HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1690-2024
Submission Date : 09-08-2024 02:15:20 PM
Applicant Type : Company
Project Type: NEW




DLF LIMITED
3RD FLOOR, SHOPPING MALL, ARJUN MARG, DLF CITY, PHASE I GURUGRAM 12202
0124769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in/homes/superluxury/LUX5
XXXX494N
L70101HR1963PLC2484
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







THE DAHLIAS
R16, DLF 5, SECTOR 54 GURUGRAM
WAZIRABAD ST
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
MR NIMIT PORWAL
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152393230-07-202411764500ICICI BANKHRERA Gurugram







16.489 (Acre)
1.75
1.75
16.489 (Acre)
License Approve by DTCP vide License No. 129 of 1995, 131 of 1995, 38 of 1996, 39 of 1996, 40 of 1996, 52 of 1996, 53 of 1996, 57 of 1996, 02 of 2002, 04 of 2002, 06 of 2002
Yes







618651.83 Lakhs
5309.16 Lakhs
513606.96 Lakhs
37579.8 Lakhs
62155.91 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 3.23
3CONSTRUCTION OF ROADS 10.07
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 2.47
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0.43
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0.28
Total16.48




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDAYes
WATER SUPPLYGMDAYes
ELECTRICITYDHVBNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS13836.63SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM1174.0SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE166.64SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM357.28SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL136.34SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING233.95SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS4272.06SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER1732.52SUBMITTED TO TOWN & COUNTRY PLANNING


12-09-2024 (date)
19-09-2024 (date)
20-04-2024
31-12-2031
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings1109.4219
Apartment/Shops/Other Buildings1108.7319
Apartment/Shops/Other Buildings1086.8219
Apartment/Shops/Other Buildings1079.1819
Apartment/Shops/Other Buildings901.9219
Apartment/Shops/Other Buildings900.0259
Apartment/Shops/Other Buildings850.8239
Apartment/Shops/Other Buildings835.2719
Apartment/Shops/Other Buildings820.9819
Apartment/Shops/Other Buildings699.06259
Apartment/Shops/Other Buildings698.21259
Apartment/Shops/Other Buildings686.24259
Apartment/Shops/Other Buildings681.77259
Apartment/Shops/Other Buildings655.8229
Apartment/Shops/Other Buildings654.3329
Apartment/Shops/Other Buildings640.7729
Apartment/Shops/Other Buildings626.0229
Apartment/Shops/Other Buildings613.79259
Apartment/Shops/Other Buildings604.5629
Apartment/Shops/Other Buildings579.101259
Apartment/Shops/Other Buildings561.10109
Apartment/Shops/Other Buildings543.02759
Apartment/Shops/Other Buildings531.1469
Apartment/Shops/Other Buildings530.64259
Apartment/Shops/Other Buildings34397.0719
Apartment/Shops/Other Buildings523.04259
Apartment/Shops/Other Buildings522.2029
Apartment/Shops/Other Buildings506.0329





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments11050.01
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments685.50
Shops0
Plots0

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1527.593091.8317438.0412145.24
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments33434.5647958.6963846.7534798.50
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments63807.9641866.5844695.8942947.11
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments43236.2743520.7823243.9810287.48
Shops0000
Plots0000

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments807.92720.094331.10984.31
Shops0000
Plots0000

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2129.265003.073027.373546.90
Shops0000
Plots0000

ParticularsYear-2031
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3546.903546.903546.900
Shops0000
Plots0000

ParticularsYear-2032
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other958.0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements00
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Earth Work03121.40

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Earth Work780.352341.053121.403121.40

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Earth Work3121.40

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
UGT038.80193.98323.30

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
UGT452.62284.50
Rain Water Harvesting0
Sewerage System0
Street Lighting0

ParticularsYear-2029
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements883.941944.682416.123241.13
Water Supply System75.00165.00205.00275.00
Sewerage treatment & garbage disposal33.2273.0990.80121.81
Electricity Supply System22.8250.2162.3983.69
Storm Water Drainage10.6523.4229.1039.03
Parks and Playgrounds272.92600.42745.981000.70
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting7.6016.7220.7827.87
Sewerage System0000
Street Lighting14.9532.8840.8554.80

ParticularsYear-2030
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements2239.331473.241178.59459.65
Water Supply System190.00125.00100.0039.00
Sewerage treatment & garbage disposal84.1655.3744.2917.28
Electricity Supply System57.8238.0430.4311.87
Storm Water Drainage26.9717.7414.195.54
Parks and Playgrounds691.39454.86363.89141.92
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting19.2612.6710.143.95
Street Lighting37.8624.9119.937.77
Sewerage System0000












Yes
No
ICICI BANK LTD.,QUTUB PLAZA, DLF PHASE-1, GURGAON-122002
017705014812
ICIC000017
110229030
00177
Pankaj Kumar, Puneet Rukheja, Ashok Nanda, Sandhy Singla, Gaurav Aroa, Amit Bansal, Pankaj Jain
Attached











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE ALREADY BEEN OBTAINED01-08-2024
II. AIRPORT AUTHORITYALREADY BEEN OBTAINED26-12-2023
III. ARAVALI NOCALREADY BEEN OBTAINED15-04-2024
IV. FOREST NOCALREADY BEEN OBTAINED18-03-2024








Yes


Yes


As per RER Act 2016







INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
1.096
52
13
52
13
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
61336328.004871.00
Cost of the apartments453553203872.00
Cost of the infrastructure000
Others costs4221008.00999.00


10362 Lakhs
760 Lakhs
0 Lakhs
5599 Lakhs
No
19-11-2024
19-11-2024




INDEPENDENT FLOORS AT DLFGARDENCITY SECTOR 91/92
2.246
124
31
124
31
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
12800121598947
Cost of the apartments10000115158303
Cost of the infrastructure000
Others costs2800644643


18376 Lakhs
6425 Lakhs
0 Lakhs
11012.00 Lakhs
No
31-03-2025
31-03-2025




GARDENCITY ARCADE, GURGAON
1.42
99
1
99
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
630854463839
Cost of the apartments416246723368
Cost of the infrastructure000
Others costs2146774470


5165 Lakhs
4140 Lakhs
0 Lakhs
5378.00 Lakhs
No
29-04-2025
29-04-2025




DLF GARDENCITY ENCLAVE, GURGAON
26.91875
0
367
0
119
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1199951972283
Cost of the apartments000
Cost of the infrastructure47383241817
Others costs7261785295


5909 Lakhs
5701 Lakhs
0 Lakhs
2589 Lakhs
No
28-03-2025
28-03-2025




INDEPENDENT FLOORS AT DLFGARDENCITY ENCLAVE, GURGAON
3.5698
388
97
388
97
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2346829165.0011985.00
Cost of the apartments1834526854.0010457.00
Cost of the infrastructure136700
Others costs30451462678.00


17320 Lakhs
36076 Lakhs
0 Lakhs
12762 Lakhs
No
19-08-2027
19-08-2027




DLF GARDENCITY ENCLAVE PH2
5.0105
544
136
536
134
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
495683940811295
Cost of the apartments30890365949174
Cost of the infrastructure300200
Others costs67141622929


25758 Lakhs
52187 Lakhs
0 Lakhs
12285.00 Lakhs
No
30-10-2028
30-10-2028




SUMMIT PLAZA SECTOR-54, GURUGRAM,HARYANA
2.65
311
1
311
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
249563410715665
Cost of the apartments185303123413585
Cost of the infrastructure000
Others costs642628732080


4093 Lakhs
6991 Lakhs
0 Lakhs
16191 Lakhs
No
30-06-2026
30-06-2026




THE GROVE DLF 5, SECTOR-54,GURU
5.3073
292
73
292
73
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
493555392027743
Cost of the apartments385325204826293
Cost of the infrastructure000
Others costs881418721450


107346 Lakhs
86699 Lakhs
0 Lakhs
42592.00 Lakhs
No
31-12-2025
31-12-2025




DLF PRIVANA SOUTH, SECTOR-77, GURGAON
25.148
1113
0
1113
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
34155037560216859
Cost of the apartments3197293433496698
Cost of the infrastructure000
Others costs218213225310161


182385 Lakhs
552872 Lakhs
0 Lakhs
25082 Lakhs
No
30-06-2031
30-06-2031




DLF PRIVANA WEST, SECTOR-77, GURGAON
12.572
795
0
795
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2793002793009346
Cost of the apartments2520892520892088
Cost of the infrastructure000
Others costs27211272117258


58858 Lakhs
507573 Lakhs
0 Lakhs
11474 Lakhs
No
31-12-2031
31-12-2031










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSECONCRETE (M30-M90 AS PER IS-456 IS2185)
2WALL FINISHING DETAILSBLOCK WORK
3KITCHEN DETAILSNA
4BATHROOM FITTINGSCP FITTING, WASH BASIN, WC
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESMS/UPVC/AL/WOOD/COMPOSITE MATERIAL
7GLASS WORKCLEAR/ TINTED/ FROSTED/ COATED
8ELECTRIC FITTINGSLIGHT FIXTURE FOR BALCONIES ONLY
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNONE
11WATER STORAGEOHT & UGT TANKS
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSUPVC/ ALUMINIUM
13.1WINDOWS/GLAZINGSSAME AS POINT#13
14DOORSMS FIRE RATED DOOR
14.1MAIN DOORSMS DOOR
14.2INTERNAL DOORSHARDWOOD /WOODEN FLUSH DOOR/ MS
15AIR CONDITIONINGOUTDOOR UNIT OF VARIABLE REFRIGERANT FLOW (VRF)
16ELECTRICAL FITTINGSSAME AS POINT#8
17CNG PIPE LINEGAS PIPELINE PROVISION ONLY
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION ONLY
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL GRADED PAINT
20INTERNAL FINISHINGBLOCK WORK
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORCONCRETE
1 . 2 WALLSBLOCK WORK
1 . 3 CEILINGCONCRETE SLAB
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORCONCRETE
2 . 2 WALLSBLOCKWORK/BRICKWORK
2 . 3 CEILINGCONCRETE SLAB
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCONCRETE
3 . 2 WALLS BLOCKWORK
3 . 3 CEILINGCONCRETE SLAB
3 . 4 COUNTERSNONE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORCONCRETE
4 . 2 WALLSBLOCKWORK
4 . 3 CEILINGCONCRETE SLAB
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCONCRETE
5 . 2 WALLSBLOCKWORK
5 . 3 CEILINGCONCRETE SLAB
5 . 4 COUNTERSNONE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, WC
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORCONCRETE
6 . 2 WALLSBLOCKWORK
6 . 3 CEILINGCONCRETE SLAB
6 . 4 COUNTERSNA
6 . 5 FIXTURESWATER POINT WITH TAP
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCONCRETE
7 . 2 WALLS & CEILINGBLOCKWORK
7 . 3 TOILETCP FITTINGS, WASH BASIN, WC
7 . 4 BALCONYCONCRETE
8 . SIT-OUTS
8 . 1 FLOORCONCRETE
8 . 2 WALLS & CEILINGBLOCKWORK
8 . 3 RAILINGSMS/SS/AL/GLASS
8 . 4 FIXTURESCEILING LED LIGHTS












Sr. No.Document DescriptionDate of Document UploadView Document
1 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 08-08-2024 View Document
2 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 08-08-2024 View Document
3 DEMARCATION PLAN 08-08-2024 View Document
4 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 08-08-2024 View Document
5 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 08-08-2024 View Document
6 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 08-08-2024 View Document
7 BS-04 FLOOR PLAN-BASEMENT 4_4_11ZON 01-10-2024 ------
8 EL-17_3_11ZON 01-10-2024 ------
9 SC-04_12_11ZON 01-10-2024 ------
10 EL-03_3_11ZON 01-10-2024 ------
11 EL-08_1_11ZON 01-10-2024 ------
12 T2-01_16_11ZON 01-10-2024 ------
13 T9-01_1_11ZON 01-10-2024 ------
14 EL-18_4_11ZON 01-10-2024 ------
15 ZONING PLAN 01-10-2024 View Document
16 T2-04_19_11ZON 01-10-2024 ------
17 T3-04_23_11ZON 01-10-2024 ------
18 SPE 01-10-2024 ------
19 BS-05 AREA DIAGRAM BASEMENT -1_5_11ZON 01-10-2024 ------
20 T9-01B_3_11ZON 01-10-2024 ------
21 EL-15_1_11ZON 01-10-2024 ------
22 T1-01_11_11ZON 01-10-2024 ------
23 T9-01C_4_11ZON 01-10-2024 ------
24 T9-05_1_11ZON 01-10-2024 ------
25 EL-10_3_11ZON 01-10-2024 ------
26 T3-01_20_11ZON 01-10-2024 ------
27 T4-03_26_11ZON 01-10-2024 ------
28 SC-10_11_11ZON 01-10-2024 ------
29 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 01-10-2024 View Document
30 SC-06_14_11ZON 01-10-2024 ------
31 T8-03_41_11ZON 01-10-2024 ------
32 SC-07_8_11ZON 01-10-2024 ------
33 BS-01 FLOOR PLAN-BASEMENT 1_1_11ZON 01-10-2024 ------
34 BS-03 FLOOR PLAN-BASEMENT 3_3_11ZON 01-10-2024 ------
35 T2-02_17_11ZON 01-10-2024 ------
36 T1-04_14_11ZON 01-10-2024 ------
37 DR-902 01-10-2024 ------
38 SC-12_13_11ZON 01-10-2024 ------
39 TT-01 01-10-2024 ------
40 T1-03_13_11ZON 01-10-2024 ------
41 RENEWAL OF LICENCE 110-133 OF 1995 DT. 11.03.20 01-10-2024 ------
42 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 01-10-2024 View Document
43 T9-01D_5_11ZON 01-10-2024 ------
44 T9-06_2_11ZON 01-10-2024 ------
45 FF-900 01-10-2024 ------
46 ST-01 KHASRA MARKED SITE PLAN_5_11ZON 01-10-2024 ------
47 SC-14_15_11ZON 01-10-2024 ------
48 EL-16_2_11ZON 01-10-2024 ------
49 T9-01A_2_11ZON 01-10-2024 ------
50 EL-05_5_11ZON 01-10-2024 ------
51 SD-03 01-10-2024 ------
52 T7-04_38_11ZON 01-10-2024 ------
53 RENEWAL DLF5 LICENSES DT 01082024 01-10-2024 ------
54 T2-03_18_11ZON 01-10-2024 ------
55 T9-03_3_11ZON 01-10-2024 ------
56 BS-02 FLOOR PLAN-BASEMENT 2_2_11ZON 01-10-2024 ------
57 SD-03_10_11ZON 01-10-2024 ------
58 ST-02 SITE PLAN GREEN ARERA_7_11ZON 01-10-2024 ------
59 T1-02_12_11ZON 01-10-2024 ------
60 T8-04_42_11ZON 01-10-2024 ------
61 BS-07 AREA DIAGRAM BASEMENT -3_7_11ZON 01-10-2024 ------
62 BS-08 AREA DIAGRAM BASEMENT- 4_11ZON 01-10-2024 ------
63 T9-07_3_11ZON 01-10-2024 ------
64 SC-01 SECTION A-A (TOWER-1_9_11ZON 01-10-2024 ------
65 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 01-10-2024 View Document
66 T9-02_2_11ZON 01-10-2024 ------
67 T7-03_37_11ZON 01-10-2024 ------
68 T9-04_4_11ZON 01-10-2024 ------
69 SD-01 01-10-2024 ------
70 T4-02_25_11ZON 01-10-2024 ------
71 T9-02(1)_1_11ZON 01-10-2024 ------
72 EL-02 ELEVATION WEST (TOWE_2_11ZON 01-10-2024 ------
73 BS-06 AREA DIAGRAM BASEMENT -2_6_11ZON 01-10-2024 ------
74 T9-04A_5_11ZON 01-10-2024 ------
75 EL-09_2_11ZON 01-10-2024 ------
76 EL-11_4_11ZON 01-10-2024 ------
77 EL-13_6_11ZON 01-10-2024 ------
78 PHASING PLAN 01-10-2024 ------
79 DR-900 01-10-2024 ------
80 SC-02_10_11ZON 01-10-2024 ------
81 SC-11_12_11ZON 01-10-2024 ------
82 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 01-10-2024 View Document
83 TD-02_4_11ZON 01-10-2024 ------
84 FF-900_9_11ZON 01-10-2024 ------
85 T3-02_21_11ZON 01-10-2024 ------
86 T4-06_29_11ZON 01-10-2024 ------
87 T8-02_40_11ZON 01-10-2024 ------
88 SUPER IMPOSED KHASRA PLAN 01-10-2024 ------
89 EL-14_7_11ZON 01-10-2024 ------
90 SD-02 01-10-2024 ------
91 T3-03_22_11ZON 01-10-2024 ------
92 SC-05_13_11ZON 01-10-2024 ------
93 T4-04_27_11ZON 01-10-2024 ------
94 CA ESTIMATED 01-10-2024 ------
95 EL-07_7_11ZON 01-10-2024 ------
96 TD-01_3_11ZON 01-10-2024 ------
97 T8-01_39_11ZON 01-10-2024 ------
98 EL-01 ELEVATION NORTH (TOW_1_11ZON 01-10-2024 ------
99 EL-04_4_11ZON 01-10-2024 ------
100 EL-06_6_11ZON 01-10-2024 ------
101 EL-12_5_11ZON 01-10-2024 ------
102 PL-900_8_11ZON 01-10-2024 ------
103 SC-03_11_11ZON 01-10-2024 ------
104 SC-08_9_11ZON 01-10-2024 ------
105 SC-09_10_11ZON 01-10-2024 ------
106 SC-13_14_11ZON 01-10-2024 ------
107 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 01-10-2024 View Document
108 T4-01_24_11ZON 01-10-2024 ------
109 DR-901_8_11ZON 01-10-2024 ------
110 T4-05_28_11ZON 01-10-2024 ------
111 T4-07_30_11ZON 01-10-2024 ------