HRERA GurugramTemp Project Id : RERA-GRG-PROJ-163-2019
Submission Date : 13-02-2019 04:27:57 AM
Applicant Type : Company
Project Type: NEW




GODREJ PROPERTIES LTD.
GODREJ ONE,5TH FLOOR, PIROJSHANAGAR, EASTERN EXPRESSWAY HIGHWAY,VIKHROLI, MUMBAI-400079
02261698500
9999840950 (Number Shared by Promoter in Public)
vidush.arya@godrejproperties.com
http://godrejproperties.com
XXXX995M
L74120MH1985PLC035308
 
 


 
 


 
 


 
 


 
 


 
 







GODREJ HABITAT
SECTOR-3, GURUGRAM
GURGAON
GURUGRAM
01244956150
9999840950 (Number Shared by Promoter in Public)
Sector3gpl@godrejproperties.com
VIDUSH ARYA
01244956150
9999840950 (Number Shared by Promoter in Public)
Sector3gpl@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
189109-01-20191023297HDFC BANKHRERA Gurugram
289009-01-2019556140HDFC BANKHRERA Gurugram
396815-02-2019237HDFC BANKHRERA Gurugram







7.46875 (Acre)
1.84
1.84
7.46875 (Acre)
18 of 2018
Yes







42400 Lakhs
10000 Lakhs
18300 Lakhs
2500 Lakhs
11500 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3649.02
3CONSTRUCTION OF ROADS6661.32
4PAVEMENTS3137.78
5PARKS AND PLAYGROUNDS8160.75
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE846.02
10SEWAGE AND SOLID WASTE TREATMENT FACILITY100
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES3022.49
12ANY OTHER0
13AREA FOR OPEN CARPARKS3262.38
14AREA FOR MAINTENANCE48.29
15AREA FOR COMMERCIAL150.86
16OPEN AREA1286
Total30324.91




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYHUDANo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS72.54YET TO BE PREPARED
2WATER SUPPLY SYSTEM14.3YET TO BE PREPARED
3STORM WATER DRAINAGE37.60YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM239.66YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL55.94YET TO BE PREPARED
6STREET LIGHTING57.2YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING150.09YET TO BE PREPARED
8PLAYGROUNDS AND PARKS25YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE643.21YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM28YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


05-03-2018 (date)
25-02-2019 (date)
31-10-2019
31-03-2024
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings43015.13844
Apartment/Shops/Other Buildings73.350
Apartment/Shops/Other Buildings1251.88681





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6254.82
Shops00
Plots00

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments600.86754.26917.341019.27
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1019.271019.271019.271090.62
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1121.21172.161172.161172.16
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1223.121223.121325.051224.08
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1019.27
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2017
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.0
Water Supply System0.2
Sewerage treatment & garbage disposal0.8
Electricity Supply System3.3
Storm Water Drainage0.5
Parks and Playgrounds0.3
Clubhouse/community centres0
Shopping area0
Other19.9

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2.43.03.64.0
Water Supply System0.50.60.70.8
Sewerage treatment & garbage disposal1.82.32.83.1
Electricity Supply System7.89.912.013.3
Storm Water Drainage1.51.51.92.1
Parks and Playgrounds0.81.01.21.4
Clubhouse/community centres00011.5
Shopping area0000
Other46.958.971.679.6

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.04.04.04.3
Water Supply System0.80.80.80.8
Sewerage treatment & garbage disposal3.13.13.13.3
Electricity Supply System13.313.313.314.2
Storm Water Drainage2.12.12.12.2
Parks and Playgrounds1.41.41.41.5
Clubhouse/community centres27.134.041.449.2
Shopping area0000
Other79.679.679.685.2

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.44.64.64.6
Water Supply System0.90.90.90.9
Sewerage treatment & garbage disposal3.43.63.63.6
Electricity Supply System14.615.315.315.3
Storm Water Drainage2.32.42.42.4
Parks and Playgrounds1.51.61.61.6
Clubhouse/community centres50.552.852.852.8
Shopping area0000
Other87.691.591.591.5

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.84.85.24.8
Water Supply System1.01.01.01.0
Sewerage treatment & garbage disposal3.73.74.03.7
Electricity Supply System16.016.017.316
Storm Water Drainage2.52.52.72.5
Parks and Playgrounds1.71.71.81.7
Clubhouse/community centres55.155.159.755.1
Shopping area0000
Other95.595.5103.595.6

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.0
Water Supply System0.8
Sewerage treatment & garbage disposal3.1
Electricity Supply System13.3
Storm Water Drainage2.1
Parks and Playgrounds1.4
Clubhouse/community centres45.9
Shopping area0
Other79.6












Yes
No
HDFC LTD. SPLENDOR TRADE TOWER , GOLF COURSE EXT. ROAD , SEC-65 , GURGAON – 122101
50200035566454
HDFC0003676
110240366
3676
Nitesh Katariya, 67/73, Heera Path, Near Dhanvantri Hospital, Mansarovar, Jaipur
Attached











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. HUDA CONSTRUCTION WATER NOC ALREADY BEEN OBTAINED30-10-2018
II. ELECTRICAL LOAD AVAILABILITY ALREADY BEEN OBTAINED15-10-2018
III. AIRPORT HEIGHT CLEARANCE NOC ALREADY BEEN OBTAINED22-10-2018
IV. LICENSEALREADY BEEN OBTAINED25-02-2018
V. ENVIRONMENTAL CLEARANCE ALREADY BEEN OBTAINED07-02-2019
VI. FOREST NOC ALREADY BEEN OBTAINED26-07-2018
VII. TREE CUTTING PERMISSION APPLIED FOR BUT YET TO RECEIVE23-10-2018
VIII. CONSENT TO ESTABLISH APPLIED FOR BUT YET TO RECEIVE12-02-2019
IX. CONSENT TO OPERATE NOCYET TO FILE FOR APPROVALNA
X. DEED OF DECLARATIONYET TO FILE FOR APPROVALNA
XI. EXECUTION OF SALE DEED YET TO FILE FOR APPROVALNA
XII. MINING PERMISSION YET TO FILE FOR APPROVAL01-09-2019
XIII. FIRE SCHEME APPROVAL YET TO FILE FOR APPROVAL28-02-2019
XIV. SERVICES ESTIMATES AND PLANS YET TO FILE FOR APPROVAL28-02-2019
XV. OCCUPATION PERMISSION INCLUDING FIRE NOC, HSVP INTERNAL AND EXTERNAL SERVICES NOC, LIFT NOC, CHIEF ELECTRICAL ENGINEER NOC AND ANY OTHER REQUIRED APPROVALYET TO FILE FOR APPROVALNA
XVI. GMDA/ HUDA/ MCG SERVICES CONNECTION PERMISSIONYET TO FILE FOR APPROVALNA
XVII. ELECTRICAL LOAD CONNECTION/ ENERGIZATION YET TO FILE FOR APPROVALNA
XVIII. HSD STORAGE NOCYET TO FILE FOR APPROVALNA








Yes


Yes


1. Total Price shall be inclusive of GST 2. The Developer shall offer possession of the units falling in Project on or before March 31, 2024 (“Completion Time Period”).













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE OR EQV. IN LIVING/DINING, WOODEN FLOORING OR EQV. IN BEDROOMS, ANTI-SKID TILES OR EQV. IN TOILETS, KITCHEN, BALCONY & UTILITY
2WALL FINISHING DETAILSACRYLIC EMULSION OR EQV. IN INTENAL WALLS, OIL BOUND DISTEMPER OR EQV. IN CEILING, WEATHER PROOF OR EQV. IN EXTERNAL
3KITCHEN DETAILSGRANITE COUNTER WITH SINK AND CP FITTINGS
4BATHROOM FITTINGSYES CP/ SANITARY
5WOOD WORK ETCYES
6DOORS AND WINDOS FRAMESTEAK FRAME IN MAIN DOOR, ALUMINIUM FRAME WITH GLASS FOR WINDOWS & SLIDING DOOR WINDOWS, RED MERANDI IN INTERNAL DOORS
7GLASS WORKYES, WINDOWS
8ELECTRIC FITTINGSONLY SWITCHES
9CONDUCTING AND WIRING DETAILSYES
10CUPBOARD DETAILSNO WARDROBE
11WATER STORAGEUNDERGROUND WATER TANK
12LIFT DETAILSYES
13EXTERNAL GLAZINGSYES - WINDOWS
13.1WINDOWS/GLAZINGSALUMINIUM
14DOORSYES
14.1MAIN DOORSTEAK WOOD FRAME WITH VENEER SHUTTER
14.2INTERNAL DOORSRED MERANDI WITH LAMINATE SHUTTER & SKIN DOOR IN TOILETS
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSONLY SWITCHES
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEWEATHER PROOF OR EQUIVALENT
20INTERNAL FINISHINGACRYLIC EMULSION OR EQV.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE OR EQV.
1 . 2 WALLSACRYLIC EMULSION OR EQV.
1 . 3 CEILINGOIL BOUND DISTEMPER OR EQV.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING OR EQV.
2 . 2 WALLSACRYLIC EMULSION OR EQV.
2 . 3 CEILINGOIL BOUND DISTEMPER OR EQV.
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILE OR EQV.
3 . 2 WALLSACRYLIC EMULSION OR EQV.
3 . 3 CEILINGGRID CEILING
3 . 4 COUNTERSGRANITE OR EQV.
3 . 5 SANITARY WARE/CP FITTINGSWASHBASIN AND CP FITTINGS
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING OR EQV.
4 . 2 WALLSACRYLIC EMULSION OR EQV.
4 . 3 CEILINGOIL BOUND DISTEMPER OR EQV.
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILE OR EQV.
5 . 2 WALLSCERAMIC TILE DADO OR EQV.
5 . 3 CEILINGGRID CEILING OR EQUIVALENT
5 . 4 COUNTERSGRANITE OR EQV.
5 . 5 SANITARY WARE/CP FITTINGSSINK AND CP FITTINGS
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORANTI SKID CERAMIC TILE OR EQV.
6 . 2 WALLSCERAMIC TITLE DADO
6 . 3 CEILINGOIL BOUND DISTEMPER OR EQV.
6 . 4 COUNTERSGRANITE OR EQUIVALENT.
6 . 5 FIXTURESSINK
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI SKID CERAMIC TILE OR EQV.
7 . 2 WALLS & CEILINGACRYLIC EMULSION OR EQV. IN INTENAL WALLS, OIL BOUND DISTEMPER OR EQV. IN CEILING
7 . 3 TOILETANTI SKID CERAMIC TILE OR EQV.
7 . 4 BALCONYANTI SKID CERAMIC TILE OR EQV.
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILE OR EQV.
8 . 2 WALLS & CEILINGACRYLIC EMULSION OR EQV. IN INTERNAL WALLS AND OIL BOUND DISTEMPER OR EQV. IN CEILING
8 . 3 RAILINGSENAMEL PAINT
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DETAIL OF CONVERED AREA ACHIEVED FAR28-02-2019 ------
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN13-02-2019 View Document
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT28-02-2019 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT13-02-2019 View Document
5IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN13-02-2019 View Document
6DEMARCATION PLAN13-02-2019 View Document
7DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.13-02-2019 View Document
8DETAIL OF PERMISSIBLE FAR28-02-2019 ------
9COPY OF LICENSE ALONG WITH SCHEDULE OF LAND08-02-2019 View Document
10LAYOUT PLAN28-02-2019 ------
11BUILDING PLAN28-02-2019 ------
12SITE PLAN28-02-2019 ------
13DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD28-02-2019 View Document
14A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS28-02-2019 View Document
15FLOOR PLAN28-02-2019 ------
16ZONING PLAN12-02-2019 View Document
17APARTMENT PLAN28-02-2019 ------
18IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN12-02-2019 View Document
19ELEVATION AND SECTION28-02-2019 ------
20PARKING PLAN28-02-2019 ------
21AGREEMENT FOR SALE GODREJ HABITAT28-02-2019 ------
22ALLOTMENT LETTER SECTOR 3 18021928-02-2019 ------
23APPLICATION FORM SECTOR 3 18021928-02-2019 ------
24CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT28-02-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Extension No. 30 of 2023 dated 11.12.2023 09-01-2024 View Document