SHOP NO 114-115, UPPER GROUND FLOOR, AKD TOWER SECTOR-14, GURUGRAM
7303469090 (Number Shared by Promoter in Public)
buildconriseonic@gmail.com
XXXX253N
U45309HR2022PTC103203
THE RIDGE RESIDENCY BY RAJGRIHAM
SECTOR 25, VILLAGE KHANPUR, SOHNA DISTRICT NUH (HARYANA)
NUH
NUH
7303469090 (Number Shared by Promoter in Public)
buildconriseonic@gmail.com
ANKIT SINGH
7303469090 (Number Shared by Promoter in Public)
buildconriseonic@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
9235
01-08-2025
1541500
IDBI BANK LIMITED
HRERA Panchkula
6.36875 (Acre)
2.37
2.368
6.36875 (Acre)
LICENSE NO. 54 OF 2025 DATED 17-04-2030 (VALID UPTO 16-04-2030)
No
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Address VILLAGE KHANPUR,SECTOR 25, SOHNA DISTRICT NUH, HARYANA
Annexure-B- COLLABORATION AGREEMENT AND POWER OF ATTORNEY EXECUTED BETWEEN THE PARTIES.
YES, THE AGREEMENT I.E. COLLABORATION AGREEMENT AND POWER OF ATTORNEY EXECUTED BEFORE GRANT OF LICENSE.
Yes
AS PER THE COLLABORATION AGREEMENT
No
Yes
Yes
24383.96 Lakhs
2000.22 Lakhs
16646.46 Lakhs
2505.43 Lakhs
3231.85 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
5678.27
3
CONSTRUCTION OF ROADS
5330.99684
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
3913.68
6
GREEN BELTS
0
7
VEHICLE PARKINGS
9026.43
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
379.83
12
ANY OTHER
0
13
COMMERCIAL
1444.21
Total
25773.41684
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVNL
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
269.69
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
447.09
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
275.22
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
0.00
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
291.09
AS PER PROJECT REPORT
6
STREET LIGHTING
90.77
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
60.81
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
122.70
AS PER PROJECT REPORT
10
SHOPPING AREA
628.26
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
ELECTRICAL SUB STATION
200.00
AS PER PROJECT REPORT
16
CONSTRUCTION OF CIRCULATION ROAD
50.00
AS PER PROJECT REPORT
17
MTC
69.80
AS PER PROJECT REPORT
NA (date)
27-06-2025 (date)
01-08-2025
31-07-2031
Sr. No
Plot Area(In Square Meter)
Number of plots in the project
1
0
0
Total
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
59.98
27
8
Apartment/Shops/Other Buildings
59.98
32
8
Apartment/Shops/Other Buildings
49.78
32
8
Apartment/Shops/Other Buildings
59.98
416
8
Apartment/Shops/Other Buildings
49.78
416
8
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
Shops
27.32
Plots
0
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
723.76
723.76
Shops
27.32
27.32
27.32
27.32
Plots
0
0
0
0
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
723.76
723.76
Shops
27.32
27.32
27.32
27.32
Plots
0
0
0
0
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
723.76
723.76
Shops
27.32
27.32
27.32
27.32
Plots
0
0
0
0
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
723.76
723.76
Shops
27.32
27.32
27.32
27.32
Plots
0
0
0
0
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
723.76
723.76
Shops
27.32
27.32
0
0
Plots
0
0
0
0
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
723.76
723.76
Shops
0
0
Plots
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
Water Supply System
19.44
Sewerage treatment & garbage disposal
12.66
Electricity Supply System
8.70
Storm Water Drainage
11.97
Parks and Playgrounds
2.64
Clubhouse/community centres
5.33
Shopping area
0
Other
9.16
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
11.73
11.73
Water Supply System
19.44
19.44
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
12.66
12.66
Electricity Supply System
8.70
8.70
8.70
8.70
Storm Water Drainage
11.97
11.97
11.97
11.97
Parks and Playgrounds
2.64
2.64
2.64
2.64
Clubhouse/community centres
5.33
5.33
5.33
5.33
Shopping area
0
0
0
0
Other
9.16
9.16
9.16
9.16
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
11.73
11.73
Water Supply System
19.44
19.44
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
12.66
12.66
Electricity Supply System
8.70
8.70
8.70
8.70
Storm Water Drainage
11.97
11.97
11.97
11.97
Parks and Playgrounds
2.64
2.64
2.64
2.64
Clubhouse/community centres
5.33
5.33
5.33
5.33
Shopping area
0
0
0
0
Other
9.16
9.16
9.16
9.16
Particulars
Year-2028
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
11.73
11.73
Water Supply System
19.44
19.44
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
12.66
12.66
Electricity Supply System
8.70
8.70
8.70
8.70
Storm Water Drainage
11.97
11.97
11.97
11.97
Parks and Playgrounds
2.64
2.64
2.64
2.64
Clubhouse/community centres
5.33
5.33
5.33
5.33
Shopping area
0
0
0
0
Other
9.16
9.16
9.16
9.16
Particulars
Year-2029
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
11.73
11.73
Water Supply System
19.44
19.44
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
12.66
12.66
Electricity Supply System
8.70
8.70
8.70
8.70
Storm Water Drainage
11.97
11.97
11.97
11.97
Parks and Playgrounds
2.64
2.64
2.64
2.64
Clubhouse/community centres
5.33
5.33
5.33
5.33
Shopping area
0
0
0
0
Other
9.16
9.16
9.16
9.16
Particulars
Year-2030
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
11.73
11.73
Water Supply System
19.44
19.44
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
12.66
12.66
Electricity Supply System
8.70
8.70
8.70
8.70
Storm Water Drainage
11.97
11.97
11.97
11.97
Parks and Playgrounds
2.64
2.64
2.64
2.64
Clubhouse/community centres
5.33
5.33
5.33
5.33
Shopping area
0
0
0
0
Other
9.16
9.16
9.16
9.16
Particulars
Year-2031
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.73
11.73
Water Supply System
19.44
19.44
Sewerage treatment & garbage disposal
12.66
12.66
Electricity Supply System
8.70
8.70
Storm Water Drainage
11.97
11.97
Parks and Playgrounds
2.64
2.64
Clubhouse/community centres
5.33
5.33
Shopping area
0
0
Other
9.16
9.16
No
No
IDBI BANK LIMITED, G 12 & 16,OMAXE MALL, SOHNA ROAD,GURGAON, HARYANA
0295102000012306
IBKL0000295
110259035
0295
Raman Grover
5H1 NIT Faridabad Haryana -121001
Yes, Uploaded.
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LC V- LICENSE
ALREADY BEEN OBTAINED
17-04-2025
II. DEMARCATION CUM ZONING PLAN
ALREADY BEEN OBTAINED
17-04-2025
III. FOREST NOC
ALREADY BEEN OBTAINED
08-04-2025
IV. BUILDING PLANS APPROVAL
ALREADY BEEN OBTAINED
27-06-2025
Yes
Yes
THE PROVISIONS OF RERA ACT AND RULES SHALL BE INCORPORATED IN THE DRAFT AGREEMENT.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
KAJARIA OR EQUIVALENT TILES
2
WALL FINISHING DETAILS
OIL BOUND DISTEMPER- ASIAN PAINT OR SIMILAR
3
KITCHEN DETAILS
OIL BOUND DISTEMPER- ASIAN PAINT OR SIMILAR
4
BATHROOM FITTINGS
BASIC STEEL FITTING OR SIMILAR
5
WOOD WORK ETC
HARDWOOD FRAME OR SIMILAR
6
DOORS AND WINDOS FRAMES
AFRICAN SAAL 4" X 2.5" OF BEST QUALITY
7
GLASS WORK
TINTED GLASS OR SIMILAR
8
ELECTRIC FITTINGS
FOR SWITCHES - 1MM, 6AMP- 2.5 MM, 16AMP- 2.5 MM, AC - 4MM, MAIN WIRE - 8MM (KEI WIRES OR SIMILAR AND HAVELS SWTICHES OR SIMILAR)
9
CONDUCTING AND WIRING DETAILS
HAVELLS OR SIMILAR
10
CUPBOARD DETAILS
N/A
11
WATER STORAGE
PVC TANK UGT/ OVERHEAD- STANDARD QUALITY OR SIMILAR
12
LIFT DETAILS
KONE OR SIMILAR
13
EXTERNAL GLAZINGS
EXTERIOR GRADE TEXTURE PAINT
13.1
WINDOWS/GLAZINGS
HARDWOOD FRAME WITH PAINTED/
14
DOORS
HARDWOOD FRAME WITH PAINTED/
14.1
MAIN DOORS
HARDWOOD FRAME WITH PAINTED/
14.2
INTERNAL DOORS
HARDWOOD FRAME WITH PAINTED/
15
AIR CONDITIONING
N/A/
16
ELECTRICAL FITTINGS
FOR SWITCHES - 1MM, 6AMP- 2.5 MM, 16AMP- 2.5 MM, AC - 4MM, MAIN WIRE - 8MM (KEI WIRES OR SIMILAR AND HAVELS SWTICHES OR SIMILAR)