HRERA GurugramTemp Project Id : RERA-GRG-PROJ-149-2019
Submission Date : 10-12-2019 02:24:18 AM
Applicant Type : Company
Project Type: ONGOING




JMS BUILDTECH PRIVATE LIMITED
3RD FLOOR.PLOT NO.10,SECTOR-44, GURUGRAM-122001
01244215132
9958000777 (Number Shared by Promoter in Public)
INFO@JMSBUILDTECH.COM
http://jmsbuildtech.com
XXXX305P
U70109HR2013PTC048244
 
 


 
 


 
 


 
 


 
 


 
 







MARINE SQUARE
SECTOR-102, GURUGRAM
GURGAON
GURUGRAM
01244215132
8448981496 (Number Shared by Promoter in Public)
INFO@JMSBUILDTECH.COM
SATYA PRAKASH PATHAK
01244215132
8448284225 (Number Shared by Promoter in Public)
SATYA.PATHAK@JMSBUILDTECH.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
19518-01-2018284000HDFC BANKHRERA Gurugram







2 (Acre)
14163.975
141.29
2 (Acre)
04.01.2018
Yes







8160 Lakhs
0 Lakhs
5860 Lakhs
2140 Lakhs
160 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS4856.22
3CONSTRUCTION OF ROADS2108.76
4PAVEMENTS809.17
5PARKS AND PLAYGROUNDS0
6GREEN BELTS319.56
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total8093.71




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSAS PER BUILDING PLAN APPROVEDYes
WATER SUPPLYOFFICE OF EXECUTIVE ENGINEER, HUDA Yes
ELECTRICITYYET TO AWARDEDNo
SEWAGE DISPOSALYET TO AWARDEDNo
STORM WATER DRAINAGENANo
ENVIRONMENTSTATE ENVIRONMENT IMPACTYes
STPOFFICE OF ADMINSTRATOR, HARYANAYes
FORESTFOREST DEPARTMENT, GOVT. OF HARYANAYes
ARAVALICITY MAGISTRATEYes
BUILDINGCHIEF TOWN PLANNER, HARYANAYes
ZOINING ZONING AUTHORITYYes
POLLUTIONHARYANA STATE POLLUTION CONTROL BOARDYes
MININGDEPARTMENT OF MINES & GEOLOGYYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS40YET TO BE PREPARED
2WATER SUPPLY SYSTEM105YET TO BE PREPARED
3STORM WATER DRAINAGE10YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM1120YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL60YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING590YET TO BE PREPARED
8PLAYGROUNDS AND PARKS125YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM15YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PARKING20YET TO BE PREPARED
16SOLID WASTE COLLECTION AND MANAGEMENT SYSTEM55YET TO BE PREPARED


21-11-2017 (date)
21-11-2017 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type S105903862041






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
SHOPS3860%


01-03-2019
02-02-2023
02-02-2023
01-03-2019
0
02-02-2023


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-03-2019
0
02-02-2023


354
0
0
20
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops461.88
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2413.15
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0
ii. No. of Flats/ Apartments booked386
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter8939.67 LakhsGST EXTRA
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter4486.74 LakhsGST EXTRA
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter4452.93 LakhsGST EXTRA
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter118.16 LakhsGST EXTRA
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)919.40 Lakhs
Apartments1491.69 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.1221.46 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession0 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS400
II. WATER SUPPLY SYSTEM1050
III. STORM WATER DRAINAGE100
IV. ELECTRICITY SUPPLY SYSTEM11200
V. SEWAGE TREATMENT & GARBAGE DISPOSAL600
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM550
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.1250
XIII. COVERED PARKING00
XIV. OPEN PARKING200
XV. GARAGES00
XVI. SECURITY SYSTEM400
XVII. OTHER FACILITIES AS PER PROJECT REPORT5650









Yes
Yes
ICICI BANK
031405004213
ICIC0000314
110229042
000314
Sanjay Aggarwal
NOT APPLICABLE AS THE COMPANY HAS NOT TAKEN ANY LOAN TILL DATE











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
No
No
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED13-02-2018
II. STPALREADY BEEN OBTAINED21-12-2017
III. DRINKING WATER ALREADY BEEN OBTAINED18-12-2017
IV. ARAVALLI ALREADY BEEN OBTAINED04-01-2018
V. FORESTALREADY BEEN OBTAINED11-12-2017
VI. BUILDING PLANALREADY BEEN OBTAINED17-01-2018
VII. LICENSEALREADY BEEN OBTAINED13-08-2014
VIII. MININGALREADY BEEN OBTAINED19-09-2019








Yes


Yes


PROVIDED AS ATTACHMENT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE1. COMMON AREA & CORRIDOR- VITRIFIED TILE & MARBLE 2. STAIR CASE - KOTA STONE MARBLE 3. TOILET - ANTISKID PYRAMID TILE
2WALL FINISHING DETAILS1. COMMON AREA & CORRIDOR- OBD WITH COMBINATION OF MARBLE 2. STAIR CASE - OBD 3. TOILET - OBD WITH COMBINATION OF PYRAMID TILE
3KITCHEN DETAILSNA
4BATHROOM FITTINGSSINGLE LEVER CP FITTING WHITE CHINAWARE
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESUPVC/ALUMINIUM DOOR WINDOW
7GLASS WORKSHOP FRONT- GLASS DOOR
8ELECTRIC FITTINGSMODULAR SWITCHES & SOCKETS LIGHT IN CORRIDOR STAIRCASE, TOILET & EXTERNAL LIGHTING
9CONDUCTING AND WIRING DETAILSCOPPER WIRING IN CONCEALED CONDUIT WITH LIGHT & POWER POINT
10CUPBOARD DETAILSNA
11WATER STORAGEUNDER GROUND WATER TANK
12LIFT DETAILS2 NO'S OF LIFT FOR PASSENGER 1 NO'S OF LIFT FOR FIRE
13EXTERNAL GLAZINGSUPVC/ ALUMINIUM
13.1WINDOWS/GLAZINGSUPVC/ ALUMINIUM
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSSHOP- GLASS DOOR
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSMODULAR SWITCHES & SOCKETS
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT IN COMBINATION WITH MARBLE
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-12-2019 View Document
2DRAFT ALLOTMENT LETTER10-12-2019 ------
3ZONING PLAN09-12-2019 View Document
4A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS10-12-2019 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT10-12-2019 View Document
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN10-12-2019 View Document
7DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-12-2019 View Document
8GIST OF UNIT BUYER AGREEMENT10-12-2019 ------
9DEMARCATION PLAN10-12-2019 View Document
10COPY OF LICENSE ALONG WITH SCHEDULE OF LAND10-12-2019 View Document
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.10-12-2019 View Document
12BBA10-12-2019 ------