9810855773 (Number Shared by Promoter in Public)
malikassociates@gmail.com
http://www.manshagroup.in
XXXX898D
U70109HR2006PTC081926
MANSHA HERITAGE
VILLAGE KAMASHPUR SECTOR 83-84, SONIPAT
SONIPAT
SONIPAT
8447129022 (Number Shared by Promoter in Public)
malikassociates@gmal.com
HIMANSHU MALIK
8447129022 (Number Shared by Promoter in Public)
malikassociates@gmal.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
3953
07-02-2024
920000
PUNJAB NATIONAL BANK, SEC 15, FARIDABAD
HRERA Panchkula
21.13125 (Acre)
1.00 FOR PLOTTED AND 1.5 FOR COMMERCIAL
1.00
21.13125 (Acre)
LICENSE NO. 266 OF 2023 DATED 26.12.2023 (VALID UPTO 25.12.2028)
No
Address P-23, SECTOR 75 FARIDABAD.
Address JG-2/769A, MAIN OUTER RING ROAD, VIKASPURI DELHI
Address VILLAGE KAMASHPUR SECTOR 83-84 SONIPAT
Address VILLAGE KAMASHPUR SECTOR 83-84 SONIPAT
Address VILLAGE KAMASHPUR SECTOR 83-84 SONIPAT
Annexure-B- COLLABORATION AND GENERAL POWER OF ATTORNEY EXECUTED BETWEEN THE LAND OWNERS AND THE DEVELOPER.
YES, THE AGREEMENTS REGISTERED BEFORE THE GRANT OF LICENSE.
Yes
THE CLAUSES RELATED TO LAND OWNER'S SHARE ALLOCATED TO THEM HAVE BEEN ENTERED IN THE COLLABORATION AGREEMENT (GIST ENCLOSED). THE GPA IS HAVING POWERS TO EXECUTE THE CONVEYANCE/ SALE DEED IN FAVOUR OF PROSPECTIVE BUYERS. THE AGREEMENTS ARE REGISTERED AND IRREVOCABLE IN NATURE.
No
Yes
Yes
12011.21 Lakhs
3650.98 Lakhs
0.00 Lakhs
2228.84 Lakhs
6131.39 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
11.023
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
7.06706
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1.7469
6
GREEN BELTS
0.02547
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.10373
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0.41200
13
COMMERCIAL
0.4550
14
NURSERY
0.241
15
UGT
0.05029
16
MILK
0.00680
Total
21.13125
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVNL
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
305.42
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
195.45
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
210.37
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
314.65
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
255.36
AS PER PROJECT REPORT
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
124.8
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
822.79
AS PER PROJECT REPORT
26-12-2023 (date)
NA (date)
01-03-2024
25-12-2028
Plot Area(In Square Meter)
Number of plots in the project
442.598
7
377.933
4
259.243
4
210.291
55
242.683
13
214.038
15
240.368
12
242.933
7
174.742
21
433.302
10
208.389
7
172.471
3
252.898
2
204.299
5
226.906
5
243.054
6
50.056
21
53.965
24
1841.500
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.16
19.85
19.85
19.85
Water Supply System
5.86
12.70
12.70
12.70
Sewerage treatment & garbage disposal
7.66
16.60
16.60
16.60
Electricity Supply System
9.44
20.45
20.45
20.45
Storm Water Drainage
6.31
13.67
13.67
13.67
Parks and Playgrounds
3.74
8.11
8.11
8.11
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
24.68
53.48
53.48
53.48
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
19.85
19.85
19.85
19.85
Water Supply System
12.70
12.70
12.70
12.70
Sewerage treatment & garbage disposal
16.60
16.60
16.60
16.60
Electricity Supply System
20.45
20.45
20.45
20.45
Storm Water Drainage
13.67
13.67
13.67
13.67
Parks and Playgrounds
8.11
8.11
8.11
8.11
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
53.48
53.48
53.48
53.48
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
19.85
19.85
19.85
19.85
Water Supply System
12.70
12.70
12.70
12.70
Sewerage treatment & garbage disposal
16.60
16.60
16.60
16.60
Electricity Supply System
20.45
20.45
20.45
20.45
Storm Water Drainage
13.67
13.67
13.67
13.67
Parks and Playgrounds
8.11
8.11
8.11
8.11
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
53.48
53.48
53.48
53.48
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
19.85
19.85
19.85
18.33
Water Supply System
12.70
12.70
12.70
11.73
Sewerage treatment & garbage disposal
16.60
16.60
16.60
15.32
Electricity Supply System
20.45
20.45
20.45
18.88
Storm Water Drainage
13.67
13.67
13.67
12.62
Parks and Playgrounds
8.11
8.11
8.11
7.49
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
53.48
53.48
53.48
49.37
No
No
ICICI BANK LIMITED, SCO-45, SECTOR 79, FARIDABAD
777705981086
ICIC0007323
110229324
007323
Sh. Naresh Kumar Malik
R/o H. No. 706 Sec 14 Faridabad
Uploaded in Upload Section.
Yes
Yes
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 266 OF 2023
ALREADY BEEN OBTAINED
26-12-2023
II. DEMARCATION-CUM-ZONING PLAN
ALREADY BEEN OBTAINED
16-01-2024
Yes
Yes
THE PROVISIONS OF RERA RULES HAVE BEEN ENTERED INTO THE DRAFT AGREEMENT TO SELL.
MANSHA CITY SECTOR 9 PALWAL
8.76875
0
191
0
191
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
1427.77
1427.77
1427.77
Cost of the apartments
0
0
0
Cost of the infrastructure
611.91
611.91
611.91
Others costs
815.86
815.86
815.86
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
22-04-2022
22-04-2022
MANSHA VEGA STREET (SEC 82 FARIDABAD)
4.234
0
60
0
60
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4448.66
4448.66
0
Cost of the apartments
0
0
0
Cost of the infrastructure
739.20
739.20
0
Others costs
3709.46
3709.46
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
16-05-2026
16-05-2026
MANSHA OAKS (SEC 98 FARIDABAD)
7.1125
0
132
0
132
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
2934.41
2934.41
0
Cost of the apartments
0
0
0
Cost of the infrastructure
1143.32
1143.32
0
Others costs
1791.09
1791.09
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
15-04-2026
15-04-2026
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: