HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1539-2024
Submission Date : 11-09-2024 07:04:09 PM
Applicant Type : Firm
Project Type: NEW


OM ESTATES
OM COMPLEX NEAR TOSHAM CHUNGI, TOSHAM ROAD, NEW MODEL TOWN, HISAR.
9467967515 (Number Shared by Promoter in Public)
kparveen1@gmail.com
0612202100215
AAHFO4792N

















OM ESTATES
VILLAGE HISAR, NH-9, HISAR DELHI BYE PASS ROAD
HISAR
HISAR
9467967515 (Number Shared by Promoter in Public)
kparveen1@gmail.com
PARVEEN KUMAR
9467967515 (Number Shared by Promoter in Public)
kparveen1@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11385909-09-2024790500AXIS BANK LIMITEDHRERA Panchkula







19.725 (Acre)
1.00 FOR PLOTTED AND 1.5 FOR COMMERCIAL
1.00
19.725 (Acre)
LICENSE NO. 117 OF 2024 DATED 14.08.2024 (VALID UPTO 13.08.2029)
Yes







7423.61 Lakhs
3814.99 Lakhs
0 Lakhs
1950.000 Lakhs
1658.62 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD11.462
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS6.286
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.5645
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.4575
12ANY OTHER0
13COMMERCIALQ0.9555
Total19.7255




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS468.00AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM351.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE292.50AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM390.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL253.50AS PER PROJECT REPORT
6STREET LIGHTING78.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS117.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


14-08-2024 (date)
NA (date)
15-09-2024
13-08-2029
Plot Area(In Square Meter)Number of plots in the project
529.684
539.982
303.287
337.611
528.493
529.601
339.167
328.601
394.954
397.641
228.051
364.3914
295.945
354.181
485.704
503.091
325.0036
333.064
63.317
128.079
144.251
148.434
143.0411
134.701
128.964
133.271
129.9316
134.274
149.979
146.3517
144.131


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.40
Water Supply System17.5517.55
Sewerage treatment & garbage disposal12.6812.68
Electricity Supply System19.5019.50
Storm Water Drainage14.6314.63
Parks and Playgrounds5.855.85
Clubhouse/community centres00
Shopping area00
Other3.903.90

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.4023.4023.40
Water Supply System17.5517.5517.5517.55
Sewerage treatment & garbage disposal12.6812.6812.6812.68
Electricity Supply System19.5019.5019.5019.50
Storm Water Drainage14.6314.6314.6314.63
Parks and Playgrounds5.855.855.855.85
Clubhouse/community centres0000
Shopping area0000
Other3.903.903.903.90

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.4023.4023.40
Water Supply System17.5517.5517.5517.55
Sewerage treatment & garbage disposal12.6812.6812.6812.68
Electricity Supply System19.5019.5019.5019.50
Storm Water Drainage14.6314.6314.6314.63
Parks and Playgrounds5.855.855.855.85
Clubhouse/community centres0000
Shopping area0000
Other3.903.903.903.90

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.4023.4023.40
Water Supply System17.5517.5517.5517.55
Sewerage treatment & garbage disposal12.6812.6812.6812.68
Electricity Supply System19.5019.5019.5019.50
Storm Water Drainage14.6314.6314.6314.63
Parks and Playgrounds5.855.855.855.85
Clubhouse/community centres0000
Shopping area0000
Other3.903.903.903.90

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.4023.4023.40
Water Supply System17.5517.5517.5517.55
Sewerage treatment & garbage disposal12.6812.6812.6812.68
Electricity Supply System19.5019.5019.5019.50
Storm Water Drainage14.6314.6314.6314.63
Parks and Playgrounds5.855.855.855.85
Clubhouse/community centres0000
Shopping area0000
Other3.903.903.903.90

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.4023.400
Water Supply System17.5517.550
Sewerage treatment & garbage disposal12.6812.680
Electricity Supply System19.5019.500
Storm Water Drainage14.6314.630
Parks and Playgrounds5.855.850
Clubhouse/community centres000
Shopping area000
Other3.903.900












Yes
No
AXIS BANK LTD SECTOR 13 HISAR
923020056991790
UTIB0002030
125211053
002030
Sh. Parveen Kumar R/o Plot No. 1-2 Om Complex New Model Town Tosham Road Hisar
Uploaded in upload Section











Yes
Yes
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 117 OF 2024ALREADY BEEN OBTAINED14-08-2024
II. LAYOUT PLAN ALREADY BEEN OBTAINED14-08-2024
III. DEMARCATION-CUM-ZONING PLAN ALREADY BEEN OBTAINED11-09-2024








Yes


Yes


The provisions of RERA Act and Rules have been incorporated in the draft agreement.







OM ESTATES
28.83
0
407
0
312
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
3547.7203547.72
Cost of the apartments000
Cost of the infrastructure2632.0002632.00
Others costs917.720917.72


3456.00 Lakhs
216.00 Lakhs
0.00 Lakhs
0.00 Lakhs
No
16-12-2026
16-12-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED COLONY
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED COLONY
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED COLONY
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED COLONY
7GLASS WORKNOT APPLICABLE BEING PLOTTED COLONY
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED COLONY
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED COLONY
11WATER STORAGENOT APPLICABLE BEING PLOTTED COLONY
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED COLONY
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED COLONY
14DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED COLONY
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED COLONY
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED COLONY
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED COLONY
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED COLONY
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED COLONY
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED COLONY
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED COLONY
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED COLONY
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED COLONY
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED COLONY
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED COLONY
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED COLONY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED COLONY
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED COLONY
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED COLONY
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED COLONY
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED COLONY
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED COLONY












Sr. No.Document DescriptionDate of Document UploadView Document
1NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT11-09-2024 View Document
2DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.11-09-2024 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN11-09-2024 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND11-09-2024 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN11-09-2024 View Document