HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1383-2023
Submission Date : 08-12-2023 11:08:52 AM
Applicant Type : Company
Project Type: NEW




MODEL ECONOMIC TOWNSHIP LIMITED
3RD FLOOR, 77-B, IFFCO ROAD, SECTOR-18 GURUGRAM- 122015
1243527369
9910612499 (Number Shared by Promoter in Public)
shankar.mukkavilli@ril.com
http://www.modeleconomictownship.com
XXXX037Q
U70109HR2006PLC036416
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







MET CITY POCKET E
SECTOR-8, YAKUBPUR, MODEL ECONOMIC TOWNSHIP LIMITED
BADLI
JHAJJAR
01243527369
9998987100 (Number Shared by Promoter in Public)
rakesh.b.sinha@ril.com
RAKESH B SINHA
01243527369
9998987100 (Number Shared by Promoter in Public)
rakesh.b.sinha@ril.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
132857109-11-2023300000HDFC BANKHRERA Panchkula







14.194 (Acre)
2.64
2.64
1034.59375 (Acre)
16 of 2018, 11 of 2021 and 64 of 2022
Yes







2961 Lakhs
1381 Lakhs
0 Lakhs
1545 Lakhs
35 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD8.631
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS4.693
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.87
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total14.194




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSPWDYes
WATER SUPPLYDTCP HARYANAYes
ELECTRICITYUHBVNYes
SEWAGE DISPOSALDTCP HARYANAYes
STORM WATER DRAINAGEDTCP HARYANAYes
LAYOUT PLANDTCP HARYANAYes
LICENSE FOR PROJECTDTCP HARYANAYes
ZONING PLANDTCP HARYANAYes
SERVICE PLAN ESTIMATEDTCP HARYANAYes
ENVIROMENTAL CLEARANCEMOEFYes
CTE PERMISSIONHARYANA STATE POLLUTION CONTROL BOARDYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS478.86YET TO BE PREPARED
2WATER SUPPLY SYSTEM115.94YET TO BE PREPARED
3STORM WATER DRAINAGE181.60YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM528.43YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL93.92YET TO BE PREPARED
6STREET LIGHTING32.52YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15HORTICULTURE37.58YET TO BE PREPARED
16CONSULTANCY FEES GATE COMPLEX ETC75.81YET TO BE PREPARED


24-05-2022 (date)
NA (date)
10-12-2023
31-12-2028
Plot Area(In Square Meter)Number of plots in the project
150.0036
146.6510
144.0027
136.801
132.382
130.0368
126.971
120.501
109.48131
107.072
99.691
27.501


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System42
Sewerage treatment & garbage disposal0
Electricity Supply System44
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Consultancy Fees Gate complex etc0
Horticulture0
Street Lighting0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.15
Water Supply System2.64
Sewerage treatment & garbage disposal3.76
Electricity Supply System0
Storm Water Drainage7.26
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Horticulture0
Street Lighting0
Consultancy Fees Gate complex etc3.03

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements14.3721.5521.5523.94
Water Supply System1.483.223.223.80
Sewerage treatment & garbage disposal2.824.234.234.70
Electricity Supply System0021.1415.85
Storm Water Drainage5.458.178.179.08
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting001.300.98
Consultancy Fees Gate complex etc2.273.413.413.79
Horticulture0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.1528.7331.1331.13
Water Supply System2.644.965.545.54
Sewerage treatment & garbage disposal3.765.636.106.10
Electricity Supply System20.7120.7123.3518.06
Storm Water Drainage7.2610.9011.8011.80
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Horticulture0000
Street Lighting1.951.952.111.79
Consultancy Fees Gate complex etc3.034.554.934.93

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements28.7323.9423.9428.73
Water Supply System4.963.803.804.96
Sewerage treatment & garbage disposal5.634.704.705.63
Electricity Supply System39.6342.2742.2739.63
Storm Water Drainage10.909.089.0810.90
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Consultancy Fees Gate complex etc4.553.793.794.55
Street Lighting2.442.602.602.44
Horticulture03.763.763.76

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements19.1528.7328.7328.73
Water Supply System2.644.124.126.12
Sewerage treatment & garbage disposal3.766.576.576.57
Electricity Supply System34.3534.3539.6329.06
Storm Water Drainage7.2612.7112.7112.71
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Consultancy Fees Gate complex etc3.034.554.554.55
Street Lighting2.112.112.441.79
Horticulture3.013.763.763.76

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements23.9419.1514.370
Water Supply System3.802.6400
Sewerage treatment & garbage disposal4.703.7600
Electricity Supply System26.4221.1415.850
Storm Water Drainage9.087.2600
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Consultancy Fees Gate complex etc3.793.032.270
Street Lighting1.631.300.980
Horticulture3.013.012.253.76












Yes
No
ICICI BANK
777705001243
ICIC0004594
124229056
na
Mr. Sudhir Jain/ Mr. Ashish Jain/ Mr. Amit Kumar Garg C/o Model Economic Township Limited, 3rd Floor, 77-B, IFFCO Road, Sector-18, Gurugram-122015, Haryana
Attached











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLAN ALREADY BEEN OBTAINED24-05-2022








Yes


Yes









MET HABITAT, SECTOR-3 FOR 20.395 ACRES, VILLAGE DADRI TOE, TEHSIL BADLI, JHAJJAR
20.395
0
105
0
38
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
26354498.05531.94
Cost of the apartments000
Cost of the infrastructure25934451.54485.43
Others costs4246.5146.51


933.5728 Lakhs
7872.4272 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2028
31-03-2028




SECTOR 8, POCKET C AND D, 34.931 ACRES
34.931
0
540
0
504
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4152.067757.49826.16
Cost of the apartments000
Cost of the infrastructure4077.137670.36739.03
Others costs74.9387.1387.13


14877.06 Lakhs
24899.94 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2027
30-11-2027




INDUSTRIAL COLONY OVER 258.44 ACRES IN VILLAGE DADRI TOI AND BIR DADRI, DIST. JHAJJAR
258.44
0
121
0
83
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
14246.0826476.5123756.15
Cost of the apartments000
Cost of the infrastructure13251.8825036.0222320.66
Others costs994.21440.491435.49


37050.09 Lakhs
1077.91 Lakhs
0 Lakhs
0 Lakhs
No
30-09-2022
30-06-2024




INDUSTRIAL COLONY FOR 79.756 ACRES IN VILLAGE DADRI TOI, SONDHI AND YAKUBPUR, DIST. JHAJJAR
79.756
0
812
0
778
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
1323713034.3210044.64
Cost of the apartments000
Cost of the infrastructure1236312806.629821.84
Others costs874227.7222.8


28157.40 Lakhs
717.6 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2026
30-06-2026




INDUSTRIAL COLONY FOR 580.722 ACRES IN SECTOR- 4, 5, 7A, 7B, DADRI TOE, BIR DADRI
580.722
0
385
0
354
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
54813.0055228.1040176.72
Cost of the apartments000
Cost of the infrastructure53038.0054114.7638435.09
Others costs1775.001813.341741.63


110053.2 Lakhs
2719.8 Lakhs
0 Lakhs
0 Lakhs
No
11-05-2024
03-09-2025




INDUSTRIAL COLONY FOR 125.36 ACRES IN SECTOR – 2B, VILLAGE SHEOJIPURA, DIST. JHAJJAR
125.36
0
87
0
82
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
876512584.524458.54
Cost of the apartments000
Cost of the infrastructure838212215.224093.87
Others costs383369.31364.67


44657.17 Lakhs
5412.83 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2027
31-03-2027




INDUSTRIAL COLONY FOR 54.638 ACRES IN SECTOR – 8, POCKET J & K, VILLAGE YAKUBPUR & SONDHI, DIST. JHAJJAR
54.636
0
684
0
661
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6052.1210064.512749.51
Cost of the apartments000
Cost of the infrastructure5872.29874.052568.56
Others costs172.92190.47180.95


31709.94 Lakhs
9291.06 Lakhs
0 Lakhs
0 Lakhs
No
31-05-2027
31-05-2027




INDUSTRIAL COLONY FOR 34.931 ACRES IN SECTOR – 8, POCKET C & D, VILLAGE YAKUBPUR & SONDHI, DIST. JHAJJAR
34.931
0
540
0
504
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
4152.067757.49826.15
Cost of the apartments000
Cost of the infrastructure4077.137670.36739.03
Others costs74.9387.1387.13


14877.06 Lakhs
24899.94 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2027
30-11-2027




A COMMERCIAL PLOT (SUPERMART) OF 3.356 ACRES, PART OF INDUSTRIAL TOWNSHIP OF 1034.59375 ACRES IN VILLAGE YAKUBPUR, DIST. JHAJJAR
3.356
0
50
0
41
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
11241615.82200.15
Cost of the apartments000
Cost of the infrastructure11081603.01187.34
Others costs1612.8112.81


3733.316 Lakhs
657.684 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2027
30-06-2027




A COMMERCIAL PLOT (HIGHWAY MART) OF 4.96 ACRES, PART OF INDUSTRIAL TOWNSHIP OF 1034.59375 ACRES IN VILLAGE YAKUBPUR, DIST. JHAJJAR (AS ON 31 MAR, 2023)
4.96
0
69
0
38
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
11242434.61243.38
Cost of the apartments000
Cost of the infrastructure11082398.621217.65
Others costs1635.9825.73


2696.952 Lakhs
15.048 Lakhs
0 Lakhs
0 Lakhs
No
01-03-2024
01-03-2024




INDUSTRIAL RESIDENTIAL COLONY FOR 85.703 ACRES IN SECTOR 10A, VILLAGE SONDHI, DIST. JHAJJAR
63.703
0
52
0
32
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6535.8118992.071761.02
Cost of the apartments000
Cost of the infrastructure6366.128825.391594.34
Others costs169.69017166.68166.68


4955.512 Lakhs
11919.488 Lakhs
0 Lakhs
0 Lakhs
No
30-11-2027
30-11-2027




MET CITY POCKET SECTOR 2A, 49.584 ACRES IN SECTOR 2A, VILLAGE DADRI TOE, BIR DADRI AND SSHEOJIPURA, TEHSIL BADLI, DISTRICT JHAJJAR
49.584
0
523
0
14
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
64258294.84694.05
Cost of the apartments000
Cost of the infrastructure63058164.02569.23
Others costs120130.82130.82


113.8016 Lakhs
866.1984 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2028
31-12-2028










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNOT APPLICABLE
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSNOT APPLICABLE
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGENOT APPLICABLE
12LIFT DETAILSNOT APPLICABLE
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSNOT APPLICABLE
14DOORSNOT APPLICABLE
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSNOT APPLICABLE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE
20INTERNAL FINISHINGNOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN01-12-2023 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN01-12-2023 View Document
3COPY OF LICENSE ALONG WITH SCHEDULE OF LAND01-12-2023 View Document
4NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT04-12-2023 View Document
5DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.04-12-2023 View Document