000.81
Other Infrastructures STP UGT Recharge Pits etc16.9816.9816.9816.98
Street Lighting0000
Maintenance Charges6.846.846.846.84

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.465.495.4910.97
Water Supply System5.585.585.585.58
Sewerage treatment & garbage disposal2.532.532.532.53
Electricity Supply System12.976.4912.9712.97
Storm Water Drainage2.362.362.362.36
Parks and Playgrounds0.45000.45
Clubhouse/community centres0000
Shopping area0000
Other7.757.757.757.75
Other Infrastructures STP UGT Recharge Pits etc016.9816.980
Street Lighting2.68002.68
Maintenance Charges6.846.846.846.84
Horticulture0.810.810.810.81

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements16.4621.9521.9510.97
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System19.4619.4619.4619.46
Storm Water Drainage0000
Parks and Playgrounds0.681.130.900.90
Clubhouse/community centres0000
Shopping area0000
Other7.757.757.757.75
Other Infrastructures STP UGT Recharge Pits etc0000
Horticulture0.810.810.810.81
Maintenance Charges6.846.846.846.84
Street Lighting5.354.015.356.69












Yes
No
ICICI BANK LIMITED, SCO 6, HSIIDC, INDUSTRIAL AREA, SECTOR 3, GT ROAD, KARNAL, HARYANA 132001
248005001710
ICIC0002480
132229105
002480
Santosh Agarwal 602, 6th Floor, Tower-J, World Trade Centre, Nauroji Nagar, New Delhi-110029
Uploaded











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE FROM DTCP-LICENSE NO. 222 OF 2025ALREADY BEEN OBTAINED14-11-2025
II. FOREST NOC FROM FOREST DEPARTMENTALREADY BEEN OBTAINED13-11-2025
III. POWER LOAD ASSURANCEALREADY BEEN OBTAINED30-09-2025
IV. CTE (CONSENT TO ESTABLISH)APPLIED FOR BUT YET TO RECEIVE30-01-2026
V. APPROVAL OF SERVICE PLAN ESTIMATEYET TO FILE FOR APPROVALNA








Yes


Yes


Added in Draft of Agreement.







ALPHA PLAZA ANNEX 2
4.232
0
59
0
51
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2597.0702323.66
Cost of the apartments000
Cost of the infrastructure1362.5001297.70
Others costs1234.5701025.96


2978.10 Lakhs
157.58 Lakhs
0 Lakhs
0 Lakhs
No
21-03-2027
31-12-2025




ALPHACORP HANU ENCLAVE
5.087
0
104
0
79
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
927.460572.66
Cost of the apartments000
Cost of the infrastructure757.060391.80
Others costs170.40180.86180.86


2500.00 Lakhs
80.16 Lakhs
1816.15 Lakhs
1764.26 Lakhs
No
27-12-2027
03-07-2025




ALPHA PLAZA ANNEX 1
4.286
0
90
0
78
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2627.1502224.30
Cost of the apartments000
Cost of the infrastructure1377.0201286.70
Others costs1250.130937.60


2613.10 Lakhs
121.48 Lakhs
1530.18 Lakhs
1486.46 Lakhs
No
21-03-2027
31-12-2025




ALPHA PLAZA
4.105
0
90
0
76
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2383.4702366.25
Cost of the apartments000
Cost of the infrastructure1357.7901340.57
Others costs1025.6801025.68


3852.18 Lakhs
145.69 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2026
03-07-2025




AVENUE 29
10.282
0
224
0
224
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1956.8601930.92
Cost of the apartments000
Cost of the infrastructure1597.2401571.30
Others costs359.620359.62


4597.55 Lakhs
265.02 Lakhs
0 Lakhs
0 Lakhs
No
11-03-2026
08-05-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNOT APPLICABLE
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSNOT APPLICABLE
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGENOT APPLICABLE
12LIFT DETAILSNOT APPLICABLE
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSNOT APPLICABLE
14DOORSNOT APPLICABLE
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSNOT APPLICABLE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE
20INTERNAL FINISHINGNOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 06-02-2026 View Document
2 DEMARCATION PLAN 06-02-2026 View Document
3 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 06-02-2026 View Document
4 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 06-02-2026 View Document
5 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 06-02-2026 View Document
6 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 09-02-2026 View Document
7 ZONING PLAN 06-02-2026 View Document
8 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 06-02-2026 View Document
9 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 06-02-2026 View Document
10 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 06-02-2026 View Document
11 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 06-02-2026 View Document
12 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 08-02-2026 View Document